HomeMy WebLinkAboutWPO202000034-16498-Full Inspection ReportCOUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
STOP WORK ORDER
Hand delivered
Project: WP0202000034
BELVEDERE - PHASE 5 - VSMP - DIGITAL
Operator/Contractor: AG Dillard, Inc.
BELVEDERE LAND HOLDINGS LLC
Issued Date: 7/27/2022
Under § 17-902 of the Albemarle County Code, you are hereby notified to immediately cease
all land disturbing activities on the above referenced property except for work to address
any necessary corrections as given in writing by the County Erosion Control Inspector. This
Stop Work Order is being issued because of the following deficiencies:
Deficiency: Denuded areas observed. Restabilize/overseed
required
Corrective Action: Overseed areas that haven't established a
vegetative cover
Deficiency: Vegetative cover not established
Corrective Action: Apply straw mulch and seed to establish a
vegetative cover
Deficiency: Missing curb inlets
Corrective Action: Install CIP
Deficiency: Diversions and stormwater conveyance channels
not stabilized and eroding
Corrective Action: Grade out eroded channeling and apply
seed, straw mulch and matting
Deficiency: Remove remaining SF when out of use
Corrective Action: Remove remaining SF when out of use
Deficiency: Remove remaining SF when out of use. SB rock
outcropping may need a clay liner prior to SW conversion
Corrective Action: Manually remove sediment from stream
utilizing buckets and shovels documenting length and volume of
sediment removed.
A sworn complaint has been made by the Albemarle County Erosion Control Inspector below. This
STOP WORK ORDER shall remain in effect for seven (7) days. If satisfactory repairs have not
been made within seven (7) days, the County may elect to issue another Stop Work Order, and/or
petition the Circuit Court for penalties and relief with regard to this violation.
Reinspections as a result of this notice to verify corrective measures will incur a $170 fee for
the first reinspection and $270 for each subsequent reinspection for single-family dwelling
units (§ 17-207). Reinspections as a result of this notice to verify corrective measures will
incur a $283 fee for the first reinspection and $383 for each subsequent reinspection for
VESCP and VSMP permits (§ 17-207 and § 17-208). A 4% technology fee is due with each
payment.
County Inspector Name: Jonney Otto
County Inspector Phone Number: 434 296-5832
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
BELVEDERE - PHASE 5 - VSMP -
DIGITAL
Project/WPO Number:
WP0202000034
Project Address:
DEQ Permit Number (if
applicable):
VAR100868
Project Operator:
AG Dillard, Inc.
Operator Telephone #:
(434) 977-3750
Project Contact:
BELVEDERE LAND HOLDINGS LLC
Contact Telephone #:
(434) 220-7701
Contact E-Mail:
SKROHN@RESORTSCOMPANIES.COM
Qualified Personnel (QP):
DJ Banton - AG Dillard, Inc
Inspector:
Jonney Otto
Qualified Personnel (QP)
Email:
Disturbed Acreage:
Weather (Wet/Dry/Rain):
Single -Family:
Inspection Date & Time:
7/27/2022 11:00:00 AM
Stage of Construction: Grading
Other Email:
Re -Inspection: No
Other Email:
Bond Inspection: No
Other Email:
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? No
Comments/Description
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
Page 1 of 6
The SWPPP includes a legible site plan identifying all appropriate
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
K? (CGP Part II A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? No
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part II B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
(CGP Part II B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part II B.4(e-f)) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? No
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
Page 2 of 6
26
Inspection reports are completed and signed in accordance with CGP
Part II F (3-4)? (CGP Part II F (3-4))
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
No
plan?
Sequencing of the project is implemented in accordance with the
yes
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
Denuded areas observed. Restabilize/overseed
been stabilized, and have stabilization requirements for impaired waters,
required
30
approved TMDL(s), pollutants of concern and exceptional waters, when
No
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
N/A
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
No
Vegetative cover not established
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
N/A
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
N/A
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
N/A
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
N/A
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
N/A
38
(9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
No
Missing curb inlets
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
NSA
Diversions and stormwater conveyance channels not
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
stabilized and eroding
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
N/A
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
N/A
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
N/A
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
N/A
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
yes
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Page 3 of 6
Have all temporary control structures that are no longer needed been
Remove remaining SF when out of use. SIB rock
46
removed and disturbed soil resulting from their removal permanently
No
outcropping may need a clay liner prior to SW
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
conversion
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
During a large storm event sediment was discharged
47
protected from erosion, sediment and damage in accordance with the
No
into a stream
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
N/A
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? No
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 6
Notes:
CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT
REQUEST FOR CORRECTIVE ACTION
Project Name: Permit Number (if applicable): Date:
Regulatory
Occurrence
Observation/Recommended Corrective Action
Checklist #
Citation/Legal
requirement'
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and
Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Construction Activities (9VAC25-880).
Page 5 of 6
Corrective Action Deadline:
Re -Inspection Date:
Comments:
The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently
constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for
ensuring compliance on the above project.
Page 6 of 6
Construction General Permit Site Inspection Report
Request for Correction Action
Check
Regulatory Citation/Legal
Occur.
Observation
Recommended Corrective
List #
Requirement*
Action
30
(9VAC 25-840-40.1)
Denuded areas observed.
Overseed areas that haven't
(9VAC25-870-54.B)
Restabilize/overseed required
established a vegetative cover
(9VAC25-880-60) (CGP
Part I F.1(a)) (CGP Part
11 A.5.b(1)) (CGP Part 11
A.2.c (8)) (CGP 11 E(1-2))
32
(9VAC 25-840-40.3)
Vegetative cover not
Apply straw mulch and seed
(CGP Part 11 A.2(c))
established
to establish a vegetative cover
(CGP 11 E(1-2))
(9VAC25-870-54. B )
39
(9VAC 25-840-40.10)
Missing curb inlets
Install CIP
(CGP Part 11 A.2(c))
(CGP 11 E(1-2))
(9VAC25-870-54. B )
40
(9VAC 25-840-40.11)
Diversions and stormwater
Grade out eroded channeling
(CGP Part 11 A.2(c))
conveyance channels not
and apply seed, straw mulch
(CGP 11 E(1-2))
stabilized and eroding
and matting
(9VAC25-870-54. B )
46
(9VAC 25-840-40.18)
Remove remaining SF when
Remove remaining SF when
(CGP Part 11 A.2(c))
out of use
out of use
(CGP 11 E(1-2))
(9VAC25-870-54. B )
46
(9VAC 25-840-40.18)
Remove remaining SF when
Manually remove sediment
(CGP Part 11 A.2(c))
out of use. SIB rock
from stream utilizing buckets
(CGP 11 E(1-2))
outcropping may need a clay
and shovels documenting
(9VAC25-870-54.B)
liner prior to SW conversion
length and volume of
sediment removed.
Recommended
Corrective Action
Deadline:
Targeted Re- 8/5/2022
Inspection Date:
Comments: Address all corrections listed in the Warning issued on 7/21/22 documenting the item
corrected and stabilization dates in your SWPPP book.
-repair SF and replace straw bails with stone rock checks on the Fire Rd. Regrading
stormwater conveyance channels and stabilize
-apply stabilization on areas that remain denuded and overseed areas that haven't
established a vegetative cover
-establish a vegetative cover on slope for SIB 1 and ST, S131 diversions
-repair damaged perimeter SF removing old SF and ensure curb inlet protection are
installed
-install inlet and outlet stone protection for slope drains
-confirm with site engineer how the rock outcropping will affect the Stormwater
conversion of SB1
-confirm ST1 weir is installed at the correct size for drainage area
-remove construction debris and cover dumpsters
A Stop Work Order has been issued for Belvedere phase 5 for discharging sediment
into a stream during a storm event on 7/25/22. Manually remove sediment from
stream utilizing buckets and shovels documenting length and volume of sediment
removed.
A reinspection date has been set for 8/5/22
*Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control
Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from
Construction Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
Photos for Item 4
Photo Description:
Photos for Item 10
Photo Description:
Photos for Item 40
TimePhoto_20220727_104555.jpg.jpg 713.56KB
Photo Description: Grade out eroded channeling and apply seed, straw mulch and matting
Photos for Item 47
Time Photo_20220727_104736.jpg.jpg 1.17MB
Photo Description: Manually remove sediment from stream utilizing buckets and shovels documenting
length and volume of sediment removed.
TimePhoto_20220727_105138.jpg.jpg 797.86KB
Photo Description: Manually remove sediment from stream utilizing buckets and shovels documenting
length and volume of sediment removed.
TimePhoto_20220727_105353.jpg.jpg 777.71 KB
Photo Description: Manually remove sediment from stream utilizing buckets and shovels documenting
length and volume of sediment removed.
TimePhoto_20220727_105454.jpg.jpg 970.21 KB
Photo Description: Manually remove sediment from stream utilizing buckets and shovels documenting
length and volume of sediment removed.
Other Photos
Photo Description:
w -
x %00014 Amu 1P:0
County Inspector
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Inspection Date: 7/28/2022