VSMP
1. SWPPP was not provided. Please provide a SWPPP. Use the following template:
https://www. a I bemarle. org/home/showpublishedd ocumenV l 66/63720231032753000
0 Rev. 1: The registration statement and section 9, signed certification, must be signed
before the plan can be approved. Approved plans must be inserted at appropriate
locations as well. Rev. 2: Comment not addressed.
Response: The SWPPP has been included in this resubmittal and includes the signed registration
statement as well as the inserted plans.
2. Ensure the PPP [Sheet CE-101] is inserted in the SWPPP. Rev. 1: Comment not
addressed. Rev. 2: Comment not addressed.
Response: The SWPPP has been included in this resubmittal and includes the PPP sheet as requested.
3. Stormwater management agreement must be recorded before this plan can be approved.
Please contact Ana Kilmer [akilmer@albemarle.org 434-296-5832 ext3246] to complete
this process. Rev. 1: Comment not addressed. Rev. 2: Comment not addressed.
Response: The stormwater management agreement will be recorded prior to plan approval.
4. Nutrient credits must be purchased before this plan can be approved. Please contact Ana Kilmer
[akilmer@albemarle.org 434-296-5832 ext3246] to complete this process. Rev. 1:
Comment not addressed. Rev. 2: Comment not addressed.
Response: Nutrient credits have been purchased as requested. Attached in this resubmittal is the signed
Bill of Sale and signed Sales Agreement. The files have been sent to Ana Kilmer on 7/13/2022.
5. Per county code 18-4.12.17.a, vehicle access aisles that are not adjacent to parking
spaces, shall not exceed a grade of ten percent. The entrance off Greenbrier Dr.
appears to exceed 10%. Rev. 1: Comment not addressed. Special exception
(SE202100048) is under review. Rev. 2: Comment not addressed.
Response: SE202100048 has been approved on February 16, 2022 and is included in this resubmittal.
6. Rev. 2: [Sheet CG-203] You must analyze the area that goes to the existing DI-213 for channel and flood
protection. This is labeled as DA- off -site.
Response: Through coordination with Emily Cox throughout the month of March and April of 2022, the
stormwater quantity analysis has been redesigned as requested.
7. Please show permission for the offsite work. Sheet CE-501 mentions an easement. This
plan cannot be approved until that is provided. Rev. 1: Comment not addressed. Rev. 2:
Comment not addressed.
Response: The REA has been recorded and has been included in this resubmittal as requested. The REA
was sent to Ana Kilmer on 7/13/2022.