HomeMy WebLinkAboutWPO202000034-88207-Full Inspection ReportCOUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
(434)296-5832
WRITTEN WARNING
Hand delivered
Project: WP0202000034
BELVEDERE - PHASE 5 - VSMP - DIGITAL
Operator/Contractor: AG Dillard, Inc.
BELVEDERE LAND HOLDINGS LLC
Issued Date:7/21/2022
This is your Written Warning in accordance with § 17-900 of the Water Protection Ordinance of
Albemarle County and Section 62.1-44.15:37 of the Virginia Stormwater Management Act.
This Written Warning is being issued because of the following deficiencies:
Deficiency: Apply stabilization on denuded and areas that have not established a vegetative cover
Corrective Action: Overseed areas that haven't established
Deficiency: Established vegetative cover not observed
Corrective Action: Apply seed and mulch to establish a vegetative cover
Deficiency: Missing curb inlet protections
Corrective Action: Install CIP
Deficiency: DD and conveyance channels not stabilized
Corrective Action: Establish a vegetative cover on DD and conveyance channels
Deficiency: SB rock cropping may need to have a clay lining installed prior to Stormwater conversion
Corrective Action: Engineer needs to confirm SB 1 rock cropping and any adjustments that may be
needed
Deficiency: damaged areas of SF observed and straw bails installed at the Fire rd.
Corrective Action: Repair damaged areas of SF and replace straw bails with rock checks on the Fire
road.
Deficiency: SF remaining after grading renders it useless
Corrective Action: Remove remaining SF once it has been graded out of use
Unless subsequently amended in writing by this office, it is expected all corrective
measures will be completed by
Failure to comply by the required date may subject the owner to penalties and remedies as listed
under § 17-900 et -al of the Water Protection Ordinance of the Albemarle County Code.
Should you have a legitimate reason you cannot complete your required corrections by the
above given date, you must immediately contact your erosion control inspector. Unless you
have contacted the inspector and agreed to alternative arrangements, all compliance work is
expected to be completed by the above date.
County Inspector Name: Jonney Otto
County Inspector Phone Number: (434) 296-5832
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
BELVEDERE - PHASE 5 - VSMP -
DIGITAL
Project/WPO Number:
WP0202000034
Project Address:
DEQ Permit Number (if
applicable):
VAR100868
Project Operator:
AG Dillard, Inc.
Operator Telephone #:
(434) 977-3750
Project Contact:
BELVEDERE LAND HOLDINGS LLC
Contact Telephone #:
(434) 220-7701
Contact E-Mail:
SKROHN@RESORTSCOMPANIES.COM
Qualified Personnel (QP):
DJ Banton - AG Dillard, Inc
Inspector:
Jonney Otto
Qualified Personnel (QP)
Email:
Disturbed Acreage:
Weather (Wet/Dry/Rain):
Clear, hot
Single -Family:
Inspection Date & Time:
7/21/2022 1:00:00 PM
Stage of Construction: Grading
Other Email:
Re -Inspection: No
Other Email:
Bond Inspection: No
Other Email:
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? No
Comments/Description
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
Page 1 of 6
The SWPPP includes a legible site plan identifying all appropriate
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
K? (CGP Part II A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? No
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part II B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
(CGP Part II B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part II B.4(e-f)) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? No
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
Page 2 of 6
26
Inspection reports are completed and signed in accordance with CGP
Part II F (3-4)? (CGP Part II F (3-4))
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
yes
plan?
Sequencing of the project is implemented in accordance with the
yes
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
Apply stabilization on denuded and areas that have
been stabilized, and have stabilization requirements for impaired waters,
not established a vegetative cover
30
approved TMDL(s), pollutants of concern and exceptional waters, when
No
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
N/A
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
No
Established vegetative cover not observed
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
yes
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
N/A
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
N/A
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
yes
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
N/A
38
(9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
No
Missing curb inlet protections
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
No
DID and conveyance channels not stabilized
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
N/A
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
N/A
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
N/A
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
N/A
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
yes
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Page 3 of 6
Have all temporary control structures that are no longer needed been
Remove remaining SF once it has been graded out of
46
removed and disturbed soil resulting from their removal permanently
No
use
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
Repair damaged areas of SF and replace straw bails
47
protected from erosion, sediment and damage in accordance with the
Yes
with rock checks on the Fire road.
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
Permanent control measures included in the SWPPP are in place?
N/A
SB rock cropping may need to have a clay lining
48
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
installed prior to Stormwater conversion
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
N/A
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
N/A
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
Construction debris observed, dumpster not covered
51
detergents, and wash water from construction materials, including the
No
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
Yes
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
Yes
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
Yes
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
N/A
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
N/A
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 6
Notes:
CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT
REQUEST FOR CORRECTIVE ACTION
Project Name: Permit Number (if applicable): Date:
Regulatory
Occurrence
Observation/Recommended Corrective Action
Checklist #
Citation/Legal
requirement'
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and
Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Construction Activities (9VAC25-880).
Page 5 of 6
Corrective Action Deadline:
Re -Inspection Date:
Comments:
The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently
constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for
ensuring compliance on the above project.
Page 6 of 6
Construction General Permit Site Inspection Report
Request for Correction Action
Check
Regulatory Citation/Legal
Occur.
Observation
Recommended Corrective
List #
Requirement*
Action
30
(9VAC 25-840-40.1)
Apply stabilization on
Overseed areas that haven't
(9VAC25-870-54.B)
denuded and areas that have
established
(9VAC25-880-60) (CGP
not established a vegetative
Part I F.1(a)) (CGP Part
cover
11 A.5.b(1)) (CGP Part 11
A.2.c (8)) (CGP 11 E(1-2))
32
(9VAC 25-840-40.3)
Established vegetative cover
Apply seed and mulch to
(CGP Part 11 A.2(c))
not observed
establish a vegetative cover
(CGP 11 E(1-2))
(9VAC25-870-54. B )
39
(9VAC 25-840-40.10)
Missing curb inlet protections
Install CIP
(CGP Part 11 A.2(c))
(CGP 11 E(1-2))
(9VAC25-870-54. B )
40
(9VAC 25-840-40.11)
DID and conveyance channels
Establish a vegetative cover
(CGP Part 11 A.2(c))
not stabilized
on DID and conveyance
(CGP 11 E(1-2))
channels
(9VAC25-870-54. B )
48
(9VAC25-870-54.C)
SIB rock cropping may need to
Engineer needs to confirm
(9VAC25-880-60) (CGP
have a clay lining installed
SB1 rock cropping and any
Part 11 F.1(a))
prior to Stormwater
adjustments that may be
conversion
needed
47
(9VAC 25-840-40.19(a-
damaged areas of SF
Repair damaged areas of SF
n))
observed and straw bails
and replace straw bails with
installed at the Fire rd.
rock checks on the Fire road.
46
(9VAC 25-840-40.18)
SF remaining after grading
Remove remaining SF once it
(CGP Part 11 A.2(c))
renders it useless
has been graded out of use
(CGP 11 E(1-2))
(9VAC25-870-54. B )
Recommended
Corrective Action
Deadline:
Targeted Re- 7/29/2022
Inspection Date:
Comments: After a DEQ site inspection on 7/14/22 a non -compliant E&S measures corrective
action list was created.
Address the corrections listed and document the items corrected and stabilization
dates in sites SWPPP book.
- repair SF and replace straw bails w/ rock checks on Fire road removing rills
- stabilize denuded areas at grade or dormant for over 14 days overseed areas
where stabilization hasn't established
- establish slope stabilization on SB1 and a vegetative cover on diversions and
conveyance channels
- repair damaged perimeter SF removing phased out SF, ensure curb inlet protection
are installed
- slope drains need stone inlet and outlet protection
- confirm with site engineer how the rock outcropping in SB1 will be addressed (clay
lining) prior to Stormwater conversion
- confirm ST1 weir has been adjusted correctly with the current drainage area
- remove construction debris and cover dumpsters
A Warning has been issued with a reinspection date set for 7/29/22
Inspection Report
*Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control
Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from
Construction Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
Photos for Item 4
Photo Description:
Photos for Item 10
Photo Description:
Photos for Item 30
TimePhoto_20220721_133431.jpg.jpg 375.72KB
Photo Description: Establish a vegetative cover on graded areas and areas that have been dormant for
over 14 days
Photos for Item 39
TimePhoto_20220721_133509.jpg.jpg 286.37KB
Photo Description: Ensure all active inlets have protections installed
Other Photos
Photo Description:
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Inspection Date: 7/22/2022
County Inspector