NOTICE TO COMPLY
Hand delivered
Project: WP0202000053
PLEASANT GREEN PHASE II - VSMP - DIGITAL
Operator/Contractor: Contour Construction
STANLEY MARTIN COMPANIES LLC
Issued Date: 12/1/2022
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with
the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the
referenced project and to immediately take corrective measures to address erosion and sediment
control deficiencies on this property. This Notice to Comply is being issued because of the
following deficiencies:
Deficiency: Numerous dirt stockpiles not stabilized
Corrective Action: Must stabilize all dirt stockpiles
Deficiency: Erosion issues on sediment basin C have not been corrected
Corrective Action: Corrections have not been adequately addressed from previous Inspection
Deficiency: Denuded areas dormant longer than 14 day have not been stabilized
Corrective Action: Large denuded area between dirt stockpiles and curb have not been stabilized.
Rill erosion has occurred adjacent to sediment basin C
Unless subsequently amended in writing by this office, it is expected all of these corrective
measures will be completed by.
Reinspections as a result of this notice to verify corrective measures will incur a $170 fee for the first
reinspection and $270 for each subsequent reinspection for single-family dwelling units (§ 17-207).
Reinspections as a result of this notice to verify corrective measures will incur a $283 fee for the first
reinspection and $383 for each subsequent reinspection for VESCP and VSMP permits (§17-207 and
§ 17-208). Failure to take effective corrective measures will result in a Stop Work Order upon
reinspection. A 4% technology fee is due with each payment.
County Inspector Name: John Yerby
County Inspector Phone Number: (434) 296-5832
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
PLEASANT GREEN PHASE II - VSMP -
DIGITAL
project/WPO Number:
WP0202000053
Project Address:
DEQ Permit Number (if
applicable):
VAR10M834
Project Operator:
Contour Construction
Operator Telephone #:
(434) 244-0001
Project Contact:
STANLEY MARTIN COMPANIES LLC
Contact Telephone #:
Contact E-Mail:
odonnellgp@stanleymartin.com
Qualified Personnel (QP):
Gregg O'Donnell
Inspector:
John Yerby
Qualified Personnel (QP)
Email:
Disturbed Acreage:
Weather (Wet/Dry/Rain):
Single -Family:
Inspection Date & Time:
11/29/2022
Stage of Construction: Grading
Other Email:
backstromC@stanleymartin.com
Re -Inspection: Yes
Other Email:
ShifflettSD@stanleymartin.com
Bond Inspection: No
Other Email:
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? Yes
Comments/Description
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
N/A
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
Yes
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
Yes
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? Yes
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
Yes
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
Yes
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
Yes
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
Yes
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
Page 1 of 6
The SWPPP includes a legible site plan identifying all appropriate
Yes
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
Yes
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
Yes
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
Yes
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
Yes
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
NIA
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
Yes
K? (CGP Part II A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
Yes
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? Yes
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
Yes
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
Yes
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
Yes
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
Yes
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part II B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
Yes
(CGP Part II B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
N/A
stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
Yes
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
Yes
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part II B.4(e-f)) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
Yes
accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? Yes
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
Yes
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
Page 2 of 6
26
Inspection reports are completed and signed in accordance with CGP
Yes
Part II F (3-4)? (CGP Part II F (3-4))
27
Corrective actions are taken consistent with the requirements of the
Yes
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
Yes
plan?
Sequencing of the project is implemented in accordance with the
Yes
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
Denuded areas dormant longer than 14 day have not
been stabilized, and have stabilization requirements for impaired waters,
been stabilized
30
approved TMDL(s), pollutants of concern and exceptional waters, when
No
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
No
Numerous dirt stockpiles not stabilized
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
NIA
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
No
Erosion issues on sediment basin C have not been
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
corrected
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
No
Diversions not reworked and stabilize from pervious
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
Inspection
54.13)
Are sediment traps and basins installed in accordance with MS-6 and the
Yes
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
Yes
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
N/A
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
N/A
38
(9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
No
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
N/A
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
N/A
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
N/A
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
N/A
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
N/A
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
Yes
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Page 3 of 6
Have all temporary control structures that are no longer needed been
46
removed and disturbed soil resulting from their removal permanently
N/A
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
Yes
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
N/A
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
Yes
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
Yes
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
Yes
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
Yes
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
Yes
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
Yes
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
Yes
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
N/A
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 6
Notes:
CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT
REQUEST FOR CORRECTIVE ACTION
Project Name: Permit Number (if applicable): Date:
Regulatory
Occurrence
Observation/Recommended Corrective Action
Checklist #
Citation/Legal
requirement'
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and
Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Construction Activities (9VAC25-880).
Page 5 of 6
Corrective Action Deadline:
Re -Inspection Date:
Comments:
The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently
constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for
ensuring compliance on the above project.
Page 6 of 6
Construction General Permit Site Inspection Report
Request for Correction Action
Check
Regulatory Citation/Legal
Occur.
Observation
Recommended Corrective
List #
Requirement*
Action
31
(9VAC 25-840-40.2)
Numerous dirt stockpiles not
Must stabilize all dirt
(CGP Part II A.2(c))
stabilized
stockpiles
(9VAC25-870-54.B)
33
(9VAC 25-840-40.4)
Erosion issues on sediment
Corrections have not been
(CGP Part II A.2(c))
basin C have not been
adequately addressed from
(CGP II E(1-2))
corrected
previous Inspection
(9VAC25-870-54. B )
30
(9VAC 25-840-40.1)
Denuded areas dormant
Large denuded area between
(9VAC25-870-54.B)
longer than 14 day have not
dirt stockpiles and curb have
(9VAC25-880-60) (CGP
been stabilized
not been stabilized. Rill
Part I F.1(a)) (CGP Part
erosion has occurred adjacent
11 A.5.b(1)) (CGP Part 11
to sediment basin C
A.2.c (8)) (CGP 11 E(1-2))
Recommended 12/13/2022
Corrective Action
Deadline:
Targeted Re- 12/13/2022
Inspection Date:
Comments: Sediment basin C still has eroding slopes from previous Inspection. Diversions
leading to sediment basin C have not been reworked or stabilized. Dirt stockpiles
have not been stabilized and must be shown in SWPPP. Contact information has
been posted and SWPPP has been updated. All deficiencies listed in this report
must be corrected by December 13, 2022 or second Notice to Comly will be issued.
*Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control
Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from
Construction Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
............................
TimePhoto_20221129_081331.jpg.jpg 346.96KB
..
i
Photos for Item 4
Photos for Item 10
Photo Description:
Coverage letter and contacts
.................................................
Photo Description:
.................................................
.............................................
Photo Description:
SWPPP/Site Contact Information
SWPPP Coordinator
Oregg O'Donnell
Stanley Martin Homcs
434.326.0370
odonnellgp@StenleyMartin.com
SWPPP fospections
Wetlands Studies and Solutions Inc.
804-253-9880
Photos for Item 30
Time Photo_20221129_083809.jpg.jpg 454.56KB
Photo Description: Denuded area between curb and dirt stockpiles
Photos for Item 31
Time Photo_20221129_081905.jpg.jpg 745.67KB
Photo Description:
TimePhoto_20221129_082528.jpg.jpg 925.65KB
Photo Description: Rill erosion adjacent to sediment basin D
Photos for Item 33
Time Photo_20221129_082108.jpg.jpg 893.27KB
Photo Description: rilll erosion on slopes have not been corrected
TimePhoto_20221129_082209.jpg.jpg 450.71 KB
Photo Description: Diversions have not been stabilized
Photo Description:
Photos for Item 39
Time Photo_20221129_083605.jpg.jpg 710.46KB
Photo Description: No curb inlet protection for live storm drains
Other Photos
Photo Description:
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
nff�7'21w'"&
Mir
Inspection Date: 12/1/2022
County Inspector