HomeMy WebLinkAboutWPO201100042 Bond 2011-07-06 Ana Kilmer
From: Ana Kilmer
Sent: Wednesday, November 09, 2011 4:06 PM
To: 'Jamie C. Dunaway'; Kenny Thacker; Philip Custer
Cc: Esther Grace
Subject: Crown BMW Retail Parts&Service Building-Water Protection Performance Bond-
W P0-2011-00042
The $283,700 water protection performance bond has been posted and approved(erosion$26,500;stormwater
$257,200). The stormwater agreement was recorded on 9/20/2011. The permit and first year inspection fee has not
been paid.
Ms. Dunaway:
Prior to setting up the preconstruction meeting, you need to pay the permit and first year inspection fee of$28
($100/per disturbed acre). Please make check payable to the County of Albemarle and submit to my attention.
Thank you.
l
,t 2---
Ana D. Kilmer
County of Albemarle
Community Development Department
401 McIntire Road
Charlottesville,VA 22902
434-296-5832
akilmerPalbemarle.org
Philip Custer
From: Philip Custer
Sent: Friday, August 19, 2011 5:41 PM
To: 'Ankita Kot'; 'Ankita Kot'
Cc: Ana Kilmer
Subject: Crown WPO Bonds
Akita,
The ESC and SWM bonds have been calculated for the Crown Project(WPO-2011-00042). The ESC bond has been
computed to be$26,500. The SWM bond has been computed to be$257,200. To post the bond, please contact Ana
Kilmer after reviewing the forms online.
Please let me know if you have any questions.
Thanks,
Phil
(434) 296-5832 x3072
1
PROJECT NAME: Crown BMW Retail Parts&Service Building
FILE#: WPO-2011-00042
DATE APPROVED: Pending
Item Unit Amount Unit Cost Subtotal
Filterra 4x6 each 3 $8,100.00 $24,300
Filterra 4x12 each 1 $12,900.00 $12,900
Filterra 6x8 each 1 $11,700.00 $11,700
Filterra Installation per project 5 $12,225
Stormfilter 1 (2 cartridges) each 1.00 $9,020.00 $9,020.00 from engineer
Stormfilter 2(3 cartridges) each 1.00 $11,550.00 $11,550.00 from engineer
Stormfilter 3(3 cartridges) each 1.00 $11,550.00 $11,550.00 from engineer
Stormfilter Installation per project 3 $8,030
CM underground detention each 1.00 $68,000.00 $68,000 from engineer
detention installation each 1.00 $34,000.00 $34,000 (50%of cost of facility)
subtotal $203,275
project management $30,491
subtotal $233,766
10%Contingency $23,377
TOTAL $257,143
ROUNDED TOTAL $257,200
min total after reduction $51,440
BOND ESTIMATE-EROSION CONTROL Spreadsheet last revised:12-5-01
PROJECT NAME: Crown BMW Retail Parts&Service Building
PROJECT NUMBER: WPO-2011-00042
DATE OF ESTIMATE: 08/19/11
ESTIMATE BY: PBC
BASED ON: plans signed 6-29-11
WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL
SEED,FERTILIZE,MULCH ACRE 2.8 1500 4200
SILT FENCE LF 180 5 900
SAFETY FENCE LF 600 3 1800
TREE PROTECTION FENCE LF 360 3 1080
DIVERSION DIKE LF 420 3 1260
SEDIMENT BASIN 1 ACRES 2.5 1000 2500
INLET PROTECTION EA 16 200 3200
PAVED CONSTRUCTION ENTRANCE EA 3 2000 6000
subtotal 20940.00
project management 3141.00
subtotal 24081.00
CONTINGENCY LS 10% 2408.10
TOTAL 26489.10
BOND AMOUNT REQUIRED ( 26500.001