HomeMy WebLinkAboutSDP201800045 Correspondence 2022-11-09I® COLLINS ENGINEERING
October 23, 2022
Department of Community Development
401 McIntire Road
200 GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
��434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
Charlottesville, VA 22902
RE: North Pointe— Northwestern Residential Area Final Site Plan (SDP2018-45)
Per discussions with Charles Rapp, this final plan has been reinstated for review and approval. The last comment
letter, dated July Ste 2019, indicated that the plan was basically ready for approval, pending confirmation that the
proffer items had been addressed. CE met with Albemarle County and VDOT in August 2019 and discussed the
completion of the project. In that meeting, it was deemed that the transportation proffers were not completely
addressed until all VDOT approvals had been obtained. This included the VDOT approvals for the shop drawings
associated with the entrance culvert and the retaining wall along Route 29. CE worked with VDOT over the past 3
years (during the pandemic) to obtain final approvals on the shop drawings for the North Pointe infrastructure
associated with the road plan, site plan, and Route 29 entrance improvement plan. Attached is the letter from
VDOT with the approval for these shop drawing designs. CE is resubmitting the final site plan for approval,
addressing the comments below from the final review letter, dated July St', 2019.
Planning
1.
Comment previously addressed
2.
Comment previously addressed
B.
Comment previously addressed
4.
Comment previously addressed
5.
Comment previously addressed
6.
Comment previously addressed
7. Comment previously addressed
8. As noted above, the road plans can now be approved with the approval from VDOT on the shop drawings.
In addition, a request to establish a road bond is being submitted to the county as well.
9. Attached is the approved letter from VDOT for the road plans, entrance plans, and shop drawings. VDOT
has now approved all aspects of the North Pointe project.
10. Comment previously addressed
11. Comment previously addressed
12. The note on sheet 6 has been updated to reference SMA2000-9.
13. Comment previously addressed
14. Comment previously addressed
15. Comment previously addressed
16. Comment previously addressed
17. Comment previously addressed
18. Comment previously addressed
19. Comment previously addressed
20. Comment previously addressed
21. Comment previously addressed
22. Comment previously addressed
23. Comment previously addressed
24. Comment previously addressed
25. This comment has been addressed with the approval from VDOT for the shop drawings for the culvert at
North Pointe.
26. Comment previously addressed
27. Comment previously addressed
28. This comment has been addressed. The WPO has been approved and VDOT has approved the stream
crossing and shop drawings for the culvert.
29. Comment previously addressed
30. Comment previously addressed
31. Comment previously addressed
32. Comment previously addressed
33. Comment previously addressed
34. Attached is the updated recreational substitution letter for review and approval.
35. Comment previously addressed
36. Comment previously addressed
37. Comment previously addressed
38. All comment have been addressed.
39. Comment previously addressed
40. Comment previously addressed
41. Comment previously addressed
42. Comment previously addressed
43. Comment previously addressed
44. Comment previously addressed
45. The WPO plans, road plans, and entrance improvement plans have all been deemed ready for approval.
46. Comment previously addressed
47. Comment previously addressed
48. Comment previously addressed
49. Comment previously addressed
50. Comment previously addressed
51. Comment previously addressed
52. Comment previously addressed
53. Lot 74 meets the minimum front setback requirements, as shown on the plans and labeled on the cover
sheet. The setback from the alley is 6', and Lot 74 meets this setback requirement.
54. Comment previously addressed
55. Comment previously addressed
56. Comment previously addressed
'' mment previously addressed
58. This comment has been addressed with the approval of the plans by VDOT.
59. This comment is addressed with the bonding of the utility improvements.
60. The bus stops have been added to the road plans and site plans. No further comments have been
received to -date. This comment has been addressed.
61. Requirements associated with a proffer will be completed prior to site plan approval, including cash
payments as required.
62. This is not a site plan comment and should be removed from the comment letter.
ARB
Plans have been approved by ARE.
E911
Plans have been approved.
Fire/Rescue
No objections
Engineering
1. The WPO is being resubmitted for final approval with an updated SWPP and registration statement.
2. This comment has been addressed. The road plans are ready for approval.
3. This comment has been addressed, the entrance improvement plan is ready for approval.
4. The roadway shift has been coordinated with Townes Engineering (engineering firm for GEMC). This has
been deemed acceptable.
VDOT
Plans have been approved.
ACSA
Plans have been approved.
Should you have any questions, please feel free to contact me at 434-293-3719.
Sincerely,
Scott Collins, PE
Collins Engineering
® COLLINS ENGINEERING
October 23, 2022
County of Albemarle - Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
200 GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
( 434.293.3719 PH 434.293.2813 FX
..collin"ngimedng.com
RE. North Pointe SDP2018-45-RequestforSubstitution ofRequiredRecreationa/Amenities
Please consider this request to allow substitution of the recreation facilities specified in section 18-
4.16 of the Zoning Ordinance. Per the approved rezoning plan, the North Pointe density on this
property is 184 townhouse units for the Northern residential development area of North Pointe.
The required amenities, as listed below, includes (4) tot lots and (1) full basketball court
The rezoning plan for the entire North Pointe development did not contemplate any active
recreational areas or tot lot areas within this section of the overall project With the close
proximity of these townhouse units to the proposed elementary school property, the active
recreational elements can be accommodated for this townhouse development with the playgrounds
and fields within the elementary school property. In addition, this section of the North Pointe
Development is platting and dedicating approximately 16.23 acres of floodplain, Greenway, and
trail area to Albemarle County as a recreational area for the benefit of the overall development and
Albemarle County. Access easements to this area will also be platted, allowing public access to the
Greenway and recreational area within this development
Required Amenities
The following summarizes the required amenities per the ordinance:
Required Recreation area:
200 s.f. x 184 units = 36,800 s.f. or 0.85 ac
Four (4) tot lots required, each to include:
• 1 swing with 4 seats • 1 buckabout or whirl
• 1 slide • 2 benches
• 2 climbers
(1) Full Basketball Court: Y2 court/100 units x 184 units =1 full or 2 half courts required
ProposedAmenitiesr Land dedication to Albemarle County
Greenway, Floodplain area, and trail area dedicated to Albemarle County along with access
easements to this property through the townhouse development
TOTAL AREA PROWDED: 16.23 acres
Please consider this land dedication and proximity to the proposed elementary school site as a
substitution for the required recreational amenities per the Albemarle County zoning regulations.
The Greenway, floodplain, and trail area will be a public amenity to everyone within the
development and also available to the residents of Albemarle County. In addition, the homeowners
will have pedestrian access to the proposed Elementary school for active recreation.
Thank you for your consideration of this request
Sincerely,nn
c�C9r?L`(�6C�K�
Scott Collins, P.E.
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 orange Road
Culpeper Virginia 22701
Stephen C. Brich, P.E.
Commissioner
June 18, 2019
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Matthew Wentland, P.E.
Re: North Pointe — Route 29 Improvements Plan (Lewis & Clark Drive)
SUB-2016-00196
Review #7
Dear Mr. Wentland:
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, as well as the Culpeper District Traffic Engineering and Location & Design Sections,
have reviewed the above referenced plan as submitted by Collins Engineering, revised 26 April
2019, and finds it to be generally acceptable.
Note that although the plans are approved, a permit will not be issued until the Culpeper District
Structure & Bridge Section approves the plans for the proposed retaining wall and box culvert.
Comments concerning these items have been provided in previous review letters.
Also note that inventoried structures such as the proposed Lewis & Clark box culvert with
utilities crossings will not be approved unless a maintenance agreement with the County of
Albemarle is obtained in order to offset relocation of utility costs associated with maintenance of
the culvert.
If further information is desired, please contact Justin Deel at 434-422-9894.
A VDOT Land Use Permit will be required prior to any work within the right-of-way. The
owner/developer must contact the Charlottesville Residency Transportation and Land Use
Section at (434) 422-9399 for information pertaining to this process.
Sincerely,
Adam J. M ore, P.E.
Area Land Use Engineer
Charlottesville Residency
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
Stephen C. Brich, P.E. 1401 East Broad Street
Commissioner Richmond, Virginia 23219
June 28, 2022
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Matthew Wentland, P.E.
Re: SUB-2016-00196 - North Pointe Northwest, Structural Review
Review #9
Dear Mr. Wentland:
(804) 786,2701
Fax: (804) 786,2940
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the above referenced plan as submitted by Collins Engineering, revised
10 May 2021, revised construction plans 5-30-2022, and find the plans generally acceptable.
If further information is desired, please contact Max Greene at 434-422-9894.
A VDOT Land Use Permit will be required prior to any work within the right-of-way. The
owner/developer must contact the Charlottesville Residency Transportation and Land Use
Section at (434) 422-9399 for information pertaining to this process.
Sincerely,
John C. Wilson, P.E.
Assistant Resident Engineer
Area Land Use
Charlottesville Residency
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Road and Drainage plan review
Project title: North Pointe — Route 29 Improvement Plan
Project file number: SUB201600196
Plan preparer: Collins Engineering [scott@colhns-engineering.com]
Owner or rep.: Neighborhood Investments NP, LLC [richard@neighborhoodprops.com]
Date Received: 14 October 2016
(Rev. 1)
(Rev. 2)
(Rev. 3)
Date of comments:
(Rev. 1)
(Rev. 2)
(Rev. 3)
2 June 2017
16 August 2017
8 May 2019
22 December 2016
28 July 2017
2 October 2017
3 July 2019
Scott,
We have reviewed the plans and have the following comments:
Engineering
1. The VSMP plan will need to be approved before the road plans can be approved. (Rev. 1)
Response noted. (Rev. 3) The V SMP has not yet been approved.
2. The plan cannot be approved until VDOT has approved the hydrologic/hydraulic computations for
the stream crossing [SP2006-34, Condition #2].
Comments have not yet been received from Planning. ACSA, Fire Rescue and ARB currently have no
objection to the plans. VDOT comments were emailed on 6/18/19.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
Engineering Review Comments
Page 2 of 2
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.org/dgptfomis.asp?departrnent=cdengmTo
If you have any questions or concerns, please contact me either by email (mwentland@albemarle.or¢) or
by phone at 434-296-5832 ext. 3458.
Sincerely,
Matt Wentland, P.E.
Civil Engineer II
File: SLB201600196 North Pointe Rt29 Improvements Road Plans review comments rcv3 07-03-19.doc