HomeMy WebLinkAboutSP200600023 Action Letter
o
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832
Fax (434) 972-4012
November 1, 2006
Ben Thompson
PO Box 29682
Richmond, VA 23242
RE: SP 2006-23 Luck Stone Quarry Flood Control Berm (Sign #50)
Tax Map 79, Parcel 7
LETTER OF CORRECTION - Original Letter dated October 30, 2006
Correction to approval condition - see underlined, italicized text on page 2
Dear Mr. Thompson:
On October 4, 2006, the Albemarle County Board of Supervisors took action on SP 2006-023,
Luck Stone Quarry Flood Control Berm, to allow fill in the floodway fringe to allow for a flood
control berm on a 127.797 acre parcel, on Tax Map 79 Parcel 7 in the Scottsville Magisterial
District. This special use permit was approved based on the following conditions:
1. County Engineer approval of a grading and an erosion and sediment control plan prior to
the issuance of a grading permit for activity in the area of the flood control berm;
2. Natural Resources Manager and Design Planner approval of a mitigation plan for the
restoration/el1hancement of the stream buffer prior to the issuance of a grading permit
for activity in the area of the flood control berm;
3. Applicant shall obtain a Conditional Letter of Map Revision (CLOMR) from the Federal
Emergency Management Agency (FEMA) and copy the County Engineer on all
correspondence;
4. County Engineer approval of as-built drawings for the completed flood control berm,
including geotechnical engineer certification of the adequate compaction of the fill; and
5. Upon completion of the flood control berm the applicant will comply with the conditions
identified in the CLOMR issued by FEMA and will copy the County Engineer on all
correspondence related to this matter.
Please be advised that although the Albemarle County Board of Supervisors took action
on the project noted above, no uses on the property as approved above may lawfully
Thompson
SP-2006-023 Luck Stone Quarry Flood Control Berm
Page 2 of 2
November 1, 2006
begin until all applicable approvals have been received and conditions have been met.
This includes:
. compliance with conditions of the SPECIAL USE PERMIT;
. approval of and compliance with a SITE PLAN amendment; and
. approval of a ZONING COMPLIANCE CLEARANCE.
In the event that the use, structure or activity for which this special use permit is issued is not
commenced within twenty-four (24) months from the date of Board approval, it shall be deemed
abandoned and the permit terminated. The term "commenced" means "construction of any
structure necessary to the use of the permit."
If you have questions or comments regarding the above-noted action, please do not hesitate to
contact Sherri Proctor at 296-5832.
Sincerely,
~~~~el--L
Director of Planning [;/-
VWC/aer
cc: Rivanna LLC C/O Charles S Luck III
127 Kennondale Ln, Richmond VA 23226
Amelia McCulley
Chuck Proctor
Tex Weaver
Sherri Proctor