Loading...
HomeMy WebLinkAboutWPO201700020 Correspondence 2022-06-06® COLLINS ENGINEERING 200 GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902 ( 434.293.3719 PH 434.293.2813 FX www.colfns-engineering.com June 3, 2022 Matt Wentland, PE Department of Community Development 401 McIntire Road Charlottesville, VA 22902 RE: Foothill Crossing II- VSMP Plan Amendment #6 (WPO 201700020) Thank you for the comments dated May 25th, 2022 on the above referenced project. Below are detailed responses to the remaining comments. A. Stormwater Pollution Prevention Plan (SWPPP) 1. This comment is acknowledged. The SWPPP will be updated once the plan is approved. B. Pollution Prevention Plan (PPP) 2. This comment is acknowledged. The PPP will be updated once the plan is approved. C. Stormwater Management Plan (SWMP) 1. Comment previously addressed 2. Comment previously addressed 3. Comment previously addressed 4. Comment previously addressed S. Comment previously addressed 6. Comment previously addressed 7. A mitigation (sheet 20) has bee included with this submission for the impacts associated with the private sanitary sewer laterals. 8. The sanitary sewer laterals have been relocated outside of the outer 50' buffer area. The impacts to the outer 50' buffer for the laterals have been added and shown on the mitigation plan, sheet 20. The E&S plan has bee updated accordingly as well. D. Erosion & Sediment Control Plan (ESCP) 1. The previous ESC plan found to be acceptable has not been modified with this resubmittal. Should you have any questions during your review and approval of this plan, please feel free to contact Graham Murray at graham@collins-engineering.com. Sincerely, Graham Murray, PE