HomeMy WebLinkAboutWPO201900010-40219-Full Inspection ReportWRITTEN WARNING Hand delivered Project: WP0201900010 EARLYSVILLE SUBDIVISION - VSMP Operator/Contractor: LUKE KITELINGER BELLA SIGNATURE HOMES LLC Issued Date:7/19/2022 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 (434)296-5832 This is your Written Warning in accordance with § 17-900 of the Water Protection Ordinance of Albemarle County and Section 62.1-44.15:37 of the Virginia Stormwater Management Act. This Written Warning is being issued because of the following deficiencies: Deficiency: GCL posted not in SWPPP book Corrective Action: Place Gen Permit coverage letter in book Deficiency: Qualified site inspector not listed Corrective Action: List site inspector info Deficiency: PPP not updated. Inspections have not been maintained Corrective Action: Resume regular site inspections and document in SWPPP book Deficiency: Delegation of Authority has not been filled out Corrective Action: Complete Delegation information Deficiency: Slopes do not have a established vegetative cover Corrective Action: Apply slope stabilization and mat. Amend soil to ensure vegetation establishes Deficiency: Level spreader has not been installed. Dry basin not maintained Corrective Action: Cut overgrowth on dry basin to observe functionality Deficiency: Perimeter SF overwhelmed with clean stormwater Corrective Action: Observed the scouring of leaves of area. Reseed and mulch repair SF and rock checks. Install level spreader Deficiency: inlet protection missing Corrective Action: Reinstall inlet protections Unless subsequently amended in writing by this office, it is expected all corrective measures will be completed by Failure to comply by the required date may subject the owner to penalties and remedies as listed under § 17-900 et -al of the Water Protection Ordinance of the Albemarle County Code. Should you have a legitimate reason you cannot complete your required corrections by the above given date, you must immediately contact your erosion control inspector. Unless you have contacted the inspector and agreed to alternative arrangements, all compliance work is expected to be completed by the above date. County Inspector Name: Jonney Otto County Inspector Phone Number: (434) 296-5832 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: EARLYSVILLE SUBDIVISION - VSMP Project/WPO Number: WP0201900010 Project Address: DEQ Permit Number (if applicable): VAR100046 Project Operator: LUKE KITELINGER Operator Telephone #: Project Contact: BELLA SIGNATURE HOMES LLC Contact Telephone #: (434) 960-3085 Contact E-Mail: kitelinger1@yahoo.com Qualified Personnel (QP): Brook R. Wood - Digs Inc Inspector: Jonney Otto Qualified Personnel (QP) Email: Disturbed Acreage: Weather (Wet/Dry/Rain): Cloudy Single -Family: Inspection Date & Time: 7/19/2022 10:00:00 AM Stage of Construction: Final Stabilization Other Email: Re -Inspection: No Other Email: Bond Inspection: No Other Email: COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? No Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) (9VAC25-870-31 0)(Al b. Co. Code §17-300, 17-302) 2 A copy of the notice of coverage letter is posted conspicuously near the main entrance of the construction activity? (CGP Part II.C) Notice of the location of the SWPPP is posted near the site's entrance, if 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? Yes Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Yes Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? Yes (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage No letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the Yes 7 construction activity, including the function of the project? (CGP Part II A.1.d) 8 The SWPPP includes a legible site plan identifying all appropriate No measures and that includes the locations of support activities and the Page 1 of 6 onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) 9 The SWPPP contains the name, phone number and qualifications of No "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? Yes (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that Yes ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria ILB ❑ II.0 ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- No 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of Yes 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III No K? (CGP Part II A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part N/A II A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? No Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters? (CGP Part II B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are identified? (CGP Part II B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part II B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? (CGP Part II B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and measures taken to prevent the recurrence of any prohibited discharge? (CGP Part II B.4(e-f)) (9VAC25-870-54.G) 24 mendments, modifications, or updates to the SWPPP are signed in accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? No Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) Page 2 of 6 26 Inspection reports are completed and signed in accordance with CGP Part II F (3-4)? (CGP Part II F (3-4)) 27 Corrective actions are taken consistent with the requirements of the CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the Yes plan? Sequencing of the project is implemented in accordance with the Yes 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization been stabilized, and have stabilization requirements for impaired waters, 30 approved TMDL(s), pollutants of concern and exceptional waters, when Yes applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected NIA 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, N/A 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land Yes 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? Yes 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are sediment traps and basins installed in accordance with MS-6 and the N/A 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct No Slopes do not have a established vegetative cover 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate No Perimeter SF overwhelmed with clean stormwater 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? N/A 38 (9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? No Reinstall inlet protection 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are stormwater conveyance channels adequately stabilized with channel No Sediment observed in roadway ditchline 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel N/A 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where N/A 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC N/A 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with N/A 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are soil and mud kept off paved or public roads to minimize the transport Yes 45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Page 3 of 6 Have all temporary control structures that are no longer needed been Level spreader has not been installed. Dry basin not 46 removed and disturbed soil resulting from their removal permanently No maintained stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately 47 protected from erosion, sediment and damage in accordance with the Yes standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? N/A (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? No Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) 53 Concrete wash water is directed into a leak -proof container or leak -proof settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from 54 storage, handling, and disposal of construction products, materials, and wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential 56 pollutant -generating activities not addressed above, when applicable? (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 6 Notes: CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT REQUEST FOR CORRECTIVE ACTION Project Name: Permit Number (if applicable): Date: Regulatory Occurrence Observation/Recommended Corrective Action Checklist # Citation/Legal requirement' Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: 1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Page 5 of 6 Corrective Action Deadline: Re -Inspection Date: Comments: The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for ensuring compliance on the above project. Page 6 of 6 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 6 (CGP Part II A.1.b & GCL posted not in SWPPP Place Gen Permit coverage c) book letter in book 9 (CGP Part II A.6) Qualified site inspector not List site inspector info listed 12 (9VAC25-870-54.D) PPP not updated. Inspections Resume regular site (CGP Part II.A.4) have not been maintained inspections and document in SWPPP book 14 (CGP Part II A.7) Delegation of Authority has Complete Delegation not been filled out information 30 (9VAC 25-840-40.1) Slopes do not have a Apply slope stabilization and (9VAC25-870-54.B) established vegetative cover mat. Amend soil to ensure (9VAC25-880-60) (CGP vegetation establishes Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) 46 (9VAC 25-840-40.18) Level spreader has not been Cut overgrowth on dry basin (CGP Part II A.2(c)) installed. Dry basin not to observe functionality (CGP II E(1-2)) maintained (9VAC25-870-54. B ) 37 (9VAC 25-840-40.8) Perimeter SF overwhelmed Observed the scouring of (CGP Part II A.2(c)) with clean stormwater leaves of area. Reseed and (CGP II E(1-2)) mulch repair SF and rock (9VAC25-870-54.B) checks. Install level spreader 39 (9VAC 25-840-40.10) inlet protection missing Reinstall inlet protections (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Recommended Corrective Action Deadline: Targeted Re- 7/29/2022 Inspection Date: Comments: After a DEQ site inspection a corrective action list was created. Address the corrections listed and document the items corrected and stabilization dates in the site SWPPP book. - update PPP map, document MSDS clean up & sources, insert a major grading sheet, resume regular SWPPP inspections - complete Delegation form - insert GCL in SWPPP book - overseed slopes that have not established a vegetative cover amend soil if necessary - Observed the scouring of leaves off site. Reseed and mulch scoured. area, repair SF and rock checks. Install level spreader - install inlet protection for all installed inlets - repair all eroding stormwater channels, removing sediment build up and establish stabilization - Cut overgrowth on dry basin to observe functionality A Warning has been issued with a reinspection date set for 7/29/22 Inspection Report *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 2 Photos for Item 4 Photo Description: Photos for Item 10 Photo Description: Photos for Item 36 Time P hoto2022071 91 03502.j pg.jpg 1.2M B Photo Description: Apply slope stabilization and mat. Amend soil to ensure vegetation establishes Photos for Item 37 Time Photo_20220719_105023.jpg.jpg 970.32KB Photo Description: Observed the scouring of leaves of area. Reseed and mulch repair SF and rock checks. Install level spreader Photos for Item 40 TimePhoto_20220719_103649.jpg.jpg 1.09MB Photo Description: Remove sediment build up and reinstall a vegetative cover utilizing matting Photos for Item 46 Time Photo_20220719_095152.jpg.jpg 1.14MB Photo Description: Cut overgrowth on dry basin to observe functionality Other Photos Photo Description: COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Inspection Date: 7/20/2022 County Inspector