Subject: WPO 2013-00030 Surplus Soil Disposal Area Wetsel Property
The $44,730 water protection performance bond has been posted and approved (erosion only). The permit and first
year inspection fee has been paid. Please contact Ray Lilly to set up the pre-construction meeting.
Thanks
Ana D. Kilmer
Management Analyst
County of Albemarle
Community Development Department
401 Mclntire Road
Charlottesville, VA 22902
434'296'5832
aki{mner0Da|bemade.urg
Surplus Soil Disposal Area:Wetsel Property
WPO file number: WP0201300030
Erosion and Sediment Control Bond Estimate
Item Item yo.Unit Unit Cost Cost
Number figstslledl
stablieation(PS,TS) 3.0 acres $5,000.00 015,000.00
Mb fence(SF) 100.0 ft $5.00 $500.00
safety fence(SAF) 0.0 ft $0.00 $0.00
diversion(DD,FD,RWD) 1000 ft $13.00 $13,000.00
temporary slope drain(TOD) pipe length 0 ft pipe diameter 0 in $0.00 $0.00
temporary sediment trap(ST or CIP) Method for volume
height of dam at toe 6 ft M at dam 0 ft (lents)z(total widt
height of dam at face 4 ft cut at high side 0 ft assume face at 2:
length of dam 50 ft length of cut 0 ft total width=34go,
top width 6 ft width of cot 0 ft average height=(
(comp.fill col) 296.3 cy (cut vol) 0.0 cy $13.00
length of spillway 15 ft (cy est) 296.3
width of spillway 18 ft (spillway stone tons) 0 050.00 03,851.85
nit fence inlet protection(IP) 0 $100.00 $0.00
stone inlet protection(IP) 0 $200.00 $0.00
outlet protection(OP) length 15 ft width 10 ft 0 $675.00 $000
channel(SCC,matted) length 0 ft width 0 ft $0.00
check dam depth in channel 0 ft channel width 0 ft 1 $0.00 $000
constructon entrance(CE) 1 $2,000.00 $2,00000
wash rack $2,000.00
paved construction entrance 0 $3,500.00 $0.00
hp-rap,placed depth 0 ft length 1.0 ft
width 1.0 (tone) 0 060.00 $0.00
survey and layout(price per 0.1 mi.) acres 0 traps and basins 1 $500.00
mobil¢ation $500.00
stream crossing(computed independently)
cost sum $35,351.85
prof mgmt $5,302.78
contingency $4,065.46
Total $44,730
•