VSMP Permit Plan Review
Troxell Poultry House
WPO202100033
401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
Telephone: 434- 29 6 - 5 832
WWW.ALBEMARLE.ORG
Brian Kinzie [Brian@blackwellengineering.com]
Broc Troxell [troxellfarms@gmail.com]
28 May 2021
07 July 2021
12 Aug 2021
07 Sept 2021
29 June 2021
30 July 2021
26 Aug 2021
06 Oct 2021
02 June 2022
Emily Cox
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is approved. The
rationale is given in the comments below. The VSMP application content requirements can be
found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP
must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please use Albemarle County SWPPP template:
https://www.a I bema rle.org/home/showpu bl i sheddocu ment/ 166/63720231032753000
0 Rev. 1: Comment addressed.
2. Ensure registration statement and section 9, signed certification are signed. Rev. 1:
Comment addressed.
3. Rev. 1: Registration statement must be signed by the operator. Either the contractor
must sign it, or the owner who signed it must be listed as the operator. Rev. 2: Comment
not addressed. Rev. 2: Comment addressed.
4. Rev. 1: Please submit a full SWPPP packet including the latest plans, registration
statement, signed certification, etc. Ensure the projected start date is updated on the
registration statement as it has already passed. Rev. 4: Addressed.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Please provide a PPP. See 17-404 for required contents:
https://mccl i bra ry. blob.core.usgovclouda pi. net/codecontent/ 12230/385730/Cha pter•` 2
017%20Water%20Protection.pdf Rev. 1: Comment addressed.
Engineering Review Comments
Page 2 of 5
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is approved.
i. A stormwater management maintenance agreement must be recorded before this plan
can be approved. Please contact Ana Kilmer [akilmer@albemarle.org 434-296-5832
ext.3246] to complete this process. Rev. 1: Comment not addressed. Rev. 2: Comment
addressed.
2. Since forest & open space is being used in the VRRM, this area must be shown on a plat
labeled as SWM forest & open space and recorded with a deed before this plan can be
approved. There must also be an easement labeled SWM Facility easement around the
proposed pond and its outfall and access area. The easement plat application can be
found here: https://www.albemarle.org/home/showdocument?id=1052 Rev. 1:
Comment not addressed. Rev. 2: Comment not addressed. Rev. 3: Comment not
addressed. Rev. 4: Addressed.
3. Please add the following note to this plan and the plat mentioned in the above comment:
"The SWM Forest and Open Space Easement is subject to the guidance set forth by DEQ
in the Virginia Stormwater Management Program. The areas will remain undisturbed in a
natural, vegetated state, except for activities as approved by the local program authority,
such as forest management, control of invasive species, replanting and revegetating,
passive recreation (e.g., trails), and limited bush hogging to maintain desired vegetative
community (but no more than four times a year)." Rev. 1: Comment not addressed.
Response letter said it was on sheet 2, but it was not evident. Rev. 2: Comment
addressed.
4. Please clarify where the 17.5 acres of forest & open space is located. The legend appear
incorrect on sheet 2. Rev. 1: Comment addressed, however, please label it as SWM
forest & open space easement. Rev. 2: Comment addressed.
5. Please add a title to sheet 1 and include WPO202100033 in the title. Rev. 1: Comment
addressed.
6. Professional seal should be signed and dated. Rev. 1: Comment addressed.
7. Please provide date the topographic information was obtained/survey was completed.
Rev. 1: Comment addressed.
8. Please show the WPO buffer and any critical slopes from county GIS on all applicable
sheets. Rev. 1: Comment addressed.
9. It would be helpful to have a grading and layout sheet separate from the E&S sheet. Rev.
1: Comment addressed.
10. Please double check all grading and contour labels. The northern end of the site appears
to have 1 ft contours tying in to 2 ft contours. Also, the proposed contours do not match
the labels on the northwest side of the site. Rev. 1: Comment addressed.
12. Please label contour elevations on all applicable sheets, especially the drainage divides.
Rev. 1: Comment addressed.
13. Please list the required maintenance for the proposed SWM pond on the plans. Rev. 1:
Comment addressed.
14. Please provide the following as -built check list on the plans:
https://www.albemarle.org/home/showpublisheddocument/3381/6373275105367000
Engineering Review Comments
Page 3 of 5
00 Rev. 1: Comment addresse
At the point where water leaves the site, it meets energy balancve as per 9VAC25-870-66.B3. At
the the point where the two streams converge (Point A), the pre and post developed conditions
have identical Ws but the developed site has a lower peak flow for both the 2 and 10 year storm
events, meeting 9VAC25-870-66.2B.
16. Please provide a detail for the emergency spillway for the permanent dry pond. Rev. 1:
Comment addressed.
17. Per 9VAC25-870-66-B, concentrated stormwater flow shall be released into a
stormwater conveyance system. The currently proposed outfall does not appear to go
into a conveyance system or channel. Rev. 1: Is this Ditch 1 in the calculations? Please
clarify and ensure plan view matches calculations. Plan view said swale cross section.
DI's and culverts were clearly labeled. Also, plan view contours do not appear to show a
v-ditch or swale as shown in calculations (or a channel). Contours below pipe outfall are
shown below. A ditch or swale is not evident. If necessary, a site visit can be completed
to verify the ditch/swale:
-' 1
-;=-� Rev. 2: Comment addressed.
18. Rev. 1: Existing drainage area appears too large. It should only be the DA to the
proposed outfall point Rev. 2: Comment addressed.
Rev. 2: Level spreader design and detail was not provided on Sheet 4. It should be
shown to scale on all sheets. It appears to be too steep downstream. It must meet this
specification: https://swbmpvwrrc.wp.prod.es.cloud.vtedu/wp-
content/uploads/2018/07/BMP Spec No 2 SHEET FLOW.pdf Rev. 3: Comment
addressed.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved.
1. Please provide the paved CE with wash rack detail from the Albemarle County Design
Standards Manual (page 8): https://www.albemarle.org/Home/ShowDocument?id=270
Rev. 1: Comment addressed.
Engineering Review Comments
Page 4 of 5
2. Please show dust control as an E&S measure. Rev. 1: Comment addressed.
3. Please show a stockpile, staging and parking area. Rev. 1: Staging and parking area
should have perimeter controls.
STOCKPILE LOCATION
STAGING & PARKING AREA
�I
1Rev. 2: Comment
addressed.
4. Please provide adequate perimeter control, including silt fence around the southern and
eastern ends of the project. Rev. 1: See comment above. Rev. 2: Comment addressed.
5. Ensure Albemarle County Standard Notes are on the plan:
httr)s://www.a I bema rle.org/home/showr)u bl i sheddocu ment/ 1262/6373213252553300
00 Rev. 1: Comment addressed.
6. Provide details for the trash rack and anti -seep collars. Rev. 1: Ensure trash rack detail
specifies the anti -vortex. Rev. 2: Comment addressed.
7. Please clearly show the drainage area for the sediment basin as well as the required dry
and wet volume storages. Rev. 1: Volumes were not evident on the plan, elevations were
shown. Also show the freeboard on the detail as well as the embankment top width.
Rev. 2: Comment addressed.
8. Please add a note to the plans that County Inspector may require additional measures as
needed on site. Rev. 1: Comment addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments
have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete
permit package with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a
meeting to discuss this review.
Process:
After approval, erosion and sediment control and stormwater management improvements must
be bonded. The bonding process begins when the plan is approved, and the applicant submits a
bond estimate request form and fee to the Department of Community Development. A plan
reviewer will prepare estimates and check parcel and easement information based on the
approved plans. The County's Management Analyst will prepare bond agreement forms, which
will need to be completed by the owner and submitted along with cash, certificates or sureties
for the amounts specified. The agreements will need to be approved and signed by the County
Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and
forms.
Engineering Review Comments
Page 5 of 5
Stormwater Management Facilities Maintenance agreements will also need to be completed and
recorded. The County's Management Analyst or other staff will prepare the forms and check for
ownership and signature information. The completed forms will need to be submitted to the
County, who will record the agreement.
After bonding and agreements are complete, county staff enters project information in a DEQ
database for state application processing, if a DEQ permit is required. DEQ reviews the
application information based on local VSMP authority approval. At this time, the DEQ portion of
the application fees will need to be paid directly to the state. For fastest processing, this is done
electronically with the emails provided on the application. DEQ should notify applicants with
instructions on how to pay fees. When DEQ approves the application, they will issue a permit
coverage letter, which must be posted at the construction site.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction
conference. Applicants must complete the request for a pre -construction conference form and
pay the remainder of the application fee. The form identifies the contractor and responsible land
disturber, and the fee remaining to be paid. This will be checked by county staff, and upon
approval, a pre -construction conference will be scheduled with the County inspector. At the pre -
construction conference, should everything proceed satisfactorily, a joint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
httos://www.al bemarle.org/government/commu nity-development/aooly-for/engineering-aool ications