Loading...
HomeMy WebLinkAboutWPO201900052-75389-Full Inspection ReportV NOTICE TO COMPLY Hand delivered Project: WP0201900052 BERKMAR DRIVE APARTMENTS - VSMP Operator/Contractor: Umer Hasan with Breeden Construction UPTOWN VILLAGE LLC Issued Date: 5/19/2022 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the referenced project and to immediately take corrective measures to address erosion and sediment control deficiencies on this property. This Notice to Comply is being issued because of the following deficiencies: Deficiency: Seed all denuded areas as required Corrective Action: Deficiency: Maintain controls as required Corrective Action: Deficiency: Overseed basin walls, remove any debris from within basin. Corrective Action: Deficiency: Seed as required Corrective Action: Deficiency: Maintain inlet protection as required, clean and or replace as needed, curb inlet and yard drain protection Corrective Action: Deficiency: Maintain a road cleaning schedule to prevent transfer Corrective Action: Deficiency: No wash facilities observed Corrective Action: Deficiency: Maintain as needed, Corrective Action: Deficiency: Traps present but not in use at time of visit, Corrective Action: Deficiency: Traps present but not in use at time of visit, trash across the site not contained as required Corrective Action: Deficiency: Maintain controls as required, Corrective Action: Unless subsequently amended in writing by this office, it is expected all of these corrective measures will be completed by. Reinspections as a result of this notice to verify corrective measures will incur a $170 fee for the first reinspection and $270 for each subsequent reinspection for single-family dwelling units (§ 17-207). Reinspections as a result of this notice to verify corrective measures will incur a $283 fee for the first reinspection and $383 for each subsequent reinspection for VESCP and VSMP permits (§ 17-207 and § 17-208). Failure to take effective corrective measures will result in a Stop Work Order upon reinspection. A 4% technology fee is due with each payment. County Inspector Name: Geoff Elsie County Inspector Phone Number: (434) 296-5832 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: BERKMAR DRIVE APARTMENTS - project/WPO Number: WP0201900052 VSMP Project Address: cprojectAddress» DEQ Permit Number (if VAR100044 applicable): Project Operator: Umer Hasan with Breeden Operator Telephone #: (804) 382-5645 Construction Project Contact: UPTOWN VILLAGE LLC Contact Telephone #: Contact E-Mail: Qualified Personnel (QP): Delton Banton with AG Dillard Inspector: Geoff Elsie Qualified Personnel (QP) «qualifiedPersonnel Email» Email: Disturbed Acreage: Weather (Wet/Dry/Rain): Single -Family: Inspection Date & Time: 5/9/2022 Stage of Construction: Grading Other Email: cOtherEmail» Re -Inspection: Yes Other Email: ((OtherEmail2o Bond Inspection: cbondinspection)) Other Email: «OtherEmail3» COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? No Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) (9VAC25-870-31 0)(Al b. Co. Code §17-300, 17-302) 2 A copy of the notice of coverage letter is posted conspicuously near the main entrance of the construction activity? (CGP Part II.C) Notice of the location of the SWPPP is posted near the site's entrance, if 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the 7 construction activity, including the function of the project? (CGP Part II A.1.d) Page 1 of 6 The SWPPP includes a legible site plan identifying all appropriate 8 measures and that includes the locations of support activities and the onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) 9 The SWPPP contains the name, phone number and qualifications of "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III K? (CGP Part II A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part II A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? No Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are identified? (CGP Part II B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part II B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? (CGP Part II B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and measures taken to prevent the recurrence of any prohibited discharge? (CGP Part II B.4(e-f)) (9VAC25-870-54.G) 24 Amendments, modifications, or updates to the SWPPP are signed in accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? No Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) Page 2 of 6 26 Inspection reports are completed and signed in accordance with CGP Part II F (3-4)? (CGP Part II F (3-4)) 27 Corrective actions are taken consistent with the requirements of the CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the yes plan? Sequencing of the project is implemented in accordance with the No Maintain perimeter controls, as needed, 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization Seed all denuded areas as required been stabilized, and have stabilization requirements for impaired waters, 30 approved TMDL(s), pollutants of concern and exceptional waters, when No applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected yes 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, NIA 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land NO Maintain controls as required, 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? N/A 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are sediment traps and basins installed in accordance with MS-6 and the No Overseed basin walls, remove any debris from within 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II basin. A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct No Seed as required 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate yes 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? yes 38 (9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? Maintain inlet protection as required, clean and or 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- No replace as needed, curb inlet and yard drain 54.13) protection Are stormwater conveyance channels adequately stabilized with channel N/A 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel N/A 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where N/A 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC N/A 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with N/A 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 45 Are soil and mud kept off paved or public roads to minimize the transport No Maintain a road cleaning schedule to prevent transfer of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) Page 3 of 6 (9VAC25-870-54. B ) Have all temporary control structures that are no longer needed been 46 removed and disturbed soil resulting from their removal permanently N/A stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately 47 protected from erosion, sediment and damage in accordance with the N/A standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? N/A (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, Yes 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels Yes 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the Yes clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle No No wash facilities observed 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) 53 Concrete wash water is directed into a leak -proof container or leak -proof Yes Maintain as needed, settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from No Traps present but not in use at time of visit, trash 54 storage, handling, and disposal of construction products, materials, and across the site not contained as required wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other Yes 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential Yes 56 pollutant -generating activities not addressed above, when applicable? (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 6 Notes: CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT REQUEST FOR CORRECTIVE ACTION Project Name: Permit Number (if applicable): Date: Regulatory Occurrence Observation/Recommended Corrective Action Checklist # Citation/Legal requirement' Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: 1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Page 5 of 6 Corrective Action Deadline: Re -Inspection Date: Comments: The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for ensuring compliance on the above project. Page 6 of 6 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 30 (9VAC 25-840-40.1) Seed all denuded areas as (9VAC25-870-54.B) required (9VAC25-880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part 11 A.2.c (8)) (CGP 11 E(1-2)) 33 (9VAC 25-840-40.4) Maintain controls as required (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B) 35 (9VAC 25-840-40.6) Overseed basin walls, remove (CGP Part 11 A.2.c (9)) any debris from within basin. (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B) 36 (9VAC 25-840-40.7) Seed as required (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B) 39 (9VAC 25-840-40.10) Maintain inlet protection as (CGP Part 11 A.2(c)) required, clean and or replace (CGP 11 E(1-2)) as needed, curb inlet and yard (9VAC25-870-54.B) drain protection 45 (9VAC 25-840-40.17) Maintain a road cleaning (CGP Part 11 A.2(c)) schedule to prevent transfer (CGP 11 E(1-2)) (9VAC25-870-54.B) 52 (CGP Part 11 A.4.e(4)) No wash facilities observed (9VAC25-870-56) 53 (CGP Part 11 A.4.e(5)) Maintain as needed, (9VAC25-870-56) 54 (CGP Part 11 A.4.e(6)) Traps present but not in use (9VAC25-870-56) at time of visit, 54 (CGP Part 11 A.4.e(6)) Traps present but not in use (9VAC25-870-56) at time of visit, trash across the site not contained as required 33 (9VAC 25-840-40.4) Maintain controls as required, (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B) Recommended 5/24/2022 Corrective Action Deadline: Targeted Re- 5/24/2022 Inspection Date: Comments: Perimeter silt fence must be maintained, add silt fence internally to reduce sediment loss from around buildings during construction, keep construction debris xcontained to proper containers, maintain all inlets, clean sediment from roads, maintain wash rack for use when needed, stabilize all denuded areas that are not within a reasonable work envelope around buildings, stabilize basin and remove stone pile from within the basin, *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 2 Photos for Item 4 Photo Description: Photos for Item 10 Photo Description: Photos for Item 29 Time Photo_20220509_101313.jpg.jpg 1.04MB Photo Description: Example of repairs needed Photos for Item 30 Time Photo_20220509_102348.jpg.jpg 411.87KB Photo Description: Example of denuded area in need of stabilizing Photos for Item 35 TimePhoto_20220509_101911.jpg.jpg 692.94KB Photo Description: Stablize basin walls and remove stone piles from within the basin Photos for Item 36 TimePhoto_20220509_101310.jpg.jpg 937.62KB Photo Description: Maintain proper siltfence and seed slope Photos for Item 39 TimePhoto_20220509_101146.jpg.jpg 662.33KB Photo Description: Example of improper inlet protection Photos for Item 45 Time Photo_20220509_101835.jpg.jpg 896.79KB a Photo Description: Example of sediment on road, improper inlet control and noncompliance with construction debris Photos for Item 54 TimePhoto_20220509_101753.jpg.jpg 1.08MB Photo Description: Trash not contained VIM County Inspector COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Inspection Date: 5/19/2022