HomeMy WebLinkAboutWPO201400063 Correspondence 2014-07-07 AiFIZ
BLACKWELL ENGINEERING, PLC
566 E.MARKET STREET • HARRISONBURG,VIRGINIA 22801 • (540)432-9555 FAX(540)434-7604
Transmittal Letter
Dept. of Community Development T. Basil Finnegan
To: Attn: Max Greene From:
Company: County of Albemarle Date: September 9,2014
401 McIntire Road
Address: Pages: See below
Charlottesville,VA 22902
New Hope Community Church
Job Name: WPO 2014 00063 Job Number: 2167
Second Submittal—Additional Prints
• Plans r Specs r Report r Proposal
✓ Letter r Calculations r Invoice r Other
Items:
1. Storm ater Manage a ent Plan — 2 sets
For Your:
Pi Approval r Use r Information r Distribution
r Signature l✓ Review r Records 1 Per your request
Comments:
Cc: Michael Henderson— New Hope Church
Sent Via:
✓ US Mail r Delivery l✓ Overnight r Email r Fax r Pick up r Other
CIVIL ENGINEERS SPECIALIZING IN LAND DEVELOPMENT, ENVIRONMENTAL NEEDS AND
CONSTRUCTION MANAGEMENT SERVING COMMERCIAL, INDUSTRIAL AND MUNICIPAL CLIENTS
Max Greene
From: Max Greene
Sent: Wednesday, August 27, 2014 1:21 PM
To: 'Basil Finnegan'
Subject: RE: New Hope Church-WP0201400063 (BE#2167)
Basil,
The plans appear to address the State Minimum Requirements for Approval. But we do not have a complete set of
plans. Also, do you have a copy of the 2014 VSMP permit from the State? I think if you send 2 complete sets of the
plans to me I can approve them once we have all the State permit information.
Thanks,
Max
From: Basil Finnegan [mailto:basilblackwellengineering.com]
Sent: Monday, August 18, 2014 10:03 AM
To: Max Greene
Subject: New Hope Church - WP0201400063 (BE# 2167)
Max,
Clarity needed on the VSMP Application Completion Check reviewed by Glenn Brooks.
Line D - Erosion and Sediment Control Plan- temporary and permanent controls in such detail to be
reasonably adequate [Which controls need more detail?]
Line G - Stormwater Pollution Prevention Plan- Qualified personnel identified. Operator, Persons to sign
inspection reports [We think the SWPPP was signed by the Owner. Does the Operator for each measure
need to be assigned to address this comment?]
Line I-Requested Variations or Exceptions if applicable-SSF, MMT, etc. [The "Modified Rock Check Dam
for l' Deep Ditches" and "Bioretention Basin-Energy Dissipator/Separator" are the only two items that I
think Glenn is referring to. Is this correct?]
Regards,
T. Basil"Tinne,gan
Senior Designer
Blackwell Engineering, PLC
540-432-9555 (Office)
540-434-7604 (Fax)
www.blackwellengineering.com
1
Nwe
Glenn Brooks
From: Glenn Brooks
Sent: Thursday, July 10, 2014 1:49 PM
To: 'mike2848 @gmail.com'; 'basil @blackwellengineering.com'
Cc: Max Greene
Subject: New Hope chruch application, WPO201400063
Attachments: NewHopeChruch_Eng_VSMP_Completeness_Check.pdf
Gentlemen,
Your application was incomplete. Please find attached our completeness review. Albemarle is now a VSMP authority,
and we are required to implement all state VSMP requirements and the General VPDES permit. These changes were
effective on July 1St
Thank you,
Glenn Brooks,P.E.
County Engineer
Albemarle County