HomeMy WebLinkAboutSDP200600051 Action Letter 2006-11-07 •
P
1-1 i
t
`I�Ir}1P
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,Room 227
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4012
November 27, 2006
Rick Artiga
301 East High Street
Charlottesville, VA 22902
RE: SDP-2006-051,Woodlands of Charlottesville
Tax Map 76 Parcels 46C,46C2 and 46C3
Dear Mr. Artiga:
The Planning Commission unanimously approved the above-referenced site plan at its November 7, 2006
meeting.
The approval of the preliminary site plan is valid for(1)one year in accordance with Zoning Ordinance
Section 32.4.3.1. Therefore,the preliminary approval shall expire November 7,2007. If the preliminary
site plan approval expires,a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight(8)tentative plan
copies to the Community Development Department. This letter must be submitted with the tentative plans,
as a checklist,to document that you have addressed all requirements or conditions, or the tentative plan
will be denied.
The Erosion and Sediment Control Plan and the BMP Stormwater Management Plan,with the associated
applications and fees,may also be submitted with the eight(8)tentative Plans. Failure to do so will result
in a separate application to be filed with the County at a later date.
After the initial tentative plan submittal, each department/agency will contact you to discuss any remaining
conditions. After all aforementioned department/agencies have granted a tentative approval,you may
submit the final mylars(2 sets), one blueprint copy, final site plan application, final site plan fee, and a
copy of all written tentative approvals to the Community Development Department for signature.
The final site plan will be subject to all final site plan requirements(Zoning Ordinance Section 32.6), in
addition to the following conditions:
The Current Development Division shall not accept submittal of the final site plan for signature until
tentative approvals for the following conditions have been obtained. The final site plan shall not be
signed until the following conditions have been met:
1. Current Development Planner approval to include:
a. Approval of Light Fixtures complying with Chapter 18, Section 4.17.3 of the County Code
definition of"Full cutoff luminaire".
b. Approval of plat combining parcels and dedicating right of way for"proposed new road".
2. Current Development Engineer approval to include:
a. Erosion and Sediment Control Plan.
b. Storm water Management Plan.
3. Albemarle County Service Authority Approval to include:
a. Water and Sewer plans.
4. Architectural Review Board approval.
5. Virginia Department of Transportation approval of road plans for"proposed new road"as a public
road connecting existing Mountainwood Road to Sunset Avenue.
6. Approval of Road Names.
Please contact me at your earliest convenience if you have any questions or require additional information.
Sincerely,
William D. Fritz, AICP
Chief of Current Development
Zoning and Current Development Division
WDF/aer
Cc: Woodlands of Charlottesville LLC
126 Briarcliff Rd Suite 9, Athens GA 30606
Ella Carey
Amelia McCulley
Jack Kelsey
Steve Allshouse