Loading...
HomeMy WebLinkAboutWPO201400082 Plan - Stormwater 2014-09-15 STORM WATER POLLUTION PREVENTION PLAN (Pursuant to Virginia Regulation 9 VAC 25-880-10) For Church Road Stormwater Management Facility Retrofit Albemarle County, VA Prepared by: Kimley-Horn and Associates, Inc. 4500 Main Street, Suite 500 Virginia Beach, Virginia 23462 757-213-8600 September 5, 2014 (Operator's Signature) Date ceret 4i&°Ai*;re CDt tL POLICY AND GENERAL PROCEDURES This SWPPP has been developed in accordance with the requirements contained in the Virginia Pollution Discharge Elimination System(VPDES)storm water general permit for discharges from construction activities(9 VAC 25-880). It is the responsibility of the Operator involved with grading, drainage,utilities or who implement a pollutant control measure identified in the Storm Water Pollution Prevention Plan (S WPPP)to secure authority to discharge stormwater from land disturbing activates of one acre or greater in full conformance with the stormwater regulations of the Virginia Department of Environmental Quality(VDEQ)as contained in 9 VAC 25-880. The Operator and all subcontractors must comply with the requirements of the VSMP as contained in the VDEQ VPDES storm water general permit and implementing regulations (9 VAC 25-880)and the erosion and sediment control requirements of the VDEQ as published in the Virginia Erosion and Sediment Control Handbook(current edition). These requirements are as follows: A. The Owner will electronically submit a Registration Statement for coverage under a VPDES general permit for stormwater discharges from construction activities based on the information contained on the Registration Statement provided by the Engineer and secure verification of coverage from the Department of Environmental Quality prior to the commencement of land disturbing activities exceeding the permit threshold. The appropriate filing fee will be remitted to the Department of Environmental Quality, Receipts Control section on a schedule established by the Owner and the VDEQ to secure general permit issuance. The fees for general permits, payable by the Owner to the VDEQ, are as follows: • Less than 1 acre(only areas within common plans of development or sale): $81 • Between 1 and 5 acres: $756 • Between 5 and 10 acres: $952 • Between 10 and 50 acres: $1,260 • Between 50 and 100 acres: $1,708 • Greater than 100 acres: $2,688 B. A copy of the Registration Statement for coverage under the general permit for storm water discharges from construction activities as well as the actual general permit when issued by the VDEQ shall be maintained by the Operator for inspection at the construction site. Land disturbing activities cannot commence until verification of coverage is received by the Operator from VDEQ. C. A complete copy of the SWPPP, including copies of all inspection reports, plan revisions, etc., must be retained by the Operator at the project site at all times during working hours and kept in the Operator's permanent project records for at least three years following submission of the Notice of Termination(NOT). D. The Operator must provide names and addresses of all subcontractors working on this project who will be involved with all construction activities that disturb site soil. This information must be kept with this SWPPP. E. The Operator and all subcontractors involved with land disturbing for this project must Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 sign a copy of the appropriate certification statement included in Appendix C which will be incorporated into the construction contract. F. As described below,the Operator shall conduct regular inspections to determine effectiveness of the SWPPP. The SWPPP shall be modified by the Operator as needed to prevent pollutants from discharging from the site. The Operator's inspector must be both a person familiar with the site and the nature of the major construction activities and be qualified to evaluate both overall system performance and individual component performance. Additionally,the Operator's inspector must either be someone empowered to implement modifications to this SWPPP and the pollutant control devices, if needed, in order to increase effectiveness to an acceptable level, or someone with the authority to cause such things to happen. This authority should be delegated to the inspector by using the enclosed Letter of Delegation of Authority(Appendix A)signed by the Operator naming the person or position responsible for undertaking these tasks on behalf of the Operator. G. This SWPPP shall be updated each time there are modifications to the pollutant prevention system or a change of Operators working on the project that disturbs site soil. The Operator shall notify the governing reviewing agency before these modifications are implemented, unless immediate Operator action is necessary to prevent unauthorized discharges. If immediate Operator action is needed,then the Operator shall notify the governing reviewing agency of the action as soon as practicable. H. Discharge of oil or other hazardous substances into the storm water is subject to reporting and cleanup requirements. Refer to Part III.G of the VPDES General Permit for additional information. Copies of the VPDES General Permit and the Registration Statement forms are available on the Department of Environmental Quality web site (http://www.deq.virginia.gov/Programs/Water/StormwaterManagement/VSMPPermits.asp x). Once the site reaches final stabilization,the Operator shall complete and submit two copies of the NOT form for activities on site. This form is included as Appendix E. If a section or phase of the project reaches final stabilization prior to the entire project reaching final stabilization, then that section may be clearly marked on the site plans and the date of final stabilization recorded in the SWPPP. Areas so marked are no longer required to be inspected as a part of permit compliance. J. This SWPPP is intended to control water-borne and liquid pollutant discharges by some combination of interception, filtration, and containment. The Operator and all subcontractors implementing this SWPPP shall remain alert to the need to periodically refine and update the SWPPP in order to accomplish the intended goals. K. This SWPPP shall be amended as necessary during the course of construction in order to keep it current with the pollutant control measures utilized at the site. Amending the SWPPP does not mean that it has to be reprinted. It is acceptable to handwrite revisions, add addenda, sketches, new sections, and/or revised drawings. L. A record of the dates when land disturbing activities occur, when construction activities Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 temporarily or permanently cease on a portion of the site, and when stabilization measures are initiated shall be maintained by the Operator until the NOT is filed. A log for keeping such records is included in the Appendices. A different form for the log may be substituted if it is found to be more useful. M. Annual permit maintenance fees are required. Maintenance fees are as follows: • Less than 1 acre(only areas within common plans of development or sale): $50 • Between 1 and 5 acres: $400 • Between 5 and 10 acres: $500 • Between 10 and 50 acres: $650 • Between 50 and 100 acres: $900 • Greater than 100 acres: $1,400 II. INTRODUCTION This SWPPP has been prepared for land disturbing activities associated with the construction of Church Road Stormwater Management Facility Retrofit in Albemarle County, VA. This SWPPP includes the elements necessary to comply with the Storm Water General Permit issued by the VDEQ under the VPDES and local governing agency requirements. This SWPPP shall be implemented at the start of construction. Construction phase pollutant sources anticipated at the site are: ® Disturbed(bare)soil, ❑ Vehicle fuels and lubricants, ❑ Chemicals associated with building construction, and building materials, ❑ Asphalt and asphalt pavement waste; chlorine for water line flushing, ❑ Other pollutants Without adequate control there is the potential for each type of pollutant to be transported by stormwater. The project will consist of the following basic activities: ® Site grading, ❑ Paving work, ® Installation of stormwater management and drainage systems, ❑ Installation of utilities, ❑ Other activities Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 Purpose A major goal of pollution prevention efforts during project construction is to control soil and pollutants that originate on the site and prevent them from flowing to surface waters of the Commonwealth. The purpose of this SWPPP is to provide requirements for achieving that goal. A successful pollution prevention program also relies upon careful inspection and adjustments during the construction process in order to enhance its effectiveness. Scope This SWPPP must be implemented when land disturbing activities begin on the site. This SWPPP will be made available for public inspection upon public request on site during normal business hours for the term of the permit authorization for the site. The SWPPP Construction Site Notice as well as a copy of the DEQ Coverage Letter must be posted conspicuously and readable from a public right of way at the job site. This SWPPP primarily addresses the impact of storm rainfall and runoff on areas of the ground surface disturbed during the construction process. In addition, there are recommendations for controlling other sources of pollution that could accompany the major construction activities. Permit coverage is terminated as of the date the lot is transferred to a new owner, coverage under a new VPDES permit is obtained, or as of the date another Operator assumes control over portions of the site not stabilized. In these situations, coverage under the permit terminates at midnight the date the Notice of Termination(NOT)is filed. Where the Operator seeks to terminate coverage because the site has reached final stabilization,termination will become effective upon concurrence by the VSMP Authority, or after 60 days from the submittal of the NOT, whichever occurs first. Forms required to implement the SWPPP are included in the Appendices to this document. The VPDES General Permit for Storm Water Discharges from Construction Activities prohibits most non-storm water discharges during the construction phase. Allowable non- storm water discharges that may occur during construction on this project, which would therefore be covered by the General Permit, include: 1. Discharges from firefighting activities; 2. Fire hydrant flushing; 3. Water used to wash vehicles or control dust where detergents are not used; 4. Water flowing from potable sources and water line flushing; 5. Water used to control dust; 6. External building wash down which does not use detergents; Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 7. Runoff from pavement wash down where spills or leaks of toxic or hazardous materials have not occurred(unless all spilled material has been removed)and where detergents have not been used; 8. Uncontaminated air conditioning or compressor condensate; 9. Springs and uncontaminated groundwater; 10. Foundation or footing drains where flows are not contaminated with process materials such as solvents; 11. Uncontaminated excavation dewatering; and 12. Landscape irrigation. The techniques described in this SWPPP focus on providing control of pollutant discharges with practical approaches that utilize readily available expertise, materials, and equipment. The Operator referred to in this SWPPP is the entity noted on the VSMP registration statement. The Operator and their subcontractor(s) will construct the site development improvements in accordance with the approved plans and this SWPPP. III. PROJECT DESCRIPTION Described below are the land disturbing construction activities that are the subject of this SWPPP. They are presented in the order(or sequence)they are expected to begin, but each activity will not necessarily be completed before the next begins. Also, these activities could occur in a different order if necessary to maintain adequate erosion and sedimentation control: A. The proposed project will be a stormwater management facility. The facility will be a constructed wetland, approximately 0.485 acres in size. The subject property is located off Seminole Trail at the intersection of Hillside and Incarnation Drive. The proposed area of disturbance is 1.73 acres. B. Sequence of Construction 1. Install construction entrance, tree protection, inlet protection, and silt fence. 2. Perform clearing and grubbing of limits of disturbance. 3. Construct sediment trap or basin as required. 4. Rough grade and install utilities and storm drainage system. 5. Install inlet protection on all stormwater inlet structures. 6. Sod and topsoil all denuded areas. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 7. Once site has been stabilized remove all erosion and sediment controls. C. The project site consists of 4.01 acres with a disturbed area of 1.73 acres. D. The pre-development runoff coefficient is 0.2. This will remain constant under post- development conditions. E. Other potential sources of pollution—Vehicle fuels and lubricants. F. The site outfalls to the Meadow Creek, a tributary of the Rivanna River. The Rivanna River is a tributary of and the James River and the Chesapeake Bay. G. The selected erosion and sediment control drawings, grading and drainage drawings, and/or erosion and sediment control narrative provided in Appendix G illustrate/outline the following: 1. Drainage patterns and approximate slopes or contours anticipated after grading activities 2. Areas of soil disturbance and areas of the site which are not to be disturbed. 3. Location of major structural and non-structural controls. 4. Location of areas where stabilization practices are expected to occur including types of vegetative cover 5. Surface waters including wetlands 6. Locations where stormwater is discharged to a surface water with an outline of the drainage area for each discharge point. 7. Existing and planned paved areas and buildings 8. Location of permanent stormwater management practices to be used to control pollutants in stormwater after construction activities have been completed 9. Location of all off-site materials, waste, borrow or equipment storage areas covered by the plan, and 10. Location of other potential sources of pollution The actual schedule for implementing pollutant control measures will be determined by project construction progress. Down slope protective measures must always be in place before soil is disturbed. IV. SITE DESCRIPTION Included as part of this SWPPP in Appendix G are selected project construction drawings. Please refer to them for detailed site information. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 A. Site Location–The proposed site location is in northern Albemarle County, VA. Southeast of Seminole Trail(US-29)it is located near the intersection of Hillside and Incarnation Drive. The center of the project is located at 38.0730 LAT and-78.4767 LONG. Surrounding land use is a mix of commercial and high density residential. B. Site Topography and Coverage–Existing site sloped toward the center of the property providing a change in elevation of approximately 20 feet. Presently there are approximately 0.30 acres of wetlands. The northern half of the site is covered with grass and the southern half of the site is forested. C. Rainfall Information–The average rainfall for Charlottesville, VA is 43 inches (MONTICELLO Weather station, NOAA and NCDC). Fifty six percent(24 inches)of the annual precipitation occurs between April and September. A rain gauge shall be installed on site to determine if an inspection triggering rainfall event has occurred. An inspection"triggering rainfall event"is rainfall that equals or exceeds one half inch(0.5") in a 24-hour period at the construction site. Site Soils–The following soils are present on-site according to a web soil survey generated from the United States Department of Agriculture(USDA)and Natural Resources Conservation Service(NRCS)online database. Map Unit: 27B—Elioak loam, 2 to 7 percent slopes Component:Elioak(80%) The Elioak component makes up 80 percent of the map unit. Slopes are 2 to 7 percent. This component is on hillslopes, piedmonts. The parent material consists of residuum weathered from mica schist. Depth to a root restrictive layer is greater than 60 inches. The natural drainage class is well drained. Water movement in the most restrictive layer is moderately high. Available water to a depth of 60 inches is moderate. Shrink-swell potential is low. This soil is not flooded. It is not ponded. There is no zone of water saturation within a depth of 72 inches. Organic matter content in the surface horizon is about 2 percent. Nonirrigated land capability classification is 2e. This soil does not meet hydric criteria. Map Unit: 34D—Glenelg loam, 15 to 25 percent slopes Component: Glenelg(80%) The Glenelg component makes up 80 percent of the map unit. Slopes are 15 to 25 percent. This component is on piedmonts, hillslopes. The parent material consists of residuum weathered from mica schist. Depth to a root restrictive layer is greater than 60 inches. The natural drainage class is well drained. Water movement in the most restrictive layer is moderately high. Available water to a depth of 60 inches is high. Shrink-swell potential is low. This soil is not flooded. It is not ponded. There is no zone of water saturation within a depth of 72 inches. Organic matter content in the surface horizon is about 2 percent. Nonirrigated land capability classification is 4e. This soil does not meet hydric criteria. Map Unit: 91—Urban land Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 Component:Urban land(85%) Generated brief soil descriptions are created for major soil components. The Urban land is a miscellaneous area. Map Unit: 95—Wehadkee silt loam Component:Wehadkee(80%) The Wehadkee component makes up 80 percent of the map unit. Slopes are 0 to 2 percent. This component is on flood plains,river valleys. The parent material consists of alluvium derived from igneous rock. Depth to a root restrictive layer is greater than 60 inches. The natural drainage class is poorly drained. Water movement in the most restrictive layer is moderately high. Available water to a depth of 60 inches is high. Shrink-swell potential is low. This soil is occasionally flooded. It is not ponded. A seasonal zone of water saturation is at 15 inches during January,February, March,April, May, June,November,December. Organic matter content in the surface horizon is about 4 percent.Nonirrigated land capability classification is 4w. This soil meets hydric criteria. D. Total Area and Disturbed Area–The project site consists of 4.01 acres with a disturbed area of 1.73 acres. E. Quality of Receiving Surface Waters and/or Wetlands– The proposed drainage of the Church Road Stormwater Management Facility Retrofit outfalls to Meadow Creek. Meadow Creek is included on the Virginia Department of Environmental Quality 2012 305(b)/303(d)Water Quality Assessment Integrated Report as impaired for recreation. The recreation impairment is based on exceedance of criteria for Escherichia Coli, or fecal coliform. To minimize the potential runoff of addition fecal coliform into receiving water, sanitary restroom facilities must be provided during construction and should be located away from any stormwater inlet or access. Meadown Creek is also listed as impaired for aquatic life based on an exceedance of Benthic-Macroinvertebrate. This impairment will likely not be affected by general construction activities. F. Threatened or Endangered Species or their Critical Habitat–The Virginia Department of Game and Inland Fisheries' Virginia Fish and Wildlife Information Service was reviewed for the presence of threatened or endangered species on the site. One species,the James Spinymussel(Pleurobema collina), was identified as threatened and endangered within two miles of the project area. There were no other potential endangered species within two miles of the project site. Coordination with the proper federal, state, and local agencies should occur if these species are observed during construction of if impacts to these species' habitats will occur. G. Erosion Control Plan–The Erosion and Sediment Control facilities show on the approved E&S Plans (Appendix G)include silt fence, inlet protection, and temporary silt check dam as shown on plan sheet 9. These plans are provided in Appendix G. H. Permanent Stormwater Controls–Permanent Stormwater Controls–Runoff from the proposed site will be retained in the onsite wetland stream complex. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 • V. STORM WATER POLLUTION PREVENTION MEASURES AND CONTROLS A variety of storm water pollutant controls (Best Management Practices) are recommended for this project. These controls are reflected in the Erosion and Sediment Control Plans enclosed herein as Appendix G. Some controls are intended to function temporarily and will be used as needed for pollutant control during the construction period. These include temporary sediment barriers such as silt fencing, a rock construction entrance, and inlet protection measures. For most disturbed areas, permanent stabilization will be accomplished by covering the soil with pavement, buildings, other improvements, and/or vegetation. A. Erosion and Sediment Controls 1. Short and Long Term Goals—All erosion and sediment control measures have been selected, designed and are to be installed in accordance with the Virginia Erosion and Sediment Control Law and Regulations. The short term goal of construction phase stabilization is to minimize the loss of sediment to adjacent waters during construction. The long term goal is to minimize the loss of sediment from the project once constructed by permanent soil stabilization. 2. Soil Stabilization- The purpose of soil stabilization is to prevent soil from leaving the site. In the natural condition, soil is stabilized by existing vegetation. The primary technique to be used at this project for stabilizing site soil will be to provide a protective cover of turf grass, pavement, other improvements, or building over disturbed soil. (a) Temporary Seeding—Stabilization for all areas to remain denuded for a period of fourteen(14)days or longer(for disturbed area draining to impaired waters, Tier III waters or to waters with a TMDL established prior to the issuance of the Construction General Permit), or;thirty(30) days or longer(for all other disturbed areas)shall be initiated within twenty-four(24)hours after construction activity ceases in these areas. The methods for establishing stabilization shall be applied within seven (7)days of initiation. Temporary seeding shall be in conformance with the project plans and/or erosion and sediment control narrative. (b) Permanent Seeding or Sodding- Stabilization for all areas at final grade shall be initiated within twenty-fours (24)hours of completion of the land disturbing activity. The methods for establishing final stabilization shall be applied within seven (7)days of initiation. Except for small level spots, seeded areas shall be protected with mulch. Permanent seeding or Sodding shall be in conformance with the project plans and/or erosion and sediment control narrative. (c) Structural Controls—Storm water runoff is to be structurally controlled as depicted on the plan sheets and/or project narrative. Structural controls Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 shall be keyed to land disturbing activities especially on sites with significant topography and shall be completely installed prior to commencement of such land disturbing activities. (d) Final Stabilization—Final stabilization is not considered established until a ground cover is achieved that is uniform, mature enough to survive and will inhibit erosion. The Operator shall stabilize all exposed earth areas with permanent vegetation as described in the project plans and/or erosion and sediment control narrative. B. Stormwater Management Controls 1. The following stormwater management controls have been utilized on this project: ❑ Dry ponds ® Stormwater retention/detention structures ❑ Flow attenuation from swales and natural depressions ❑ Infiltration of site runoff ❑ Bio-retention systems ® Stormwater wetlands ❑ Water quality structures ❑ Other measures(Specify) C. Construction Phase "Best Management Practices" Control of sediments has been described previously. Other aspects of this SWPPP are listed below: 1. Dust Control -Construction traffic must enter and exit the site at the stabilized construction entrance. The purpose is to trap dust and mud that would otherwise be carried off-site by construction traffic. Dust control shall be provided by the Operator in compliance with applicable local and state dust control regulations. After construction,the site will be stabilized(as described elsewhere), which will reduce the potential for dust generation. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 2. Effluent from de-watering activities must be filtered or passed through an approved sediment trapping device, or both, before being discharged from the site. No contaminated effluent or groundwater may be discharged with stormwater without a separate VPDES discharge permit from the VDEQ. Such permit shall be obtained by the Operator, prior to discharge. 3. Solid Waste Disposal-No solid materials, including building materials, are allowed to be discharged from the site with storm water. All solid waste, including disposable materials incidental to the major construction activities, must be collected, removed from the site and disposed of in a legal manner. The locations of solid waste containers must be shown on the site maps. Substances that have the potential for polluting surface water and/or groundwater must be controlled by whatever means necessary in order to ensure that they are not discharged from the site. As an example, special care must be exercised during equipment fueling and servicing operations. If a spill occurs, it must be contained and disposed of so that it will not flow from the site or enter groundwater, even if this requires removal, treatment, and disposal of soil. In this regard, potentially polluting substances should be handled in a manner consistent with the impact they represent. 4. Sanitary Facilities-All personnel involved with construction activities must comply with state and local sanitary or septic system regulations. Temporary sanitary facilities where provided at the site throughout the construction phase must be utilized by all construction personnel and shall be serviced by a commercial operator when provided. Their location must be shown on the project site maps if installed on site. 5. Water Source-Non-storm water components of site discharge must be clean water. Water used for construction, which discharges from the site, must originate from a public water supply or private well approved by the Virginia Department of Health. Water used for construction that does not originate from an approved public supply must not discharge from the site. It is to be retained in ponds until it infiltrates and evaporates. D. Construction Phase "Best Management Practices" During the construction phase,the Operator shall implement the following measures where appropriate: 1. Material resulting from clearing and grubbing shall be stockpiled up slope from adequate sedimentation controls or hauled off-site. All soil stockpile areas shall be annotated on the project plans in Appendix G. 2. All soil stockpile areas shall be maintained sufficiently far from water bodies or wetlands and shall be adequately protected from erosion to preclude migration of sediments into the water bodies or wetlands. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 3. The Operator shall designate areas for equipment cleaning, maintenance, and repair. The Operator and subcontractor(s) shall utilize those areas. The areas shall be protected by a temporary perimeter berm or silt fencing. 4. Use of detergents for large scale washing is prohibited(i.e.,vehicles, buildings, pavement surfaces, etc.) 5. Chemicals, paints, solvents, fertilizers, and other toxic material must be stored in waterproof containers. Except during application,the contents must be kept locked in trucks or within locked storage facilities. Runoff containing such material must be collected, removed from the site, treated, and disposed at an approved solid waste or chemical disposal facility. 6. All materials used for concrete mixing shall be washed down in a designated area where the corresponding runoff is directed into a leak-proof container or leak-proof settling basin. This concrete wash water shall be properly disposed of off-site. VI. LOCAL PLANS In addition to this SWPPP, construction activities associated with this project must comply with all additional requirements set forth by the County of Albemarle, Office of Facilities Development. VII. INSPECTIONS AND SYSTEM MAINTENANCE The purpose of site inspections is to assess performance of pollutant controls. The inspections shall be conducted by the Operator's designated E&S inspector. If deficiencies in the erosion and sediment control measures are determined,they shall be recorded on the inspection form by the Operator and corrective action shall be initiated by the Operator within the time frame specified below. Between the time this SWPPP is implemented and final site stabilization is achieved, all disturbed areas and pollutant controls must be inspected at one of the two frequencies below: (Operator shall mark chosen inspection frequency) ❑ At least once every four business days or, ❑ At least once every five business days and no later than 48 hours following a measurable storm event. In the event that a measurable storm event occurs when there are more than 48 hours between business days,the inspection shall be conducted on the next business day. Based on these inspections,the Operator shall decide whether it is necessary to modify this SWPPP, add or relocate sediment barriers, or institute other actions required in order to prevent pollutants from leaving the site via storm water runoff. The Operator has the duty to repair, modify, maintain, or supplement pollutant control measures and take other actions necessary to achieve effective pollutant control Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 The Operator may install a rain gauge at the site to determine site specific rainfall conditions or must provide estimates of rainfall at the project site and provide information as to how the estimates were generated. For purposes of permit compliance, it is strongly recommended that the Operator install a rain gauge at the project site. Examples of particular items to be evaluated during site inspections are listed below. This list is not intended to be comprehensive. During each inspection, the Operator's inspectors must evaluate overall pollutant control system performance, as well as the effectiveness of system components. Additional factors should be considered as appropriate to the circumstances. A. Locations where vehicles enter and exit the site must be inspected for evidence of off-site sediment tracking. A stabilized construction entrance will be constructed where vehicles enter and exit. This entrance will be maintained or supplemented as necessary to prevent sediment from leaving the site on vehicles. Sediment tracked onto public roadways must be shoveled or swept from the roadway and re-deposited on site in a manner that minimizes its offsite release potential. B. Sediment barriers must be inspected and, if necessary,they must be enlarged or cleaned in order to provide additional capacity. All material excavated from behind sediment barriers shall be stockpiled on the up slope side of the barrier. Additional sediment barriers must be constructed as needed. Sediment must be removed from sediment traps and sediment basins when the design capacity has been reduced by 50%. C. Inspections will evaluate disturbed areas and areas used for storing materials that are exposed to rainfall for evidence of, or the potential for, pollutants entering the drainage system. If necessary, the materials must be covered or original covers must be repaired or supplemented. Also, protective berms must be constructed, if needed, in order to contain runoff from material storage areas. Grassed areas will be inspected to confirm that a healthy stand of grass is maintained. The site has achieved final stabilization when turf grass cover provides permanent stabilization of the soil surface exclusive of areas that have been paved or covered by building(s). Permanent stabilization is not considered established until a ground cover is achieved that is uniform, mature enough to survive and will inhibit erosion. D. All discharge points must be inspected to determine whether erosion control measures are effective in preventing impacts to receiving waters. Based on inspection results, any modification necessary to increase effectiveness of this SWPPP to an acceptable level shall be made by the Operator within seven calendar days of the inspection. All modifications to the SWPPP document and approved plan will be noted on the construction plans. The inspection reports must be completed entirely and additional remarks shall be included if needed to fully describe a situation. An important aspect of the inspection report is the description of additional measures that need to be taken to enhance plan effectiveness. The inspection report must identify whether the site was in compliance with the SWPPP at the time of inspection and specifically identify all incidents of non-compliance. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 Inspection reports will be kept on file by the Operator as an integral part of this SWPPP for at least thirty six months following the month the Notice of Termination is filed with the VDEQ. It is the responsibility of the Operator to ensure the adequacy of site storm water pollutant discharge controls. Physical site conditions, weather conditions or Operator practices may make it necessary to install more structural controls than are shown on the plans. (For example, localized concentrations of runoff could make it necessary to install additional sediment barriers.) Assessing the need for additional controls and implementing them or adjusting existing controls are key aspects of the effectiveness of this SWPPP until the site achieves final stabilization. Should a control fail, be bypassed or otherwise be ineffective in maintaining sediments onsite and releasing sediment offsite the Operator will provide notification to the VDEQ in accordance with Part III. G. of the VPDES Storm Water General Permit, as necessary. If it is determined by the Operator's Inspector that there has been an upset or bypass of the control measures resulting in a release of sediment to State waters,the Operator's Inspector shall report the bypass or upset to the Valley Regional Office of the Virginia Department of Environmental Quality(VDEQ)at 757-574-7800 within 24 hours of discovery of the unanticipated bypass or upset. Within five days of making the verbal report to VDEQ, a written report shall be submitted by the Operator containing: • A description of the nature and location of the discharge; • The cause of the discharge; • The date on which the discharge occurred; • The length of time that the discharge continued; • The volume of the discharge; • If the discharge is continuing, how long it is expected to continue; • If the discharge is continuing, what the expected total volume of the discharge will be; and • Any steps planned or taken to reduce, eliminate and prevent a recurrence of the present discharge or any future discharges not authorized by this general permit. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 APPENDICES APPENDIX A - AUTHORITY LETTER APPENDIX B- GENERAL PERMIT FOR STORMWATER DISCHARGES FROM CONSTRUCTION ACTIVITIES (VAR 10)-REGISTRATION STATEMENT DEPARTMENT OF ENVIRONMENTAL QUALITY CONSTRUCTION ACTIVITY OPERATOR PERMIT FEE FORM STORM WATER GENERAL PERMIT FOR CONSTRUCTION ACTIVITIES (VAR10) GENERAL VPDES PERMIT FOR DISCHARGED OF STORMWATER FROM CONSTRUCTION ACTIVITES (9VAC25-880) APPENDIX C - OPERATOR CERTIFICATION FORMS APPENDIX D - INSPECTION REPORTS APPENDIX E - NOTICE OF TERMINATION (NOT) FORM APPENDIX F - RECORD OF STABILIZATION AND CONSTRUCTION ACTIVITY DATES APPENDIX G - SELECTED EROSION AND SEDIMENT CONTROL SITE PLAN SHEETS APPENDIX H - SWPPP CONSTRUCTION SITE NOTICE APPENDIX I - STORMWATER CALCULATIONS Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 APPENDIX A AUTHORITY LETTER Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 DELEGATION OF AUTHORITY TO SIGN STORMWATER INSPECTION AND OTHER REPORTS Project Title Church Road Stormwater Management Facility Retrofit City State Albemarle County,VA t-De fwwre) vt, (Owner contact—this person must be classified as an officer of the company), ii officer of k F,1 v roti 1 Zr1 Co (insert organization or company name here) and its entities,with the authority over stormwater compliance of all Owner construction related activities, do hereby delegate Tod A_, (insert the name of the delegated individual(s)), of the below listed General Contractor the authority to sign/certify any and all stormwater inspection reports and/or related documents. This authorization includes the authority to sign/certify any and all inspection forms and or associated reports in accordance with the Virginia Pollutant Discharge Elimination System(VPDES) general permit for stormwater discharges from construction activities. Sincerely, or- 1111011H----.0% ..4111 AIPAIZIN y (Owner signature) (Date) (Print Name) (Title) General Contractor tt Company Name Company Contact 089 �R?trr rv� SI'I Business Address / 4111-a0 c A'G 700 336 - 7.2S - polo Business Phone Number Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 • GENERAL CONTRACTOR SIGNATURE DELEGATION FOR REPORTS GENERAL PERMIT FOR STORMWATER DISCHARGES FROM CONSTRUCTION ACTIVITIES I,the undersigned,hereby delegate the Project Superintendent(s)or Compliance Officer(s)of I- ,tJ t ii _Ste G Trill)rvo meet Iea1, Zet.G. (Company Name) as the authorized signatory for all reports required by this permit and other information requested by the Owner or authorized representative of the Owner in accordance with the provisions of the General Permit. I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage this system, or those persons directly responsible for gathering the information, the information submitted is,to the best of my knowledge and belief, true accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Sincerely, Principal or Officer of the General Contractor (Principal or Officer of the General Contractor signature) ( e Th)A r-re 11 T. Tirt ere (Print Name) (Title) /14ri .Ytra't't- ref idn o wtr.41,'j (Company) Church Road Stornnvater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 APPENDIX B VSMP GENERAL PERMIT FOR STORMWATER DISCHARGES FROM CONSTRUCTION ACTIVITIES (VAR 10) - REGISTRATION STATEMENT DEPARTMENT OF ENVIRONMENTAL QUALITY CONSTRUCTION ACTIVITY OPERATOR PERMIT FEE FORM STORM WATER GENERAL PERMIT FOR CONSTRUCTION ACTIVITIES (VAR10) COVERAGE LETTER (WHEN RECEIVED FROM DEQ) GENERAL VPDES PERMIT FOR DISCHARGES OF STORMWATER FROM CONSTRUCTION ACTIVITI I ,S (9VAC25-880) Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 • Registration Statement • • General VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10) . (Please Type or Print All Information) 1. Construction Activity.Operator: (General permit coverage will be issued to this operator. The Certification in Item #12 must be signed by the appropriate person associated with this operator.) Name: County of Albemarle, Virainia Contact: Frank Pohl, Office of Facilities Development Mailing Address: 4 01 McIntire Avenue City: Charlottesville State: VA Zip: 22902 Phone: 434-872-4501 Email address(if available): fpohl @albemarle.org Indicate if DEQ may transmit general permit correspondence electronically: Yes ® No❑ 2. Existing General Permit Registration Number(for renewals only): N/A 3. Name and Location of the Construction Activity: Name: Church Road Stormwater Management Facility Retrofit Address(if available): at the corner of Incarnation Drive and Hillsdale Drive City: Charlottesville State: Virginia Zip: County (if not located within a City): Albemarle Latitude(decimal degrees): 38 . 0730 Longitude (decimal degrees): —7 8 . 4767 Name and Location of all Off-site Support Activities to be covered under the general permit: Name: Address (if available): City: State: Zip: County(if not located within a City): Latitude (decimal degrees): Longitude (decimal degrees): 4. Status of the Construction Activity (check only one): Federal ❑ State ❑ Public Z Private❑ 5. Nature of the Construction Activity (e.g., commercial, industrial, residential, agricultural, oil and gas,etc.): Stormwater Management Facility 6. Name of the Receiving Water(s) and Hydrologic Unit Code(HUC): Name: Meadow Creek Name: HuC: 020802040401 HUC: 7. If the discharge is through a Municipal Separate Storm Sewer System (MS4),the name of the MS4 operator: Albemarle County 8. Estimated Project Start and Completion Date: Start Date(mm/dd/yyyy): 10/06/14 Completion Date(mm/dd/yyyy): 10/06/15 9. Total Land Area of Development(to the nearest one-hundredth acre): 1 73 Estimated Area to be Disturbed (to the nearest one-hundredth acre): 1 . 73 10. Is the area to be disturbed part of a larger common plan of development or sale? Yes[ No 11. A stormwater pollution prevention plan (SWPPP) must be prepared in accordance with the requirements of the General VPDES Permit for Discharges of Stormwater from Construction Activities prior to submitting this Registration Statement. By signing this Registration Statement the operator is certifying that the SWPPP has been prepared. 12. Certification: "I certify under penalty of law that I have read and understand this Registration Statement and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations." Printed Name: , rank V. Pohl I 4 I / Title: !Sr. Project Mgr Signature: �_ �I � Ji, ' Date: 109/10/14 ___(.?iease s gn_in_I lK._This_Ger_tificafion.,must be,signed by the_appropriate person associated with the operator identified in Item#1.) 01/2014 Page 1 of 1 • Virginia Stormwater Management Program (VSMP) Application for Albemarle County Project Name: Church Road Stormwater Management Facility Retrofit �. (The name should be the same as it appears on plans) Is this an amendment to an approved plan? Yes D No g Is this a revision or resubmission for review? Yes E No X , WPO-201400082 County File Number: (to be provided by the County for new applications) The following are required elements of new applications[from code section 17-401]. For revisions or amendments,please indicate which items are being amended. Signatures must be provided for any submission. TrA. Signature of the Property Owner for each parcel: (Required with every submission or revision,NOT TO BE SIGNED BY AN AGENT OR CONSULTANT) By signing this application as the owner,I hereby certify that all requirements of these plans and permits will be complied with,and I have the authority to authorize the land disturbing activities and development on the subject property. I hereby grant the County of Albemarle the right to enter upon the property as.required to ensure compliance with the approved plans and permits. 6-0 -oo-00%0 ev � a . /"" dr47, Tax Map&Parcel Print Nam1 of property Owner gignature of Owner Date Tax Map&Parcel Print Name of Property Owner Signature of Owner Date Tax Map&Parcel Print Name of Property Owner Signature of Owner Date Tax Map&Parcel Print Name of Property Owner Signature of Owner Date Contact Information for the Owner(s)to receive correspondence: /L Print Name (, -N� 44ei.it C 1 % '/�4- ' "7/ Address t oc-t Pke-1[-/I7e-3 City State Zip Daytime Phone( ) k �� , __ _ _ v + 1 7 Gn. All Fees [Code section 17-208] For new or-modified plans;Total acres proposed to be disturbed /.-?3 A c,g-es Acres to be Total Fee Fee Due with this Fee with Transfer or disturbed Application modification of permit coo Less than 1 $290 $145 $20 ° 7 .l 1 and less than 5 $2,700 $1,350 $200 � O A 5 and less than 10 $3,400 $1,700 $250 ��✓ r11 LV 10 and less than 50 $4,500 $2,250 $300 1' 50 and less than - $6,100 $3,050 $450 � 100 A T 100 and more $9,600 $4,800 $700 02 ' For(minor)amendments to an approved plan;$200 per review Variances;$150 • Mitigation Plan;$150" ESC. Registration Statement on the official DEQ form. dD. Erosion and Sediment Control Plan satisfying the requirements of code section 17-402. /JIVE. Stormwater Management Plan satisfying the requirements of code section 17-403. B/F. Pollution Prevention Plan'satisfying the requirements of code section 17-404. R.'G. Stormwater Pollution Prevention Plan satisfying.the requirements of code section 17-405. 67H. Mitigation Plan satisfying the requirements of code section 17-406 for any proposed disturbance of stream buffers. N/A I. Requested Variations or Exceptions as provided in code sections 17-407 and 408. VJ. Construction Record Drawings (as-builts)for any existing facilities in the proposal satisfying the requirements of code section 17-422. Provide 2 copies of all plans and any supporting documents. Professional seals must have original signatures. Additional information if not provided on plans and documents: Name of a Contact Person for correspondence(usually the plan preparer,consultant or agent) Print Name Frank Pohl (OFD) Address Office of Facilities Development, County of Albemarle City State Zip Daytime Phone( ) Ext.7914 E-mail fpohl @albemarle.org *When applications and plans are reviewed,but not approved,and a response to comments is not received within 6 months from the date of county comments,the application will be deemed withdrawn. Applications without valid owner's signatures will not be considered valid. — FOR-OFFiCE-USE--ONLY--- #._ ,,.-,....--_..__..�� — — -_ Fee Amount$ Date Paid By who? Receipt# C.# By: CHAPTER 880 GENERAL VPDES PERMIT FOR DISCHARGES OF STORMWATER FROM CONSTRUCTION ACTIVITIES 9VAC25-880-1. Definitions. The words and terms used in this chapter shall have the meanings defined in the Virginia Stormwater Management Act (Article 2.3 (§ 62.1-44.15:24 et seq.) of Chapter 3.1 of Title 62.1 of the Code of Virginia), this chapter, and 9VAC25-870 unless the context clearly indicates otherwise, except as otherwise specified in this section. Terms not defined in the Act, this chapter, or 9VAC25-870 shall have the meaning attributed to them in the federal Clean Water Act (33 USC § 1251 et seq.) (CWA). For the purposes of this chapter: "Business day" means Monday through Friday excluding state holidays. "Commencement of land disturbance" means the initial disturbance of soils associated with clearing, grading, or excavating activities or other construction activities (e.g., stockpiling of fill material). "Construction site" means the land where any land-disturbing activity is physically located or conducted, including any adjacent land used or preserved in connection with the land-disturbing activity. "Final stabilization" means that one of the following situations has occurred: 1. All soil disturbing activities at the site have been completed and a permanent vegetative cover has been established on denuded areas not otherwise permanently stabilized. Permanent vegetation shall not be considered established until a ground cover is achieved that is uniform (e.g., evenly distributed), mature enough to survive, and will inhibit erosion. 2. For individual lots in residential construction, final stabilization can occur by either: a. The homebuilder completing final stabilization as specified in subdivision 1 of this definition; or b. The homebuilder establishing temporary soil stabilization, including perimeter controls for an individual lot prior to occupation of the home by the homeowner, and informing the homeowner of the need for, and benefits of, final stabilization. 3. For construction projects on land used for agricultural purposes , final stabilization may be accomplished by returning the disturbed land to its preconstruction agricultural use. Areas disturbed that were not previously used for agricultural activities, such as buffer strips immediately adjacent to surface waters, and areas that are not being returned to their preconstruction agricultural use must meet the final stabilization criteria specified in subdivision 1 or 2 of this definition. "Immediately" means as soon as practicable, but no later than the end of the next business day, following the day when the land-disturbing activities have temporarily or permanently ceased. In the context of this general permit, "immediately" is used to define the deadline for initiating stabilization measures. "Impaired waters" means surface waters identified as impaired on the 2012 § 305(b)/303(d) Water Quality Assessment Integrated Report. "Infeasible" means not technologically possible or not economically practicable and achievable in light of best industry practices. "Initiation of stabilization activities" means: 1. Prepping the soil for vegetative or nonvegetative stabilization; Page 1 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) 2. Applying mulch or other nonvegetative product to the exposed area; 3. Seeding or planting the exposed area; 4. Starting any of the above activities on a portion of the area to be stabilized, but not on the entire area; or 5. Finalizing arrangements to have the stabilization product fully installed in compliance with the applicable deadline for completing stabilization. This list is not exhaustive. "Measurable storm event" means a rainfall event producing 0.25 inches of rain or greater over 24 hours. "Stabilized" means land that has been treated to withstand normal exposure to natural forces without incurring erosion damage. 9VAC25-880-10. Purpose. This general permit regulation governs stormwater discharges from regulated construction activities. For the purposes of this chapter, these discharges are defined as stormwater discharges associated with large construction activity, and stormwater discharges associated with small construction activity. Stormwater discharges associated with other types of industrial activity shall not have coverage under this general permit. This general permit covers only discharges through a point source to surface waters or through a municipal or nonmunicipal separate storm sewer system to surface waters. Stormwater discharges associated with industrial activity that originate from construction activities that have been completed and the site has undergone final stabilization are not authorized by this general permit. 9VAC25-880-15. Applicability of incorporated references based on the dates that they became effective. Except as noted, when a regulation of the United States set forth in the Code of Federal Regulations is referenced and incorporated herein, that regulation shall be as it exists and has been published in the July 1, 2013, update. 9VAC25-880-20. Effective date of general permit. This general permit is effective on July 1, 2014. The general permit will expire on June 30, 2019. This general permit is effective for any covered operator upon compliance with all provisions of 9VAC25-880-30. 9VAC25-880-30. Authorization to discharge. A. Any operator governed by this general permit is authorized to discharge to surface waters of the Commonwealth of Virginia provided that: 1. The operator submits a complete and accurate registration statement, if required to do so, in accordance with 9VAC25-880-50 and receives acceptance of the registration by the board; 2. The operator submits any permit fees, if required to do so, in accordance with 9VAC25-870-700 et seq.; 3. The operator complies with the applicable requirements of 9VAC25-880-70; 4. The operator obtains approval of: Page 2 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) a. An erosion and sediment control plan from the appropriate VESCP authority as authorized under the Erosion and Sediment Control Regulations (9VAC25-840), unless the operator receives from the VESCP an "agreement in lieu of a plan" as defined in 9VAC25-840-10 or prepares the erosion and sediment control plan in accordance with annual standards and specifications approved by the department. The operator of any land-disturbing activity that is not required to obtain erosion and sediment control plan approval from a VESCP authority or is not required to adopt department-approved annual standards and specifications shall submit the erosion and sediment control plan to the department for review and approval; and b. A stormwater management plan from the appropriate VSMP authority as authorized under the Virginia Stormwater Management Program (VSMP) Regulation (9VAC25-870), unless the operator prepares the stormwater management plan in accordance with annual standards and specifications approved by the department. The operator of any land-disturbing activity that is not required to obtain stormwater management plan approval from a VSMP authority or is not required to adopt department-approved annual standards and specifications shall submit the stormwater management plan to the department for review and approval; and 5. The board has not notified the operator that the discharge is not eligible for coverage in accordance with subsection B of this section. B. The board will notify an operator that the discharge is not eligible for coverage under this general permit in the event of any of the following: 1. The operator is required to obtain an individual permit in accordance with 9VAC25- 870-410 B; 2. The operator is proposing discharges to surface waters specifically named in other board regulations that prohibit such discharges; 3. The discharge causes, may reasonably be expected to cause, or contributes to a violation of water quality standards (9VAC25-260); 4. The discharge violates or would violate the antidegradation policy in the Water Quality Standards (9VAC25-260-30) ; or 5. The discharge is not consistent with the assumptions and requirements of an applicable TMDL approved prior to the term of this general permit. C. This general permit also authorizes stormwater discharges from support activities (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas) located on-site or off-site provided that: 1. The support activity is directly related to a construction activity that is required to have general permit coverage for discharges of stormwater from construction activities; 2. The support activity is not a commercial operation , nor does it serve multiple unrelated construction activities by different operators; 3. The support activity does not operate beyond the completion of the last construction activity it supports; 4. The support activity is identified in the registration statement at the time of general permit coverage; 5. Appropriate control measures are identified in a stormwater pollution prevention plan and implemented to address the discharges from the support activity areas; and 6. All applicable, state, federal, and local approvals are obtained for the support activity. D. Support activities located off-site are not required to be covered under this general permit. Discharges of stormwater from off-site support activities may be authorized under Page 3 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) another state or VPDES permit. Where stormwater discharges from off-site support activities are not authorized under this general permit, the land area of the off-site support activity need not be included in determining the total land disturbance acreage of the construction activity seeking general permit coverage. E. Discharges authorized by this general permit may be commingled with other sources of stormwater that are not required to be covered under a state permit, so long as the commingled discharge is in compliance with this general permit. Discharges authorized by a separate state or VPDES permit may be commingled with discharges authorized by this general permit so long as all such discharges comply with all applicable state and VPDES permit requirements. F. Authorized nonstormwater discharges. The following nonstormwater discharges from construction activities are authorized by this general permit: 1. Discharges from firefighting activities; 2. Fire hydrant flushings; 3. Water used to wash vehicles or equipment where soaps, solvents, or detergents have not been used and the wash water has been filtered, settled, or similarly treated prior to discharge; 4. Water used to control dust that has been filtered, settled, or similarly treated prior to discharge; 5. Potable water source, including uncontaminated waterline flushings; 6. Routine external building wash down where soaps, solvents, or detergents have not been used and the wash water has been filtered, settled, or similarly treated prior to discharge; 7. Pavement wash water where spills or leaks of toxic or hazardous materials have not occurred (or where all spilled or leaked material has been removed prior to washing); where soaps, solvents, or detergents have not been used; and where the wash water has been filtered, settled, or similarly treated prior to discharge; 8. Uncontaminated air conditioning or compressor condensate; 9. Uncontaminated groundwater or spring water; 10. Foundation or footing drains where flows are not contaminated with process materials such as solvents; 11. Uncontaminated, excavation dewatering, including dewatering of trenches and excavations that have been filtered, settled, or similarly treated prior to discharge; and 12. Landscape irrigations. G. Approval for coverage under this general permit does not relieve any operator of the responsibility to comply with any other applicable federal, state or local statute, ordinance or regulation. H. Continuation of general permit coverage. 1. Any operator that was authorized to discharge under the general permit issued in 2009 and that submits a complete and accurate registration statement on or before June 30, 2014, is authorized to continue to discharge under the terms of the 2009 general permit until such time as the board either: a. Issues coverage to the operator under this general permit or b. Notifies the operator that the discharge is not eligible for coverage under this general permit. 2. When the operator is not in compliance with the conditions of the expiring or expired general permit the board may choose to do any or all of the following: Page 4 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) a. Initiate enforcement action based upon the 2009 general permit; b. Issue a notice of intent to deny the new general permit. If the general permit is denied, the owner or operator would then be required to cease the activities authorized by the continued general permit or be subject to enforcement action for operating without a state permit; c. Issue a new state permit with appropriate conditions; or d. Take other actions authorized by the VSMP Regulation (9VAC25-870). 9VAC25-880-40. Delegation of authorities to state and local programs. A board-approved VSMP authority is authorized to administer requirements of this general permit, including but not limited to: (i) registration statement acceptance; (ii) fee collection; (iii) stormwater management plan review and approval; and (iv) permit compliance and enforcement dependent upon conditions established as part of the board approval. 9VAC25-880-50. General permit application (registration statement). A. Deadlines for submitting registration statement. Any operator seeking coverage under this general permit, and that is required to submit a registration statement, shall submit a complete and accurate general VPDES permit registration statement in accordance with this section, which shall serve as a notice of intent for coverage under the general VPDES permit for discharges of stormwater from construction activities. 1. New construction activities. a. Any operator proposing a new stormwater discharge from construction activities shall submit a complete and accurate registration statement to the VSMP authority prior to the commencement of land disturbance. b. Any operator proposing a new stormwater discharge from construction activities in response to a public emergency where the related work requires immediate authorization to avoid imminent endangerment to human health or the environment is authorized to discharge under this general permit, provided that: (1) The operator submits a complete and accurate registration statement to the VSMP authority no later than 30 days after commencing land disturbance; and (2) Documentation to substantiate the occurrence of the public emergency is provided with the registration statement. c. Any operator proposing a new stormwater discharge associated with the construction of a single-family residence separately built, disturbing less than one acre and part of a larger common plan of development or sale, is authorized to discharge under this general permit and is not required to submit a registration statement or the department portion of the permit fee, provided that the stormwater management plan for the larger common plan of development or sale provides permanent control measures (i.e., stormwater management facilities) encompassing the single family residence. 2. Existing construction activities. a. Any operator that was authorized to discharge under the general permit issued in 2009 and that intends to continue coverage under this general permit shall: (1) Submit a complete and accurate registration statement to the VSMP authority on or before June 1, 2014; and Page 5 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) (2) Update its stormwater pollution prevention plan to comply with the requirements of this general permit no later than 60 days after the date of coverage under this general permit. b. Any operator with an existing stormwater discharge associated with the construction of a single-family residence separately built, disturbing less than one acre and part of a larger common plan of development or sale, and that intends to continue coverage under this general permit, is authorized to discharge under this general permit and is not required to submit a registration statement or the department portion of the permit fee, provided that: (1) The stormwater management plan for the larger common plan of development or sale provides permanent control measures (i.e., stormwater management facilities) encompassing the single-family residence; and (2) The operator updates its stormwater pollution prevention plan to comply with the requirements of this general permit no later than 60 days after the date of coverage under this general permit. 3. For stormwater discharges from construction activities where the operator changes, the new operator must submit a complete and accurate registration statement or transfer agreement form to the VSMP authority prior to assuming operational control over site specifications or commencing work on-site. 4. Late notifications. Operators are not prohibited from submitting registration statements after commencing land disturbance. When a late registration statement is submitted, authorization for discharges shall not occur until coverage under the general permit is issued. The VSMP authority, department, board, and the EPA reserve the right to take enforcement action for any unpermitted discharges that occur between the commencement of land disturbance and discharge authorization. B. Registration statement. The operator shall submit a registration statement to the VSMP authority that shall contain the following information: 1. Name, contact, mailing address, telephone number, and email address if available of the construction activity operator. No more than one operator may receive coverage under each registration statement. NOTE: General permit coverage will be issued to this operator, and the certification in subdivision 11 of this subsection must be signed by the appropriate person associated with this operator; 2. Name and location if available of the construction activity and all off-site support activities to be covered under this general permit, including city or county, and latitude and longitude in decimal degrees; 3. Status of the construction activity: federal, state, public, or private; 4. Nature of the construction activity (e.g., commercial, industrial, residential, agricultural, oil and gas, etc.); 5. Name of the receiving water(s) and HUC ; 6. If the discharge is through a municipal separate storm sewer system (MS4), the name of the municipal separate storm sewer system operator; 7. Estimated project start date and completion date; 8. Total land area of development and estimated area to be disturbed by the construction activity (to the nearest one-hundredth of an acre); 9. Whether the area to be disturbed by the construction activity is part of a larger common plan of development or sale; Page 6 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) 10. A stormwater pollution prevention plan (SWPPP) must be prepared in accordance with the requirements of the General VPDES Permit for Stormwater Discharges from Construction Activities prior to submitting the registration statement. By signing the registration statement the operator certifies that the SWPPP has been prepared ; and 11. The following certification: "I certify under penalty of law that I have read and understand this registration statement and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations." C. The registration statement shall be signed in accordance with 9VAC25-880-70, Part Ill K. 9VAC25-880-60. Termination of general permit coverage. A. Requirements. The operator of the construction activity shall submit a notice of termination to the VSMP authority after one or more of the following conditions have been met: 1. Necessary permanent control measures included in the SWPPP for the site are in place and functioning effectively and final stabilization has been achieved on all portions of the site for which the operator is responsible. When applicable, long-term responsibility and maintenance requirements for permanent control measures shall be recorded in the local land records prior to the submission of a notice of termination; 2. Another operator has assumed control over all areas of the site that have not been finally stabilized and obtained coverage for the ongoing discharge; 3. Coverage under an alternative VPDES or state permit has been obtained; or 4. For residential construction only, temporary soil stabilization has been completed and the residence has been transferred to the homeowner. The notice of termination should be submitted no later than 30 days after one of the above conditions being met. Authorization to discharge terminates at midnight on the date that the notice of termination is submitted for the conditions set forth in subdivisions 2 through 4 of this subsection unless otherwise notified by the VSMP authority or the department. Termination of authorizations to discharge for the conditions set forth in subdivision 1 of this subsection shall be effective upon notification from the department that the provisions of subdivision 1 of this subsection have been met or 60 days after submittal of the notice of terminations, whichever occurs first. B. Notice of termination. The notice of termination shall contain the following information: 1. Name, contact, mailing address, telephone number, and email address if available of the construction activity operator. 2. Name and location if available of the construction activity covered under this general permit, including city or county, and latitude and longitude in decimal degrees. 3. The general permit registration number. 4. The basis for submission of the notice of termination, pursuant to subsection A of this section. 5. Where applicable, a list of the on-site and off-site permanent control measures (both structural and nonstructural) that were installed to comply with the stormwater Page 7 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) • management technical criteria. For each permanent control measure that was installed, the following information shall be included: a. The type of permanent control measure installed and the date that it became functional as a permanent control measure; b. The location if available of the permanent control measure, including city or county, and latitude and longitude in decimal degrees; c. The receiving water of the permanent control measures; and d. The number of total and impervious acres treated by the permanent control measure (to the nearest one-tenth of an acre). 6. Where applicable, the following information related to participation in a regional stormwater management plan. For each regional stormwater management facility, the following information shall be included: a. The type of regional facility to which the site contributes; b. The location if available of the regional facility, including city or county, and latitude and longitude in decimal degrees; and c. The number of total and impervious site acres treated by the regional facility (to the nearest one-tenth of an acre). 7. Where applicable, the following information related to perpetual nutrient credits that were acquired in accordance with § 62.1-44.15:35 of the Code of Virginia: a. The name of the nonpoint nutrient credit generating entity from which perpetual nutrient credits were acquired; and b. The number of perpetual nutrient credits acquired (lbs. per acre per year). 8. The following certification: "I certify under penalty of law that I have read and understand this notice of termination and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations." C. The notice of termination shall be signed in accordance with 9VAC25-880-70 Part Ill K. D. Termination by the board. The board may terminate coverage under this general permit during its term and require application for an individual permit or deny a general permit renewal application on its own initiative in accordance with the Act, this chapter, and the VSMP Regulation, 9VAC25-870. 9VAC25-880-70. General permit. Any operator whose registration statement is accepted by the board will receive the following general permit and shall comply with the requirements contained therein and be subject to all requirements of 9VAC25-870. Page 8 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) General Permit No.: VAR10 Effective Date: July 1, 2014 Expiration Date: June 30, 2019 GENERAL VPDES PERMIT FOR DISCHARGES OF STORMWATER FROM CONSTRUCTION ACTIVITIES AUTHORIZATION TO DISCHARGE UNDER THE VIRGINIA STORMWATER MANAGEMENT PROGRAM AND THE VIRGINIA STORMWATER MANAGEMENT ACT In compliance with the provisions of the Clean Water Act, as amended, and pursuant to the Virginia Stormwater Management Act and regulations adopted pursuant thereto, operators of construction activities are authorized to discharge to surface waters within the boundaries of the Commonwealth of Virginia, except those specifically named in State Water Control Board regulations that prohibit such discharges. The authorized discharge shall be in accordance with this cover page, Part I - Discharge Authorization and Special Conditions, Part II - Stormwater Pollution Prevention Plan, and Part III - Conditions Applicable to All VPDES Permits as set forth herein. PART I DISCHARGE AUTHORIZATION AND SPECIAL CONDITIONS A. Coverage under this general permit. 1. During the period beginning with the date of coverage under this general permit and lasting until the general permit's expiration date, the operator is authorized to discharge stormwater from construction activities. 2. This general permit also authorizes stormwater discharges from support activities (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas) located on-site or off-site provided that: a. The support activity is directly related to the construction activity that is required to have general permit coverage for discharges of stormwater from construction activities; b. The support activity is not a commercial operation, nor does it serve multiple unrelated construction activities by different operators ; c. The support activity does not operate beyond the completion of the last construction activity it supports; d. The support activity is identified in the registration statement at the time of general permit coverage; e. Appropriate control measures are identified in a stormwater pollution prevention plan and implemented to address the discharges from the support activity areas; and f. All applicable state, federal, and local approvals are obtained for the support activity. B. Limitations on coverage. 1. Post-construction discharges. This general permit does not authorize stormwater discharges that originate from the site after construction activities have been completed and the site, including any support activity sites covered under the general permit Page 9 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) registration, has undergone final stabilization. Post-construction industrial stormwater discharges may need to be covered by a separate VPDES permit. 2. Discharges mixed with nonstormwater. This general permit does not authorize discharges that are mixed with sources of nonstormwater, other than those discharges that are identified in Part I E (Authorized nonstormwater discharges) and are in compliance with this general permit. 3. Discharges covered by another state permit. This general permit does not authorize discharges of stormwater from construction activities that have been covered under an individual permit or required to obtain coverage under an alternative general permit. 4. Impaired waters and TMDL limitation. Discharges of stormwater from construction activities to surface waters identified as impaired in the 2012 § 305(b)/303(d) Water Quality Assessment Integrated Report or for which a TMDL wasteload allocation has been established and approved prior to the term of this general permit for (i) sediment or a sediment-related parameter (i.e., total suspended solids or turbidity) or (ii) nutrients (i.e., nitrogen or phosphorus) are not eligible for coverage under this general permit unless the operator develops, implements, and maintains a SWPPP that minimizes the pollutants of concern and, when applicable, is consistent with the assumptions and requirements of the approved TMDL wasteload allocations. In addition, the operator shall implement the following items: a. The impaired water(s), approved TMDL(s), and pollutant(s) of concern, when applicable, shall be identified in the SWPPP; b. Permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; c. Nutrients shall be applied in accordance with manufacturer's recommendations or an approved nutrient management plan and shall not be applied during rainfall events; and d. The applicable SWPPP inspection requirements specified in Part II F 2 shall be amended as follows: (1) Inspections shall be conducted at a frequency of (i) at least once every four business days or (ii) at least once every five business days and no later than 48 hours following a measurable storm event. In the event that a measurable storm event occurs when there are more than 48 hours between business days, the inspection shall be conducted on the next business day; and (2) Representative inspections used by utility line installation, pipeline construction, or other similar linear construction activities shall inspect all outfalls discharging to surface waters identified as impaired or for which a TMDL wasteload allocation has been established and approved prior to the term of this general permit. 5. Exceptional waters limitation. Discharges of stormwater from construction activities not previously covered under the general permit issued in 2009 to exceptional waters identified in 9VAC25-260-30 A 3 c are not eligible for coverage under this general permit unless the operator implements the following: a. The exceptional water(s) shall be identified in the SWPPP; b. Permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; c. Nutrients shall be applied in accordance with manufacturer's recommendations or an approved nutrient management plan and shall not be applied during rainfall events; and Page 10 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) d. The applicable SWPPP inspection requirements specified in Part II F 2 shall be amended as follows: (1) Inspections shall be conducted at a frequency of (i) at least once every four business days or (ii) at least once every five business days and no later than 48 hours following a measurable storm event. In the event that a measurable storm event occurs when there are more than 48 hours between business days, the inspection shall be conducted on the next business day; and (2) Representative inspections used by utility line installation, pipeline construction, or other similar linear construction activities shall inspect all outfalls discharging to exceptional waters. 6. There shall be no discharge of floating solids or visible foam in other than trace amounts. C. Commingled discharges. Discharges authorized by this general permit may be commingled with other sources of stormwater that are not required to be covered under a state permit, so long as the commingled discharge is in compliance with this general permit. Discharges authorized by a separate state or VPDES permit may be commingled with discharges authorized by this general permit so long as all such discharges comply with all applicable state and VPDES permit requirements. D. Prohibition of nonstormwater discharges. Except as provided in Parts I A 2, I C and I E, all discharges covered by this general permit shall be composed entirely of stormwater associated with construction activities. All other discharges including the following are prohibited: 1. Wastewater from washout of concrete; 2. Wastewater from the washout and cleanout of stucco, paint, form release oils, curing compounds, and other construction materials; 3. Fuels, oils, or other pollutants used in vehicle and equipment operation and maintenance; 4. Oils, toxic substances, or hazardous substances from spills or other releases; and 5. Soaps, solvents , or detergents used in equipment and vehicle washing. E. Authorized nonstormwater discharges. The following nonstormwater discharges from construction activities are authorized by this general permit when discharged in compliance with this general permit: 1. Discharges from firefighting activities; 2. Fire hydrant flushings; 3. Waters used to wash vehicles or equipment where soaps, solvents, or detergents have not been used and the wash water has been filtered, settled, or similarly treated prior to discharge; 4. Water used to control dust that has been filtered, settled, or similarly treated prior to discharge; 5. Potable water sources, including uncontaminated waterline flushings; 6. Routine external building wash down where soaps, solvents or detergents have not been used and the wash water has been filtered, settled, or similarly treated prior to discharge; 7. Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (or where all spilled or leaked material has been removed prior to Page 11 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) washing); where soaps, solvents, or detergents have not been used ; and where the wash water has been filtered, settled, or similarly treated prior to discharge; 8. Uncontaminated air conditioning or compressor condensate; 9. Uncontaminated ground water or spring water; 10. Foundation or footing drains where flows are not contaminated with process materials such as solvents; 11. Uncontaminated excavation dewatering, including dewatering of trenches and excavations that have been filtered, settled, or similarly treated prior to discharge; and 12. Landscape irrigation. F. Termination of general permit coverage. 1. The operator of the construction activity shall submit a notice of termination in accordance with 9VAC25-880-60 to the VSMP authority after one or more of the following conditions have been met: a. Necessary permanent control measures included in the SWPPP for the site are in place and functioning effectively and final stabilization has been achieved on all portions of the site for which the operator is responsible. When applicable, long term responsibility and maintenance requirements shall be recorded in the local land records prior to the submission of a notice of termination; b. Another operator has assumed control over all areas of the site that have not been finally stabilized and obtained coverage for the ongoing discharge; c. Coverage under an alternative VPDES or state permit has been obtained; or d. For residential construction only, temporary soil stabilization has been completed and the residence has been transferred to the homeowner. 2. The notice of termination should be submitted no later than 30 days after one of the above conditions in subdivision 1 of this subsection are met. Authorization to discharge terminates at midnight on the date that the notice of termination is submitted for the conditions set forth in subdivisions 1 b through 1 d of this subsection. Termination of authorizations to discharge for the conditions set forth in subdivision 1 a of this subsection shall be effective upon notification from the department that the provisions of subdivision 1 a of this subsection have been met or 60 days after submittal of the notice of termination, whichever occurs first. 3. The notice of termination shall be signed in accordance with Part III K of this general permit. G. Water quality protection. 1. The operator must select, install, implement and maintain control measures as identified in the SWPPP at the construction site that minimize pollutants in the discharge as necessary to ensure that the operator's discharge does not cause or contribute to an excursion above any applicable water quality standard. 2. If it is determined by the department that the operator's discharges are causing, have reasonable potential to cause, or are contributing to an excursion above any applicable water quality standard, the department, in consultation with the VSMP authority, may take appropriate enforcement action and require the operator to: a. Modify or implement additional control measures in accordance with Part II B to adequately address the identified water quality concerns; Page 12 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 711/2014) b. Submit valid and verifiable data and information that are representative of ambient conditions and indicate that the receiving water is attaining water quality standards; or c. Submit an individual permit application in accordance with 9VAC25-870-410 B 3. All written responses required under this chapter must include a signed certification consistent with Part III K. PART II STORMWATER POLLUTION PREVENTION PLAN A stormwater pollution prevention plan (SWPPP) shall be developed prior to the submission of a registration statement and implemented for the construction activity, including any support activity, covered by this general permit. SWPPPs shall be prepared in accordance with good engineering practices. Construction activities that are part of a larger common plan of development or sale and disturb less than one acre may utilize a SWPPP template provided by the department and need not provide a separate stormwater management plan if one has been prepared and implemented for the larger common plan of development or sale. The SWPPP requirements of this general permit may be fulfilled by incorporating by reference other plans such as a spill prevention control and countermeasure (SPCC) plan developed for the site under § 311 of the federal Clean Water Act or best management practices (BMP) programs otherwise required for the facility provided that the incorporated plan meets or exceeds the SWPPP requirements of Part II A. All plans incorporated by reference into the SWPPP become enforceable under this general permit. If a plan incorporated by reference does not contain all of the required elements of the SWPPP, the operator must develop the missing elements and include them in the SWPPP. Any operator that was authorized to discharge under the general permit issued in 2009, and that intends to continue coverage under this general permit, shall update its stormwater pollution prevention plan to comply with the requirements of this general permit no later than 60 days after the date of coverage under this general permit. A. Stormwater pollution prevention plan contents. The SWPPP shall include the following items: 1. General information. a. A signed copy of the registration statement for coverage under the general VPDES permit for discharges of stormwater from construction activities; b. Upon receipt, a copy of the notice of coverage under the general VPDES permit for discharges of stormwater from construction activities (i.e., notice of coverage letter); c. Upon receipt, a copy of the general VPDES permit for discharges of stormwater from construction activities; d. A narrative description of the nature of the construction activity, including the function of the project (e.g., low density residential, shopping mall, highway, etc.); e. A legible site plan identifying: (1) Directions of stormwater flow and approximate slopes anticipated after major grading activities; (2) Limits of land disturbance including steep slopes and natural buffers around surface waters that will not be disturbed; Page 13 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) (3) Locations of major structural and nonstructural control measures, including sediment basins and traps; perimeter dikes, sediment barriers, and other measures intended to filter, settle, or similarly treat sediment, that will be installed between disturbed areas and the undisturbed vegetated areas in order to increase sediment removal and maximize stormwater infiltration; (4) Locations of surface waters; (5) Locations where concentrated stormwater is discharged; (6) Locations of support activities, when applicable and when required by the VSMP authority, including but not limited to (i) areas where equipment and vehicle washing, wheel wash water, and other wash water is to occur; (ii) storage areas for chemicals such as acids, fuels, fertilizers, and other lawn care chemicals; (iii) concrete wash out areas; (iv) vehicle fueling and maintenance areas; (v) sanitary waste facilities, including those temporarily placed on the construction site; and (vi) construction waste storage; and (7) When applicable, the location of the on-site rain gauge or the methodology established in consultation with the VSMP authority used to identify measurable storm events for inspection purposes. 2. Erosion and sediment control plan. a. An erosion and sediment control plan approved by the VESCP authority as authorized under the Erosion and Sediment Control Regulations (9VAC25-840), an "agreement in lieu of a plan" as defined in 9VAC25-840-10 from the VESCP authority, or an erosion and sediment control plan prepared in accordance with annual standards and specifications approved by the department. Any operator proposing a new stormwater discharge from construction activities that is not required to obtain erosion and sediment control plan approval from a VESCP authority or does not adopt department-approved annual standards and specifications shall submit the erosion and sediment control plan to the department for review and approval. b. All erosion and sediment control plans shall include a statement describing the maintenance responsibilities required for the erosion and sediment controls used. c. A properly implemented approved erosion and sediment control plan, "agreement in lieu of a plan," or erosion and sediment control plan prepared in accordance with department-approved annual standards and specifications, that adequately: (1) Controls the volume and velocity of stormwater runoff within the site to minimize soil erosion; (2) Controls stormwater discharges, including peak flow rates and total stormwater volume, to minimize erosion at outlets and to minimize downstream channel and stream bank erosion; (3) Minimizes the amount of soil exposed during the construction activity; (4) Minimizes the disturbance of steep slopes; (5) Minimizes sediment discharges from the site in a manner that addresses (i) the amount, frequency, intensity, and duration of precipitation; (ii) the nature of resulting stormwater runoff; and (iii) soil characteristics, including the range of soil particle sizes present on the site; (6) Provides and maintains natural buffers around surface waters, directs stormwater to vegetated areas to increase sediment removal, and maximizes stormwater infiltration, unless infeasible; Page 14 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) (7) Minimizes soil compaction and, unless infeasible, preserves topsoil; (8) Ensures that stabilization of disturbed areas will be initiated immediately whenever any clearing, grading, excavating, or other land-disturbing activities have permanently ceased on any portion of the site, or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 days; and (9) Utilizes outlet structures that withdraw stormwater from the surface (i.e., above the permanent pool or wet storage water surface elevation), unless infeasible, when discharging from sediment basins or sediment traps. 3. Stormwater management plan. a. New construction activities. A stormwater management plan approved by the VSMP authority as authorized under the Virginia Stormwater Management Program (VSMP) Regulation (9VAC25-870), or a stormwater management plan prepared in accordance with annual standards and specifications approved by the department. Any operator proposing a new stormwater discharge from construction activities that is not required to obtain stormwater management plan approval from a VSMP authority or does not adopt department-approved annual standards and specifications shall submit the stormwater management plan to the department for review and approval. b. Existing construction activities. Any operator that was authorized to discharge under the general permit issued in 2009, and that intends to continue coverage under this general permit, shall ensure compliance with the requirements of 9VAC25- 870-93 through 9VAC25-870-99 of the VSMP Regulation, including but not limited to the water quality and quantity requirements. The SWPPP shall include a description of, and all necessary calculations supporting, all post-construction stormwater management measures that will be installed prior to the completion of the construction process to control pollutants in stormwater discharges after construction operations have been completed. Structural measures should be placed on upland soils to the degree possible. Such measures must be designed and installed in accordance with applicable VESCP authority, VSMP authority, state, and federal requirements, and any necessary permits must be obtained. 4. Pollution prevention plan. A pollution prevention plan that addresses potential pollutant-generating activities that may reasonably be expected to affect the quality of stormwater discharges from the construction activity, including any support activity. The pollution prevention plan shall: a. Identify the potential pollutant-generating activities and the pollutant that is expected to be exposed to stormwater; b. Describe the location where the potential pollutant-generating activities will occur, or if identified on the site plan, reference the site plan; c. Identify all nonstormwater discharges, as authorized in Part I E of this general permit, that are or will be commingled with stormwater discharges from the construction activity, including any applicable support activity; d. Identify the person responsible for implementing the pollution prevention practice or practices for each pollutant-generating activity (if other than the person listed as the qualified personnel); e. Describe the pollution prevention practices and procedures that will be implemented to: (1) Prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, and cleaning up spills, leaks, and other Page 15 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part Ill G; (2) Prevent the discharge of spilled and leaked fuels and chemicals from vehicle fueling and maintenance activities (e.g., providing secondary containment such as spill berms, decks, spill containment pallets, providing cover where appropriate, and having spill kits readily available); (3) Prevent the discharge of soaps, solvents, detergents, and wash water from construction materials, including the clean-up of stucco, paint, form release oils, and curing compounds (e.g., providing (i) cover (e.g., plastic sheeting or temporary roofs) to prevent contact with stormwater; (ii) collection and proper disposal in a manner to prevent contact with stormwater; and (iii) a similarly effective means designed to prevent discharge of these pollutants); (4) Minimize the discharge of pollutants from vehicle and equipment washing, wheel wash water, and other types of washing (e.g., locating activities away from surface waters and stormwater inlets or conveyance and directing wash waters to sediment basins or traps, using filtration devices such as filter bags or sand filters, or using similarly effective controls); (5) Direct concrete wash water into a leak-proof container or leak-proof settling basin. The container or basin shall be designed so that no overflows can occur due to inadequate sizing or precipitation. Hardened concrete wastes shall be removed and disposed of in a manner consistent with the handling of other construction wastes. Liquid concrete wastes shall be removed and disposed of in a manner consistent with the handling of other construction wash waters and shall not be discharged to surface waters; (6) Minimize the discharge of pollutants from storage, handling, and disposal of construction products, materials, and wastes including (i) building products such as asphalt sealants, copper flashing, roofing materials, adhesives, and concrete admixtures; (ii) pesticides, herbicides, insecticides, fertilizers, and landscape materials; and (iii) construction and domestic wastes such as packaging materials, scrap construction materials, masonry products, timber, pipe and electrical cuttings, plastics, styrofoam, concrete, and other trash or building materials; (7) Prevent the discharge of fuels, oils, and other petroleum products, hazardous or toxic wastes, and sanitary wastes; and (8) Address any other discharge from the potential pollutant-generating activities not addressed above; and f. Describe procedures for providing pollution prevention awareness of all applicable wastes, including any wash water, disposal practices, and applicable disposal locations of such wastes, to personnel in order to comply with the conditions of this general permit. The operator shall implement the procedures described in the SWPPP. 5. SWPPP requirements for discharges to impaired waters, surface waters with an applicable TMDL wasteload allocation established and approved prior to the term of this general permit, and exceptional waters. The SWPPP shall: a. Identify the impaired water(s), approved TMDL(s), pollutant(s) of concern, and exceptional waters identified in 9VAC25-260-30 A 3 c, when applicable; b. Provide clear direction that: (1) Permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; Page 16 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) (2) Nutrients shall be applied in accordance with manufacturer's recommendations or an approved nutrient management plan and shall not be applied during rainfall events; and (3) A modified inspection schedule shall be implemented in accordance with Part I B 4 or Part I B 5. 6. Qualified personnel. The name, phone number, and qualifications of the qualified personnel conducting inspections required by this general permit. 7. Delegation of authority. The individuals or positions with delegated authority, in accordance with Part III K, to sign inspection reports or modify the SWPPP. 8. SWPPP signature. The SWPPP shall be signed and dated in accordance with Part III K. B. SWPPP amendments, modification, and updates. 1. The operator shall amend the SWPPP whenever there is a change in the design, construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters and that has not been previously addressed in the SWPPP. 2. The SWPPP must be amended if, during inspections or investigations by the operator's qualified personnel, or by local, state, or federal officials, it is determined that the existing control measures are ineffective in minimizing pollutants in discharges from the construction activity. Revisions to the SWPPP shall include additional or modified control measures designed and implemented to correct problems identified. If approval by the VESCP authority, VSMP authority, or department is necessary for the control measure, revisions to the SWPPP shall be completed no later than seven calendar days following approval. Implementation of these additional or modified control measures must be accomplished as described in Part II G. 3. The SWPPP must clearly identify the contractor(s) that will implement and maintain each control measure identified in the SWPPP. The SWPPP shall be amended to identify any new contractor that will implement and maintain a control measure. 4. The operator shall update the SWPPP no later than seven days following any modification to its implementation. All modifications or updates to the SWPPP shall be noted and shall include the following items: a. A record of dates when: (1) Major grading activities occur; (2) Construction activities temporarily or permanently cease on a portion of the site; and (3) Stabilization measures are initiated; b. Documentation of replaced or modified controls where periodic inspections or other information have indicated that the controls have been used inappropriately or incorrectly and where modified as soon as possible; c. Areas that have reached final stabilization and where no further SWPPP or inspection requirements apply; d. All properties that are no longer under the legal control of the operator and the dates on which the operator no longer had legal control over each property; e. The date of any prohibited discharges, the discharge volume released, and what actions were taken to minimize the impact of the release; f. Measures taken to prevent the reoccurrence of any prohibited discharge; and Page 17 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) • g. Measures taken to address any evidence identified as a result of an inspection required under Part II F. 5. Amendments, modifications, or updates to the SWPPP shall be signed in accordance with Part III K. C. Public Notification. Upon commencement of land disturbance, the operator shall post conspicuously a copy of the notice of coverage letter near the main entrance of the construction activity. For linear projects, the operator shall post the notice of coverage letter at a publicly accessible location near an active part of the construction project (e.g., where a pipeline crosses a public road). The operator shall maintain the posted information until termination of general permit coverage as specified in Part I F. D. SWPPP availability. 1. Operators with day-to-day operational control over SWPPP implementation shall have a copy of the SWPPP available at a central location on-site for use by those identified as having responsibilities under the SWPPP whenever they are on the construction site. 2. The operator shall make the SWPPP and all amendments, modifications, and updates available upon request to the department, the VSMP authority, the EPA, the VESCP authority, local government officials, or the operator of a municipal separate storm sewer system receiving discharges from the construction activity. If an on-site location is unavailable to store the SWPPP when no personnel are present, notice of the SWPPP's location must be posted near the main entrance of the construction site. 3. The operator shall make the SWPPP available for public review in an electronic format or in hard copy. Information for public access to the SWPPP shall be posted and maintained in accordance with Part II C. If not provided electronically, public access to the SWPPP may be arranged upon request at a time and at a publicly accessible location convenient to the operator or his designee but shall be no less than once per month and shall be during normal business hours. Information not required to be contained within the SWPPP by this general permit is not required to be released. E. SWPPP implementation. The operator shall implement the SWPPP and subsequent amendments, modifications, and updates from commencement of land disturbance until termination of general permit coverage as specified in Part I F. 1. All control measures must be properly maintained in effective operating condition in accordance with good engineering practices and, where applicable, manufacturer specifications. If a site inspection required by Part II F identifies a control measure that is not operating effectively, corrective action(s) shall be completed as soon as practicable, but no later than seven days after discovery or a longer period as established by the VSMP authority, to maintain the continued effectiveness of the control measures. 2. If site inspections required by Part II F identify an existing control measure that needs to be modified or if an additional control measure is necessary for any reason, implementation shall be completed prior to the next anticipated measurable storm event. If implementation prior to the next anticipated measurable storm event is impracticable, then alternative control measures shall be implemented as soon as practicable, but no later than seven days after discovery or a longer period as established by the VSMP authority. F. SWPPP Inspections. 1. Personnel responsible for on-site and off-site inspections. Inspections required by this general permit shall be conducted by the qualified personnel identified by the operator in the SWPPP. The operator is responsible for insuring that the qualified personnel conduct the inspection. Page 18 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) 2. Inspection schedule. a. Inspections shall be conducted at a frequency of: (1) At least once every five business days; or (2) At least once every 10 business days and no later than 48 hours following a measurable storm event. In the event that a measurable storm event occurs when there are more than 48 hours between business days, the inspection shall be conducted no later than the next business day. b. Where areas have been temporarily stabilized or land-disturbing activities will be suspended due to continuous frozen ground conditions and stormwater discharges are unlikely, the inspection frequency may be reduced to once per month. If weather conditions (such as above freezing temperatures or rain or snow events) make discharges likely, the operator shall immediately resume the regular inspection frequency. c. Representative inspections may be utilized for utility line installation, pipeline construction, or other similar linear construction activities provided that: (1) Temporary or permanent soil stabilization has been installed and vehicle access may compromise the temporary or permanent soil stabilization and potentially cause additional land disturbance increasing the potential for erosion; (2) Inspections occur on the same frequency as other construction activities; (3) Control measures are inspected along the construction site 0.25 miles above and below each access point (i.e., where a roadway, undisturbed right-of-way, or other similar feature intersects the construction activity and access does not compromise temporary or permanent soil stabilization); and (4) Inspection locations are provided in the report required by Part II F. 3. Inspection requirements. a. As part of the inspection, the qualified personnel shall: (1) Record the date and time of the inspection and when applicable the date and rainfall amount of the last measurable storm event; (2) Record the information and a description of any discharges occurring at the time of the inspection; (3) Record any land-disturbing activities that have occurred outside of the approved erosion and sediment control plan; (4) Inspect the following for installation in accordance with the approved erosion and sediment control plan, identification of any maintenance needs, and evaluation of effectiveness in minimizing sediment discharge, including whether the control has been inappropriately or incorrectly used: (a) All perimeter erosion and sediment controls, such as silt fence; (b) Soil stockpiles, when applicable, and borrow areas for stabilization or sediment trapping measures; (c) Completed earthen structures, such as dams, dikes, ditches, and diversions for stabilization; (d) Cut and fill slopes; (e) Sediment basins and traps, sediment barriers, and other measures installed to control sediment discharge from stormwater; (f) Temporary or permanent channel, flume, or other slope drain structures installed to convey concentrated runoff down cut and fill slopes; Page 19 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) (g) Storm inlets that have been made operational to ensure that sediment laden stormwater does not enter without first being filtered or similarly treated; and (h) Construction vehicle access routes that intersect or access paved roads for minimizing sediment tracking; (5) Inspect areas that have reached final grade or that will remain dormant for more than 14 days for initiation of stabilization activities; (6) Inspect areas that have reached final grade or that will remain dormant for more than 14 days for completion of stabilization activities within seven days of reaching grade or stopping work; (7) Inspect for evidence that the approved erosion and sediment control plan, "agreement in lieu of a plan," or erosion and sediment control plan prepared in accordance with department-approved annual standards and specifications has not been properly implemented. This includes but is not limited to: (a) Concentrated flows of stormwater in conveyances such as rills, rivulets or channels that have not been filtered, settled, or similarly treated prior to discharge , or evidence thereof; (b) Sediment laden or turbid flows of stormwater that have not been filtered or settled to remove sediments prior to discharge; (c) Sediment deposition in areas that drain to unprotected stormwater inlets or catch basins that discharge to surface waters. Inlets and catch basins with failing sediments controls due to improper installation, lack of maintenance, or inadequate design are considered unprotected; (d) Sediment deposition on any property (including public and private streets) outside of the construction activity covered by this general permit; (e) Required stabilization has not been initiated or completed on portions of the site; (f) Sediment basins without adequate wet or dry storage volume or sediment basins that allow the discharge of stormwater from below the surface of the wet storage portion of the basin; (g) Sediment traps without adequate wet or dry storage or sediment traps that allow the discharge of stormwater from below the surface of the wet storage portion of the trap; and (h) Land disturbance outside of the approved area to be disturbed; (8) Inspect pollutant generating activities identified in the pollution prevention plan for the proper implementation, maintenance and effectiveness of the procedures and practices; (9) Identify any pollutant generating activities not identified in the pollution prevention plan; and (10) Identify and document the presence of any evidence of the discharge of pollutants prohibited by this general permit. 4. Inspection report. Each inspection report shall include the following items: a. The date and time of the inspection and when applicable, the date and rainfall amount of the last measurable storm event; b. Summarized findings of the inspection; c. The location(s) of prohibited discharges; d. The location(s) of control measures that require maintenance; Page 20 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) e. The location(s) of control measures that failed to operate as designed or proved inadequate or inappropriate for a particular location; f. The location(s) where any evidence identified under Part II F 3 a (7) exists; g. The location(s) where any additional control measure is needed that did not exist at the time of inspection; h. A list of corrective actions required (including any changes to the SWPPP that are necessary ) as a result of the inspection or to maintain permit compliance; i. Documentation of any corrective actions required from a previous inspection that have not been implemented; and j. The date and signature of the qualified personnel and the operator or its duly authorized representative. The inspection report and any actions taken in accordance with Part II must be retained by the operator as part of the SWPPP for at least three years from the date that general permit coverage expires or is terminated. The inspection report shall identify any incidents of noncompliance. Where an inspection report does not identify any incidents of noncompliance, the report shall contain a certification that the construction activity is in compliance with the SWPPP and this general permit. The report shall be signed in accordance with Part III K of this general permit. G. Corrective actions. 1. The operator shall implement the corrective action(s) identified as a result of an inspection as soon as practicable but no later than seven days after discovery or a longer period as approved by the VSMP authority. If approval of a corrective action by a regulatory authority (e.g., VSMP authority, VESCP authority, or the department) is necessary, additional control measures shall be implemented to minimize pollutants in stormwater discharges until such approvals can be obtained. 2. The operator may be required to remove accumulated sediment deposits located outside of the construction activity covered by this general permit as soon as practicable in order to minimize environmental impacts. The operator shall notify the VSMP authority and the department as well as obtain all applicable federal, state, and local authorizations, approvals, and permits prior to the removal of sediments accumulated in surface waters including wetlands. PART I I I CONDITIONS APPLICABLE TO ALL VPDES PERMITS NOTE: Discharge monitoring is not required for this general permit. If the operator chooses to monitor stormwater discharges or control measures, the operator must comply with the requirements of subsections A, B, and C, as appropriate. A. Monitoring. 1. Samples and measurements taken for the purpose of monitoring shall be representative of the monitoring activity. 2. Monitoring shall be conducted according to procedures approved under 40 CFR Part 136 or alternative methods approved by the U.S. Environmental Protection Agency, unless other procedures have been specified in this general permit. Analyses performed according to test procedures approved under 40 CFR Part 136 shall be performed by an environmental laboratory certified under regulations adopted by the Department of General Services (1 VAC30-45 or 1 VAC30-46). Page 21 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) 3. The operator shall periodically calibrate and perform maintenance procedures on all monitoring and analytical instrumentation at intervals that will ensure accuracy of measurements. B. Records. 1. Monitoring records and reports shall include: a. The date, exact place, and time of sampling or measurements; b. The individual(s) who performed the sampling or measurements; c. The date(s) and time(s) analyses were performed; d. The individual(s) who performed the analyses; e. The analytical techniques or methods used; and f. The results of such analyses. 2. The operator shall retain records of all monitoring information, including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, copies of all reports required by this general permit, and records of all data used to complete the registration statement for this general permit, for a period of at least three years from the date of the sample, measurement, report or request for coverage. This period of retention shall be extended automatically during the course of any unresolved litigation regarding the regulated activity or regarding control standards applicable to the operator, or as requested by the board. C. Reporting monitoring results. 1. The operator shall update the SWPPP to include the results of the monitoring as may be performed in accordance with this general permit, unless another reporting schedule is specified elsewhere in this general permit. 2. Monitoring results shall be reported on a discharge monitoring report (DMR); on forms provided, approved or specified by the department; or in any format provided that the date, location, parameter, method, and result of the monitoring activity are included. 3. If the operator monitors any pollutant specifically addressed by this general permit more frequently than required by this general permit using test procedures approved under 40 CFR Part 136 or using other test procedures approved by the U.S. Environmental Protection Agency or using procedures specified in this general permit, the results of this monitoring shall be included in the calculation and reporting of the data submitted in the DMR or reporting form specified by the department. 4. Calculations for all limitations which require averaging of measurements shall utilize an arithmetic mean unless otherwise specified in this general permit. D. Duty to provide information. The operator shall furnish, within a reasonable time, any information which the board may request to determine whether cause exists for modifying, revoking and reissuing, or terminating this general permit or to determine compliance with this general permit. The board, department, EPA, or VSMP authority may require the operator to furnish, upon request, such plans, specifications, and other pertinent information as may be necessary to determine the effect of the wastes from his discharge on the quality of surface waters, or such other information as may be necessary to accomplish the purposes of the CWA and the Virginia Stormwater Management Act. The operator shall also furnish to the board, department, EPA, or VSMP authority, upon request, copies of records required to be kept by this general permit. E. Compliance schedule reports. Reports of compliance or noncompliance with, or any progress reports on, interim and final requirements contained in any compliance schedule of this general permit shall be submitted no later than 14 days following each schedule date. Page 22 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) F. Unauthorized stormwater discharges. Pursuant to § 62.1-44.5 of the Code of Virginia, except in compliance with a state permit issued by the department, it shall be unlawful to cause a stormwater discharge from a construction activity. G. Reports of unauthorized discharges. Any operator who discharges or causes or allows a discharge of sewage, industrial waste, other wastes or any noxious or deleterious substance or a hazardous substance or oil in an amount equal to or in excess of a reportable quantity established under either 40 CFR Part 110, 40 CFR Part 117, 40 CFR Part 302, or § 62.1- 44.34:19 of the Code of Virginia that occurs during a 24-hour period into or upon surface waters or who discharges or causes or allows a discharge that may reasonably be expected to enter surface waters, shall notify the Department of Environmental Quality of the discharge immediately upon discovery of the discharge, but in no case later than within 24 hours after said discovery. A written report of the unauthorized discharge shall be submitted to the department and the VSMP authority within five days of discovery of the discharge. The written report shall contain: 1. A description of the nature and location of the discharge; 2. The cause of the discharge; 3. The date on which the discharge occurred; 4. The length of time that the discharge continued; 5. The volume of the discharge; 6. If the discharge is continuing, how long it is expected to continue; 7. If the discharge is continuing, what the expected total volume of the discharge will be; and 8. Any steps planned or taken to reduce, eliminate and prevent a recurrence of the present discharge or any future discharges not authorized by this general permit. Discharges reportable to the department and the VSMP authority under the immediate reporting requirements of other regulations are exempted from this requirement. H. Reports of unusual or extraordinary discharges. If any unusual or extraordinary discharge including a "bypass" or "upset", as defined herein, should occur from a facility and the discharge enters or could be expected to enter surface waters, the operator shall promptly notify, in no case later than within 24 hours, the department and the VSMP authority by telephone after the discovery of the discharge. This notification shall provide all available details of the incident, including any adverse effects on aquatic life and the known number of fish killed. The operator shall reduce the report to writing and shall submit it to the department and the VSMP authority within five days of discovery of the discharge in accordance with Part III 12. Unusual and extraordinary discharges include but are not limited to any discharge resulting from: 1. Unusual spillage of materials resulting directly or indirectly from processing operations; 2. Breakdown of processing or accessory equipment; 3. Failure or taking out of service of some or all of the facilities; and 4. Flooding or other acts of nature. I. Reports of noncompliance. The operator shall report any noncompliance which may adversely affect surface waters or may endanger public health. 1. An oral report to the department and the VSMP authority shall be provided within 24 hours from the time the operator becomes aware of the circumstances. The following shall be included as information that shall be reported within 24 hours under this subdivision: Page 23 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) a. Any unanticipated bypass; and b. Any upset that causes a discharge to surface waters. 2. A written report shall be submitted within five days and shall contain: a. A description of the noncompliance and its cause; b. The period of noncompliance, including exact dates and times, and if the noncompliance has not been corrected, the anticipated time it is expected to continue; and c. Steps taken or planned to reduce, eliminate, and prevent reoccurrence of the noncompliance. The department may waive the written report on a case-by-case basis for reports of noncompliance under Part Ill I if the oral report has been received within 24 hours and no adverse impact on surface waters has been reported. 3. The operator shall report all instances of noncompliance not reported under Part III 11 or 2 in writing as part of the SWPPP. The reports shall contain the information listed in Part Ill 12. NOTE: The reports required in Part III G, H and I shall be made to the department and the VSMP authority. Reports may be made by telephone, email, or by fax. For reports outside normal working hours, leaving a recorded message shall fulfill the immediate reporting requirement. For emergencies, the Virginia Department of Emergency Management maintains a 24-hour telephone service at 1-800-468-8892. 4. Where the operator becomes aware of a failure to submit any relevant facts, or submittal of incorrect information in any report, including a registration statement, to the department or the VSMP authority, the operator shall promptly submit such facts or correct information. J. Notice of planned changes. 1. The operator shall give notice to the department and the VSMP authority as soon as possible of any planned physical alterations or additions to the permitted facility or activity. Notice is required only when: a. The operator plans an alteration or addition to any building, structure, facility, or installation that may meet one of the criteria for determining whether a facility is a new source in 9VAC25-870-420; b. The operator plans an alteration or addition that would significantly change the nature or increase the quantity of pollutants discharged. This notification applies to pollutants that are not subject to effluent limitations in this general permit; or 2. The operator shall give advance notice to the department and VSMP authority of any planned changes in the permitted facility or activity, which may result in noncompliance with state permit requirements. K. Signatory requirements. 1. Registration statement. All registration statements shall be signed as follows: a. For a corporation: by a responsible corporate officer. For the purpose of this chapter, a responsible corporate officer means: (i) a president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy-making or decision-making functions for the corporation; or (ii) the manager of one or more manufacturing, production, or operating facilities, provided the manager is authorized to make management decisions that govern the operation of the regulated facility including having the Page 24 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) explicit or implicit duty of making major capital investment recommendations, and initiating and directing other comprehensive measures to assure long-term compliance with environmental laws and regulations; the manager can ensure that the necessary systems are established or actions taken to gather complete and accurate information for state permit application requirements; and where authority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures; b. For a partnership or sole proprietorship: by a general partner or the proprietor, respectively; or c. For a municipality, state, federal, or other public agency: by either a principal executive officer or ranking elected official. For purposes of this chapter, a principal executive officer of a public agency includes: (i) the chief executive officer of the agency or (ii) a senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency. 2. Reports, etc. All reports required by this general permit, including SWPPPs, and other information requested by the board or the department shall be signed by a person described in Part III K 1 or by a duly authorized representative of that person. A person is a duly authorized representative only if: a. The authorization is made in writing by a person described in Part III K 1; b. The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the operator. (A duly authorized representative may thus be either a named individual or any individual occupying a named position); and c. The signed and dated written authorization is included in the SWPPP. A copy must be provided to the department and VSMP authority, if requested. 3. Changes to authorization. If an authorization under Part III K 2 is no longer accurate because a different individual or position has responsibility for the overall operation of the construction activity, a new authorization satisfying the requirements of Part III K 2 shall be submitted to the VSMP authority as the administering entity for the board prior to or together with any reports or information to be signed by an authorized representative. 4. Certification. Any person signing a document under Part III K 1 or 2 shall make the following certification: "I certify under penalty of law that I have read and understand this document and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." L. Duty to comply. The operator shall comply with all conditions of this general permit. Any state permit noncompliance constitutes a violation of the Virginia Stormwater Management Act and the Clean Water Act, except that noncompliance with certain provisions of this general permit may constitute a violation of the Virginia Stormwater Management Act but not the Clean Water Act. Permit noncompliance is grounds for enforcement action; for state permit Page 25 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) termination, revocation and reissuance, or modification; or denial of a state permit renewal application. - The operator shall comply with effluent standards or prohibitions established under § 307(a) of the Clean Water Act for toxic pollutants within the time provided in the regulations that establish these standards or prohibitions or standards for sewage sludge use or disposal, even if this general permit has not yet been modified to incorporate the requirement. M. Duty to reapply. If the operator wishes to continue an activity regulated by this general permit after the expiration date of this general permit, the operator shall submit a new registration statement at least 90 days before the expiration date of the existing general permit, unless permission for a later date has been granted by the board. The board shall not grant permission for registration statements to be submitted later than the expiration date of the existing general permit. N. Effect of a state permit. This general permit does not convey any property rights in either real or personal property or any exclusive privileges, nor does it authorize any injury to private property or invasion of personal rights, or any infringement of federal, state or local law or regulations. O. State law. Nothing in this general permit shall be construed to preclude the institution of any legal action under, or relieve the operator from any responsibilities, liabilities, or penalties established pursuant to any other state law or regulation or under authority preserved by § 510 of the Clean Water Act. Except as provided in general permit conditions on "bypassing" (Part III U) and "upset" (Part III V), nothing in this general permit shall be construed to relieve the operator from civil and criminal penalties for noncompliance. P. Oil and hazardous substance liability. Nothing in this general permit shall be construed to preclude the institution of any legal action or relieve the operator from any responsibilities, liabilities, or penalties to which the operator is or may be subject under §§ 62.1-44.34:14 through 62.1-44.34:23 of the State Water Control Law or § 311 of the Clean Water Act. Q. Proper operation and maintenance. The operator shall at all times properly operate and maintain all facilities and systems of treatment and control (and related appurtenances), which are installed or used by the operator to achieve compliance with the conditions of this general permit. Proper operation and maintenance also includes effective plant performance, adequate funding, adequate staffing, and adequate laboratory and process controls, including appropriate quality assurance procedures. This provision requires the operation of back-up or auxiliary facilities or similar systems, which are installed by the operator only when the operation is necessary to achieve compliance with the conditions of this general permit. R. Disposal of solids or sludges. Solids, sludges or other pollutants removed in the course of treatment or management of pollutants shall be disposed of in a manner so as to prevent any pollutant from such materials from entering surface waters and in compliance with all applicable state and federal laws and regulations. S. Duty to mitigate. The operator shall take all steps to minimize or prevent any discharge in violation of this general permit that has a reasonable likelihood of adversely affecting human health or the environment. T. Need to halt or reduce activity not a defense. It shall not be a defense for an operator in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this general permit. U. Bypass. 1. "Bypass," as defined in 9VAC25-870-10, means the intentional diversion of waste streams from any portion of a treatment facility. The operator may allow any bypass to occur that does not cause effluent limitations to be exceeded, but only if it also is for Page 26 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 711/2014) essential maintenance to ensure efficient operation. These bypasses are not subject to the provisions of Part III U 2 and 3. 2. Notice. a. Anticipated bypass. If the operator knows in advance of the need for a bypass, the operator shall submit prior notice to the department, if possible at least 10 days before the date of the bypass. b. Unanticipated bypass. The operator shall submit notice of an unanticipated bypass as required in Part III I. 3. Prohibition of bypass. a. Except as provided in Part III U 1, bypass is prohibited, and the board or department may take enforcement action against an operator for bypass unless: (1) Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage. Severe property damage means substantial physical damage to property, damage to the treatment facilities that causes them to become inoperable, or substantial and permanent loss of natural resources that can reasonably be expected to occur in the absence of a bypass. Severe property damage does not mean economic loss caused by delays in production; (2) There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass that occurred during normal periods of equipment downtime or preventive maintenance; and (3) The operator submitted notices as required under Part III U 2. b. The department may approve an anticipated bypass, after considering its adverse effects, if the department determines that it will meet the three conditions listed in Part Ill U 3 a. V. Upset. 1. An "upset," as defined in 9VAC25-870-10, means an exceptional incident in which there is unintentional and temporary noncompliance with technology-based state permit effluent limitations because of factors beyond the reasonable control of the operator. An upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation. 2. An upset constitutes an affirmative defense to an action brought for noncompliance with technology-based state permit effluent limitations if the requirements of Part Ill V 4 are met. A determination made during administrative review of claims that noncompliance was caused by upset, and before an action for noncompliance, is not a final administrative action subject to judicial review. 3. An upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventative maintenance, or careless or improper operation. 4. An operator who wishes to establish the affirmative defense of upset shall demonstrate, through properly signed, contemporaneous operating logs or other relevant evidence that: a. An upset occurred and that the operator can identify the cause(s) of the upset; b. The permitted facility was at the time being properly operated; Page 27 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) c. The operator submitted notice of the upset as required in Part III I; and d. The operator complied with any remedial measures required under Part III S. 5. In any enforcement proceeding, the operator seeking to establish the occurrence of an upset has the burden of proof. W. Inspection and entry. The operator shall allow the department as the board's designee, the VSMP authority, EPA, or an authorized representative of either entity (including an authorized contractor), upon presentation of credentials and other documents as may be required by law to: 1. Enter upon the operator's premises where a regulated facility or activity is located or conducted, or where records must be kept under the conditions of this general permit; 2. Have access to and copy, at reasonable times, any records that must be kept under the conditions of this general permit; 3. Inspect and photograph at reasonable times any facilities, equipment (including monitoring and control equipment), practices, or operations regulated or required under this general permit; and 4. Sample or monitor at reasonable times, for the purposes of ensuring state permit compliance or as otherwise authorized by the Clean Water Act or the Virginia Stormwater Management Act, any substances or parameters at any location. For purposes of this section, the time for inspection shall be deemed reasonable during regular business hours, and whenever the facility is discharging. Nothing contained herein shall make an inspection unreasonable during an emergency. X. State permit actions. State permits may be modified, revoked and reissued, or terminated for cause. The filing of a request by the operator for a state permit modification, revocation and reissuance, or termination, or a notification of planned changes or anticipated noncompliance does not stay any state permit condition. Y. Transfer of state permits. 1. State permits are not transferable to any person except after notice to the department. Except as provided in Part III Y 2, a state permit may be transferred by the operator to a new operator only if the state permit has been modified or revoked and reissued, or a minor modification made, to identify the new operator and incorporate such other requirements as may be necessary under the Virginia Stormwater Management Act and the Clean Water Act. 2. As an alternative to transfers under Part III Y 1, this state permit may be automatically transferred to a new operator if: a. The current operator notifies the department at least 30 days in advance of the proposed transfer of the title to the facility or property; b. The notice includes a written agreement between the existing and new operators containing a specific date for transfer of state permit responsibility, coverage, and liability between them; and c. The department does not notify the existing operator and the proposed new operator of its intent to modify or revoke and reissue the state permit. If this notice is not received, the transfer is effective on the date specified in the agreement mentioned in Part III Y 2 b. 3. For ongoing construction activity involving a change of operator, the new operator shall accept and maintain the existing SWPPP, or prepare and implement a new SWPPP prior to taking over operations at the site. Page 28 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) Z. Severability. The provisions of this general permit are severable, and if any provision of this general permit or the application of any provision of this state permit to any circumstance, is held invalid, the application of such provision to other circumstances and the remainder of this general permit shall not be affected thereby. 9VAC25-880-80. (Repealed.) 9VAC25-880-82. (Repealed.) 9VAC25-880-84. (Repealed.) 9VAC25-880-86. (Repealed.) 9VAC25-880-88. (Repealed.) 9VAC25-880-90. (Repealed.) 9VAC25-880-100. Delegation of authority. The director, or his designee, may perform any act of the board provided under this chapter, except as limited by § 62.1-44.14 of the Code of Virginia. FORMS (9VAC25-880) Department of Environmental Quality Construction Activity Operator Permit Fee Form (rev. 01/2014) Notice of Termination - General VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10) (rev. 01/2014) Registration Statement - General VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10) (rev. 01/2014) Transfer Agreement - General VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10) (rev. 01/2014) Page 29 of 29 9VAC25-880 (adopted 12/17/2013 - published 2/24/2014 - effective 7/1/2014) • APPENDIX C CERTIFICATION FORMS Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 ' I OPERATOR CERTIFICATIONS Project Name:Church Road Stormwater Management Facility Retrofit Project Location:Albemarle County,VA The contractor and subcontractor(s)that will implement the pollutant control measures described in the SWPPP must be identified below. Each must sign a statement certifying that they understand the VPDES general permit authorizing storm water discharges during construction. These statements must be maintained in the SWPPP file on site. Operator or subcontractor implementing the SWPPP: Ale-e4 ,,vien.'etre'/I(t ,Zt e; Business Name Rg9 I owe? -c/free Business Address �l/tNreeh, ^S;�r.,� NG 27/o/ 3:36, 7AS -A 0/0 Business Telephone Number Activities operator or subcontractor responsible for: CERTIFICATION: "I certifj'under penalty of law that I understand the terms and conditions of the VPDES General Permit for Discharges of Stornnvater from Construction Activities(VAR 10)and the SWPPP that authorizes storm water discharges associated with land disturbing activities from the construction site identified as part of this certification." o y Signature D� Printed Name Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job#113038014 APPENDIX D INSPECTION REPORT Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 STORM WATER POLLUTION PREVENTION PLAN INSPECTION REPORT Project Name: Church Road Stormwater Management Facility Retrofit Location: Albemarle County,VA Contractor: Anticipated Completion Date: Inspection Date: Inspector: Inspector's Qualifications: SITE CONDITIONS: POLLUTANT CONTROL IN EFFECTIVE LOCATION OF Non Conformance CONFORMANCE Construction Entrance YES/NO/NA YES/NO/NA Sediment Barriers YES/NO/NA YES/NO/NA Storage/Disposal Areas YES/NO/NA YES/NO/NA Sediment Traps YES/NO/NA YES/NO/NA Check Dams YES/NO/NA YES/NO/NA Inlet Protection YES/NO/NA YES/NO/NA VIOLATIONS NOTED: (Explain each "NO" circled above) REMEDIAL ACTIONS TO BE TAKEN: COMMENTS: Based on the results of the inspection,necessary control modifications shall be implemented within 7 calendar days. This report shall be kept on file by the General Contractor as part of the Storm Water Pollution Prevention Plan for at least 3 years from the date of completion and submission of the Notice of Termination. Certification Statement "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system,or those persons directly responsible for gathering the information,the information submitted is,to the best of my knowledge and belied true,accurate,and complete. I am aware that there are significant penalties for submitting false information,including the possibility of fine and imprisonment for knowing violations. Name: Address: Phone: Date: (Authorized Signature) Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 APPENDIX E NOTICE OF TERMINATION Two copies of the Notice of Termination shall be completed by the Operator when construction activities that disturb site soil have been completed and the site has achieved fmal stabilization. In addition, a list of permanent stormwater Best Management Practices (BMPs) installed on site must be prepared. For each permanent BMP, the following information must be submitted: name of the BMP (i.e. Permanent Wet Pond 1; Hydrodynamic Separator 1; Oil Water Separator 1; Permanent Seeded Area, etc.), the site acreage treated by the BMP, the name of the water body receiving runoff treated by the BMP and the 8-digit Hydrologic Unit Code (HUC) of the receiving water body receiving runoff treated by the BMP. One NOT shall be forwarded to the Project Owner. The other NOT shall be sent via registered or certified mail, with return receipt requested, to the following address: Department of Environmental Quality Office of Stormwater Permits, 10th Floor P.O. Box 1105 Richmond, VA 23218 Permit coverage is terminated as of the date the lot is transferred to a new owner, coverage under a new VPDES permit is obtained, or as of the date another Operator assumes control over portions of the site not stabilized. In these situations, coverage under the permit terminated at midnight the date the Notice of Termination (NOT) is filed. Where the Operator seeks to terminate coverage because the site has reached fmal stabilization, termination will become effective upon concurrence by the VSMP Authority, or after 60 days from the submittal of the NOT have passes, whichever occurs first. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 General Permit for Discharges of Stormwater from Construction Activities (VAR10) • - Notice of Termination • (Please Type or Print All Information) - 1. Construction Activity Operator: - Name: Mailing Address: - City: State: Zip: Phone: Email address(if available): 2. Location of Construction Activity (As listed on registration statement): Name: Address: City: State: Zip: County: If street address unavailable: Latitude Longitude 3. Stormwater General Permit Number: 4. The Reason for Terminating Coverage Under the General Permit (The construction activity operator may only submit a Notice of Termination after one or more of the conditions below have been met): ❑ A. Necessary post-construction control measures included in the SWPPP for the site are in place and functioning effectively and final stabilization has been achieved on all portions of the site for which the operator is responsible; ❑' B. Another operator has assumed control over all areas of the site that have not been finally stabilized and obtained coverage for the ongoing discharge; ❑' C. Coverage under an alternative VPDES or State permit has been obtained; or ❑' D. For residential construction only temporary stabilization has been completed and the residence has been transferred to the homeowner. The Notice of Termination must be submitted within 30 days of one of the above conditions being met. Authorization to discharge terminates at midnight on the date that the Notice of Termination is submitted for conditions B through D above. Authorization to discharge terminates upon notification from the Department or 60 days after the submittal of the Notice of Termination(whichever occurs first)for condition A above. 5. Permanent Control Measures Installed: Attach a list of permanent control measures (both structural and non-structural) that were installed at the construction site. For each control measure, include the following information: (a) Type of control measure installed and the date that it became functional as a permanent control measure; (b) Geographic location (county or city and Hydrologic Unit Code) (latitude and longitude may additionally be included if available); (c) Waterbody the control measure discharges into; and, (d) Number of acres that will be treated (to the nearest one-tenth of an acre). If no permanent control measures were installed please check this box D. 6. Participation in a Regional Stormwater Management Plan: Where applicable, attach the following information related to participation in a regional stormwater management plan: (a) Type of regional facility to which the site discharges; (b) Geographic location of any regional facility to which the site discharges (county or city and Hydrologic Unit Code); (c) Geographic location of the site (county or city and Hydrologic Unit Code) (latitude and longitude may additionally be included if available); and (d) Number of acres treated by a regional facility. 7. Nutrient Offsets: Where applicable, attach the following information related to nutrient offsets that were acquired in accordance with §62.1-44.15:35 of the Code of Virginia: (a) Name of the broker from which offsets were acquired; (b) Geographic location (county or city and Hydrologic Unit Code)of the broker's offset generating facility; (c) Number of nutrient offsets acquired (lbs. per acre per year);and (d) Nutrient reductions achieved on site(lbs. per acre per year). 8. Certification: "I certify under penalty of law that I have read and understand this notice of termination and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations." Print Name: Title: Signature: Date: (Please sign in INK.The person signing this form must be associated with the operator identified in Item #1 above.) Mail to: Department of Environmental Quality, Office of Stormwater Management, 10`h Floor, P.O. Box 1105, Richmond,VA 23218 (DEQ 199-147) (08/13) INSTRUCTIONS for FORM DEQ 199-147 General Permit Notice of Termination -Construction Activity Stormwater Discharges General - (c) Waterbody the control measure discharges into; and, A Notice of Termination must be submitted when an (d) Number of acres that will be treated (to the nearest operator no longer wishes to be covered under the General one-tenth of an acre). Permit for Stormwater Discharges from Construction If no permanent control measures were installed, please Activities. check the box at the end of this section. Mail to: Department of Environmental Quality Office of Stormwater Management, 10th Floor Section 6 Participation in a Regional Stormwater P.O. Box 1105 Management Plan Richmond,VA 23218 Where applicable, attach the following information related to participation in a regional stormwater management plan: (a) Type of regional facility to which the site discharges; (b) Section 1 Activity Operator Information Geographic location of any regional facility to which the site Give the legal name of the person,firm, public organization, discharges (county or city and Hydrologic Unit Code); (c) or any other entity that was issued the general permit for Geographic location of the site (county or city and the site described in this Notice of Termination. Do not use Hydrologic Unit Code) (latitude and longitude may a colloquial name. Enter the complete address and phone additionally be included if available); and, (d) Number of number of the operator. acres treated by a regional facility. Section 2 Activity Location Information Section 7 Nutrient Offsets Enter the activity's official name and complete street Where applicable, attach the following information related to address, including city (or town), county (if not located nutrient offsets that were acquired in accordance with within a City), state and ZIP code. If the site lacks a street §62.1-44.15:35 of the Code of Virginia: (a) Name of the address, enter the city (or town), county (if not located within a City) and the latitude and longitude in degrees, broker from which offsets were acquired; (b) Geographic minutes, seconds(DMS). location (county or city and Hydrologic Unit Code) of the broker's offset generating facility; (c) Number of nutrient Section 3 Permit Information offsets acquired (lbs. per acre per year); and (d) Nutrient Enter the existing Stormwater General Permit Number reductions achieved on site(lbs. per acre per year). assigned to the activity or site identified in Section 1 that the operator wishes to be terminated. Section 8 Certification State statutes provide for severe penalties for submitting Section 4 Reason for Termination false information on this Notice of Termination. State Check the appropriate statement indicating the reason for regulations require this Notice of Termination to be signed submitting this Notice of Termination. The Notice of as follows: Termination may only be submitted after one or more of the For a corporation: by a responsible corporate following conditions have been met: officer. For the purpose of this section, a responsible A. Necessary post-construction control measures corporate officer means: (1) A president, secretary, included in the SWPPP for the site are in place and treasurer, or vice-president of the corporation in charge of a functioning and final stabilization has been achieved principal business function, or any other person who on all portions of the site for which the operator is performs similar policy-or decision-making functions for the responsible; corporation, or (2) the manager of one or more B. Another operator has assumed control over all areas manufacturing, production, or operating facilities provided of the site that have not been finally stabilized; the manager is authorized to make management decisions C. Coverage under an alternative VPDES or State which govern the operation of the regulated facility including permit has been obtained; or having the explicit or implicit duty of making major capital D. For residential construction only, temporary investment recommendations, and initiating and directing stabilization has been completed and the residence other comprehensive measures to assure long term has been transferred to the homeowner. environmental compliance with environmental laws and The Notice of Termination must be submitted within 30 regulations; the manager can ensure that the necessary days of one of the above conditions being met. systems are established or actions taken to gather complete and accurate information for permit application Section 5 Permanent Control Measures Installed requirements; and where authority to sign documents has Attach a list of the permanent control measures (both been assigned or delegated to the manager in accordance structural and non-structural) that were installed at the with corporate procedures. construction site. For each control measure, include the For a partnership or sole proprietorship: by a following information: general partner or the proprietor. (a) Type of control measure installed; For a municipality, state, federal, or other public (b) Geographic location (county or city and Hydrologic agency: by either a principal executive officer or a ranking Unit Code); elected official. The Department of Environmental Quality reserves the right to request additional information not directly addressed by the registration statement if.in its discretion,a facility or operation poses a potential impact on water quality. (DEQ 199-147) (08/13) APPENDIX F RECORD OF STABILIZATION AND CONSTRUCTION ACTIVITY DATES Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 SITE STABILIZATION_and CONSTRUCTION ACTIVITY DATES A record of dates when land disturbing activities occur, when construction activities temporarily or permanently cease on a portion of the site, and when stabilization measures are initiated shall be maintained by the Operator until final site stabilization is achieved and the Notice of Termination is filed. The dates can be entered in the following form, or on a different form. LAND DISTURBING ACTIVITIES Description of Activity: Begin(date): Site Contractor: Location: End(date): Description of Activity: Begin (date): Site Contractor: Location: End(date): Description of Activity: Begin (date): Site Contractor: Location: End(date): Description of Activity: Begin (date): Site Contractor: Location: End(date): Description of Activity: Begin (date): Site Contractor: Location: End (date): Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 APPENDIX G SELECTED EROSION AND SEDIMENT CONTROL SITE PLAN SHEETS Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 . W U) J J 0 z r W ZO w O W W -. _ d Z O O n J J J J 11 0000 IWWC GO HF- HH r 1 Z Z Z Z l • 0 0 0 0 H H H H H Q _1 ZZZZF- 0 1 11 W W W W W 0) • l 2 2 2 20 fA � M r- 2 O F— II Z co W' WOHF- (,W BZ . • � WWW LLI W W / 0 g .I .l o .I C C/ F - 0 Z O co M I I = 11 1 (7 J Z Z Z Z Z_ Z_ Z_ W (1) 11 Z , i a , O_ OOOHHHH Q � W I,is O w fn U) C!1 U) V) Z Z Z W O W u_ H < w itxX [tog -1 � Qa E- H C ► 1 0 1 W W W W O C O d 0 W 0 F- m X 0W O H W � w 0 0 - Ncv � u, (O 00 H.. Z l•IA atv CK Z ,s Yi1 >.‘ 0 ' � L 6 a �W; N. Elm. - -- g g W O 0 0 _ W Q z O CeLij C�CC •a Q 0 z o_ w M H. = 0 0 U) U) Ww < l ' O Z "ct ' , . < (.1 pQaJ I2 CK < ILI i I R ‘--0 N cozz OZ uj N-- 6� -_- z M — _, W co U 1 O ..:4- w m J 0 Ct *N W � wH2 UW Qz LLI =u) 2 Z w 0 >■ CIO (: D W V- Qd ` d Q ? Q w � o�,o `� O Z Z W 2 F > f� d?� y �]� <, Q > z 3 m a UJ W pct - wow N o D i m 0 (n om � o w r O � ~� � = Z aQ 0,, < m m J z u } U V` � � W � y b o a U H o2z Y H 2 < ..... .- -- ` � C)>- N v, w �OmZ ' S a 0 Qom c CO Z w N T zO C•) W SSS ! i:U E g P;E g (f) ›,--\e' , , . ,, –..‹,,, ,4 . �R .. ^...r W 111 ,L- � 0.- n ? i w ate tl \ '4 " '' �. \` ki" a a ut N. F- ( g — Illm emfD s ,d' f ,. "s '` ,, ,o,, yy 1 " )�w , o t f :� _' P A F G.` '. Y \ ,',., r,-,–, , V ., N w f lY aul'wlw,00eey Duo woH-A0!w!h of XI N.11 nog;!-aq IW4e So!'sa)ol...V puo..1-1-4,1w II Aq uo!)oldopo Duo iolloz!nq;o ualiun�no4l!*puawnaop a!4 uo a udaidwl puo.o aanay pamda.d eo.l!4o!4n ion lua!P POD aaodind>!Ilaadc agl,oy Ago papualul ai, as io luawnAkaui,uo co Cosy paluaea�d a,..,,,puo a,daawa e4�4HM O,,og �uawnoop ep 6mp'133H5 31111 l\0°ps uo!d\oay0\,(q;lpod 4al00500 0 aluowaglV blo9£O£ll\AN3 9VA\p wdbb fi££0 P lot '/0 4ago)o0 133H5 3110 u' l:ro,Co1 ua4orwdo}S aluowaglV b109£O£ll 1aS 7aags pop')dog/Po;old CC w CO I z W Li U I N i b U M = o apt o i 0 IN mm O_ a j / (� < Z n 1�yy ! F p...... / = a ; z 0 Fa CD W W / 3 7 y m Z / y0 ��', a 5 c g ,b a 0 I 2 rl 1271 r. , . , II :43::::, siti QE/ /;; i' e��.0 h t4 - :1 o 1` � ? �lil • v < y LL 'lE $.,• '',viii.: M :is.; ��� \� �' w O LI i%i pew �� Q F— " ,s; H D 0 Li u) g O � O .,:; a ; ' ,,' R.'! it, ir + 1 .♦��♦� � 3. . a a } ♦r° { , J� i '_ ♦ AE �< „F.', u V o o S W w W• Q u- L- � \ 1 Q� \ ° h1,! !r �- \ � 1.2 a ct z w• w CO 1k .fI � _ � I;go v :� w � 1.��; -. © ` � 7 OCS O y �, g; ' , z 1 2 2 L / o' ` o z oW 3'• ` I S g o pa D <k € 8 , Z k i t _ A ia` r♦�®9 A. , a zpzLL F j ms. fi € k : gVoii l •♦♦S, _E ...,:-;44-0,;:e.;;:-.*:. .'.�,, a ®♦i.A♦ W C m t . rr, � }♦o OWW, o ; , . AAA♦• \ �0W 3 m o{0€ E-,1 ka .9 A V\ a,, # � y�♦�♦®♦ _1, TA♦♦ I o o w= n m •,.!: >m: „,.;44,4.,. ; ♦AA♦ :i a ”`?1AA♦ _s r�1.p, . 1♦A A♦A A4 `i .6,0/4 e J a o o^ Q 3 g,E _ s E Wa 3 pt 'i k A♦AA♦•♦ y a 6♦A♦ ' Y o ,.i i I € * ♦AA♦Ai •a . ♦ \E V ♦ ¢�y ' ♦♦♦♦♦♦ 43...4** A, \ 0 Y Q A� b a�♦♦A A A'" A®♦♦ O a .♦d �j pp e♦A 1 A*4 ♦••••♦ a ik'Ik 9 ; ,♦A♦♦4 ♦♦ , r a �♦y k ♦♦♦ a �♦ �♦♦• ;,„,,7 A 1 i t 1 ♦♦♦ a i i♦ w,..0 1A ■ �y♦ 1{ �AAy€ I � � ♦4 4 ® K_ � Off►_ 4, 1♦e♦ \ .i N®�� 2 ♦A, 44° ;„ 1 1 ,,,I.: "7,air, € :5 ` AA • ♦A1•A♦AA♦A A♦♦ a.�`�• t!� 1 m mo > ' �♦♦ �t,♦ \ A W♦ :' ♦ m/ a ♦�♦ $ C •••• ♦•N ; d0♦♦♦1 •i@ 41;. Fie 1 = y Q o♦♦ t A•y . \ A♦AA A ♦.Ai 1A:A• ♦�A� ■ 'A♦♦♦ 1 a a ♦♦ A♦ a AiAAA ,i�♦A♦A w"§■s •OAv, a 1.♦ A.A, s♦ ' 5; 1 ww '` d A♦ ♦ W 1 AAA i ti' .yam♦♦ g¢ o o i J ®A A 4 a , 1 ♦i e ! , : o- ∎♦♦* ♦ 1,,,f0-4-- 0 Af �A A , a w A•♦A a 1♦ g AI JA` i Af At♦"♦:4. ' , I v 4 t tr t i a a,1 „4.,-4:-,...,. ,:s3 AgA!., II: !i € 1\i, { iA♦♦ : a a ♦o y , /' w$ j' t r E F ►AAf d .. 8 4`k', € E k k S F i t a •O A j a a-4 , a i`00 A' ` J W LLLL I e r 1 t ` k 1♦AA♦♦A♦♦. a ♦s®AA• x.� ''' A♦i. A i i 4 k ; i - , w 0 : LA‘s.:,i . Wo. .',,,1 - '.,.,:ii--,,,,;.;.:•.1....,. ,,,..„—=..sly,t,„ -....:,:s.' ;.,, r.,., ', ,, , ', ; .,.. .,..,, :R . , i i ii; ;.L•fi'l',',;T •: : : ', ‘ • 2"-, 4.--7""k,,, ve,10,1•41",..„oroa"'"==‘,„ ,,, ' „: , ,, , ,., , , ,,,,,1,,,f:-,-,, : F ■■ V • . 1•.1 E. aY l i 1 W e 12 0 i 4 : ,,,,i.iv,,, ° � DPI —' ' N y W � °:11 pz I zs �p NATION / —J /ro I! gyp_ ' d �HC/'V� "%� m IgeTil d' J .i ° U' W R'L'V 6 E W oO W U =1y fS1• PZ Fa�a.. € � •• _ V i? g IL M /1 lyl'1 C) Q `W Z rL C O i 12g cl CWCW LL g UU Y ! R W Ul lit Ew. .0(} Z`Wg o F 'kl = ��� OJ JGf W °0$ = rc U K '.. ' ��U� �O � q � ��il��y�� Kll W =0 j= z1OOF.GGW1 !�,/' f3Y> � O t1< 3 aul Yulolaoasy puo wPH-.(a1WIN o]R1111W11 lnornio eq Iloyc'aul'.DI%awpV pus woH-A'''''',<V uollPldopo puP uDllDx{mV1pP ua13Vx�rwy{IM luawnaop alVl uP aauolPJ uadoudwl PUS to acmtl'Pa,odsud co%{I VaIVw•,ul>wIP PUS esoNnd pYlaads a4;bl Al.pupwl4 cl'aay.{aa to luawwasul uP cP•wauaV p.lwcaud au6 0 W.P Duo a ouoa PV1 V11M crac o{•�vawnaPP c141 z 6Mp'Ntlld ONIOV210 P\slaa.S uold\00V0\Flllpod ialo0w;oiS alpowagly'q op ofIt\o N3-8VA\NI wd00 LZ SO 4100 '6L aunt NYld 0N10V80 —47nolo� �alow,w�ois uiuowagly p 090001 IWS 3aay ' o40;(O pallold CL W 8 g4., 2 CO FiY m . 'Z ALL ; 2z 2- a a q x ■ W% I s m 1 Ya > ' � •� W w � � aGnQ■ il \ '< s s F_W o �w 3 II�� i� �� Y� Y u x=, U;« W= %jwS. A x11 m' ' £. a u w �_ * I W ua ° o F Y<� �W ma FZ 11•• M >i z A #� 4- -t 4 ,t 1111111 p m mma wg �' J P o° ,, 45- $ ,9. 8a0 1 INN - -A ZY W ��� �� �I�'� ` �'�I�� -e Z ° m °& �A < ��° �_6 I,�'11 • • &- 6 ', 4 ■�. 9, !° gig sm �� w �J�l 00-- tv Q VI mo,&n , wW' im rue. Q — om o .°3 Y S r".2. ¢ F—D IJJ o io n oho ° �i� 'sm��w,°a oo ' I ,a c o_ w � Qa �zm� o$w 0°g w 0 w o'm z� w p;. wqa`' ,°,5`3' .�.' f" L1 q'1 _ ry$:m n I$ !O, ..--1R g o ow w� ahw i?; xt `r8 x!E gm fy ct �awwa NM a rs'A F—H —I z ff _ Sao o N N r Y m m n m t.i mYo IMA 6.1 °m y� o W of wSa Mi > a;`°6g Y' gd H Z Q $ W m s sa w.«w °a _ 1333 lN3NIl..H.. 5 rc6� Luz i NM O 2rw2 SAIlWA ..o-.e <o4° F— °Sih om`�2i,Z£ 6 .g o gg ,m"G' q:g C9 a W .31.,4e q- N2iU:NNn nF <a ° fn _ € Q a I ��' .∎42INNI :jo'I LW 1111 1t -- R PA r Y *,_ __. I ♦1�au1■• N I ► 411 — i KM� o = ' a� .F. , >. C n � .ttjiJ1 I17_ LI:E!L1 o /:� - ∎\(JIa 1■ '�t$P# � s 6��°' w u �� .� -o°: z L _ ao � emo"¢ w fr .m F—O N anm N M iSw T • z W i ,a -1 Io 8 r g QsoB � � . " 4141 !' N r'i a F _ 'NIW 0 - n n Y m n m o fh cF�< Gw n O. ° uv� k WWS ua 6..hroa ee y gt yN.4444• Q I'— > LL Q W Z ? @ f D b O cO <� F — _ °O : I ¢ J Q s<a = o igg Q E % 1;,,-Oils 6 e.a Kidgg s o ap � 66I Lij® i CO /1 J g 09' /Gird a§ !!g155 15a o> ce cp 1%NI o ci a g w 1 '4x' r 2 m W egg•r .,i' S 4 MI Ef V G 7I 11 io• y U ° < a •.- i IV ` 16 I 0�1, Dpi, DPI _ 2 " �° Az �If �= 1 111 /� 1� /� w ° 1 0 t. N 8 q d �d I��' S5 _ =F.4v ,•1 •'•'•- CO• � iDi 11I Flo !ip&1psI;1 Q ad d. a d ` c M IPLI i 71 ' 11, ❑ N CD co Pg _ Wy7 l�Z Y _ ex. g, w W h ,,Ir I Y iii*S55z. ' O MX 11• FLOW •'7 l W p (C��p Z <N • ' o �5xP '� CO 11ilI, I1 10'1/ _4 1 •• z aN 5 o °fin N u �1D�1�1D�1/1D�1/1D�11 o o a n wa. m L _ _ ° I D I l 6 �I r' , '11, 0.0i D,1, t 0 N ;I 1.11.1.1.1 O >Y Q 0-til Ali 6•47. 641 6,All.- Z Ili Eu.., N 1_ s 1- 11-7•11 �I: 1.1 .H 1 5 1 Q r w m Z v Psi - - - -J : o< u) z 0 N 5 w cc o '�ul'caloWaaay puo unH-Aalwp o}(1lpgog}myli.eq IPVa'aul'aalolaoeatl puo woH-,falw!q Aq uollolEOpo puo uol�ozuaVl^o w}lu.LmyIN�uew^aop sly uo a uo1Ni iedoiduu puo�o aeney pamde�d co.�I 41.141.ion�uep�puo aaodmd a�lzde eye ml,(luo papua�w sl'a u0$to luawwlaui uo eo enV P.po.o.d eu6laap puo 0�da�uoo aVl Vll*�ayla6ol•�uawnaop wyl Z 6Mp'SlIV130 1V535130 5\.1..415 uoId\(MVO\4s1!o03.a1oM oo15 oIoowagIv b10$3£0£ll\AN3 BVA\5 wdbl!CZ SO 'I'IOC '54 0.51 SlIV130 1V03N30—L'1no1lol ..pow,45,op5 aluowagIVrbl09£O£l1 lay 1aalS 0144.3'UaLPUOyS;(g pallor w W Z O 3 oo z N , VT ,o Q m r 0 J =U N O _,Z W U QU Q i < N U m U ° I-w 0 o � O v"° LL` a 26 ae 1Q Jg: F— W W WWW —OW —WO W ? 0 o z J N CO( Z... •I I ® iil C O N @ ® ® 8 ® Lii W s„ c.:, — Q W ' � � h O QH¢ �' W = I- Z°j Z Z cz%9 0 0 zaOo Z,,O� U Wimu Cl) Z �W U 00 O K w W ;Y H=wU N U U Q • / .zq - 00<Z d r >-1.—Z Z _ sr �OQZg .ate �Mr .. / 4.F- Z o: g l + 6 i / r�� ''. 1-ZUW F 1 r Y�> '` z � � 0 Z %� i V' Q QOZW O 3 &O / WCCOd � oa. CCS)-008 CC LL J U D Q > W I-C~J ~ H LL t. �" �\ _v H Z W Q Q F- 1. S, \<. O OW=2 W z 1 t, Z U 1—t—N 1- \ a � � D `' F- � � < c`�� � J0O cz 1 /i, k 0 0wa Q 2 ( rte; A 0 O?p WCC m i id � (9LL} iz f `\\th o W' . ' \ - ,� Z O Q U ® a F # 4 r. ' '\. ',.,.: . :, ' 1 . ‘ :::;::: , ?:, \ Z Z w a u ' ' :'\ ''' " - , ;: -I,"fi",. ..',..j I 1..:.'.1 ':' .. : ; ':;:.i;'',`;,'.';; „. .., \ - \ , \4\ \\\\\\\o O /� 1 N ' — , Q C N 1 N >v0 .. \ - v 1 m S ' (Goln7 _.....f �. Z N ". cni N 1 CD Q U U X K 2 s a t7 1 EEO spa ki' a � z � i • ,,,...,, ,,,, , ,,, ,, ,, ,,, ,•,:.;,„,,,,,, :, , , : : :: : , :, , ,, ,.• -r r __ ® ` 1E1 1~1 W,.., . 0 @ 0 .,,, .,:::,:,,,„ , ,„ .,,•:,,,,.„.,. ..:. ,,, ,,,, .., .. , ...,_ ..gg /� „,,, z ,,, . ., ,. . - , . . ,,..: ...,-- ,,:, l • . ®��1 // . ':: : A 1.‘:',...,:...,. ,-' , - _______\-- .3S------.00�aT i�.�� T tEIAP� �8T g :'.?r•�� �l m,,,,, , . : „ . , . , . .. ,... . . „ ., . . . , . , . _ . • � fy __ Y- 1111 - Z ° dz INCAp710ND / �� o��c_____,,,, , ;,, , .: ,/,li ' r--- H ..,L lit d Lu Iii tli � o °� � `� ghl W/ „I :,1 aul'ce7gaoecy puo woH-FeIWN of tt!I!go!I}aoy}!x eq Iloyc�Iq'ce}gooccy puo woN,telwfN.(q uolloldopo puo uoyoz!aoy}no ue}lµx proylfx 7uwnaop e!y7 uo a uo!ler utlortlwf puo yo aanep pe.odeUP cox p ya!yx m}lue!p puo aeotlin }!aadv aye rol'-'10021 DapueluI cl'aayrac to}wwnvlcul uo co aray pe}uaca.d cu6!aap puo cltlaowa epp y}Ix a p Sop•}uaw^aop a!41 Z 6MP'NVId 302!1N00 1N3W1035 ONV N0150213 6\s7aay5 uo!d\OOVOVp!Ipod uapoa wuo7S allo wagIV b109£0£LL\AN3 9V�\N wtl9£Zb 0 PLOZ 'P0 uagola0 Nyld 1 NOO 1N3WI03S ONV NOISOP3 ui 6 1^0,(0'! ual^.xwuopS aluowagIV b10900£Ll laS 10005 000')tlo N><9 pa7}old • m w m n O Z F T- , w w I— Z W W 2 F- O 0 w (0 _1 °a 0 za O 1— p w— z Z 8 apS M N F a O O U• m *cc iJ! ZOr °� �0 `r-' (WJ Zr OW Z2 N 06 W ° � m0� Q W o�JOZ N �Z ~A� °. J 0 Z EW r O O x° ° °QF20 dx d.BTS� ZW � < F d F N mWD,y,,N6 01n <>- z PQm,.Jw 0W W Jh z}Om—W 3 Na00a .5< mawN v9Zm< Nr wv1g r} Qr mrFa ��� 0E .‹ ~ J K W K OW Z < S dJ U W ^K^ w-° Z W I d d. Q <�p Q<y� Uz< O m= wZ WZO O OU W w U O<6yQU V6 ZWZ rW vd`� jQW�Oz ° Q 2W ^ate } Op,K5ff < om� ZZ �N� z0: (_7 oW W W r°NW vm-0� ° F�B�ZQw U�a eeo O zzap oN m F. >Or$ 76 w� <Nw? ..Mh Z U z z N<dlrn NN a. r Zx2 VjN mi 1y3j <axz 0Nd' -Li rc 3mN W Z3UK 1p a W FAan�wzwv SfY3J Wmmm<O°m 5>NZ °(�Zw o oW <a<03 omw dd ZwZZ O 3�¢¢Faz `„.1N k 1 d. m a} .z<7Z 17'r� O m<wuaz nao< mFY, UF?W O_am °WU la-Or bs 8z 0 O <0 N< dp Wd o Uw 7° zd � � N ma< o< < q-z Wa a ''z ma �00 ww zd w dz °- wz N° Qo mwwp} =< oN rmF "' zN rU< z z `' s z � 00 N ��° <m wz� 0<o� ao 3 a 'FJ`xz mf„.5°J S mw 8,0(71 °W° 3<<.<mN ���� o��s and c }fffoa}mN3 ��ez<o c°>3W°��' z<v°i�.. _.,mw i °�AmF< w��i <w wpm <o°id a im w 'woJ°�< ��`.on e� o} m� m�Fom�BF oUymz F�r2 � `r7 < ly a frc<m z}wr fizO z°° zlww �O� N°�wNw at �-map W<. aN°oa am N-�-m{ �N yfrw zrco m°N Z..N F=8376 > N6 P 3a a��? °z v_1^� �WNpi,r° m� °id°id zU m oar o�fw < M8° 1dwn°2 axmf., aF°zo 2 >-moo M3mR.( �- m3' oZ �wZNN0a� °d I- w> a-Z2 w x < a S N�o1n3 zl.i z f- U ° F N zo mR<z<°zi-O Nm<za z� o }Y cU N1�Zn h 0 } m rwzz 0Rm NWO NW� Z°jw o�ao w LL 2W .00 pm <Vl1 W Z< mN rBOoQ�r O°UQa Wr Oat ZVmNW }CJ 'J-y<000 <z�y pN Od' SNdd w oom P w 0 OW xa 2°8N8ZW U,NaW 3z °QW Zm > m z°QyA ° °NN bbd 00 04444- l.d.,Z° LT-8 . ....0.2F 3 082 F_ t F m WQ�70 wmvlmAO NZZO m<a� <Zm77 0m1 Q0o N<°U <W6'� ���'<<zr Q U° UzLL 30UmJ33m ammm W° 0 26M88R Wr-§M r7W Wl.A Wm�ma= Z ZF Z}Z < 3Z OKIr/lO d� O� ZNr d'1.�OQ< �OW M a�<Jm mOFm U3m NfA °Z Zar np< ZdUri ...x r°Z NN NZ <ZS 0N�«v1 << Oda z 7cd vg67 -a-izzi awzww X6--i-iw C� LL zg� w Pam w v13 oWWZ F.F -w{o{r.�w °d NG�/ z c°im a d m (3 ��w 3ldil < m d m FII aw°n'4 Foroor ama0001- LL D < ui ro ad of o 0 ~ o H —1 2 O (/) U 2 a < WJ ry a 0 0 f- a Q q Z Zz w � W w m } V0,m O 8 N N Q W < N z Z� QmF I W >9 < v <x N z M °maN wz- I 0 Q it _° O° WJ Fj 2N Y 00 JW < NKmO W p 3 WN n�. °8 J KZaz NZ < 0< WwWUN� 010.1 (000 ��U r0 I- W m° W < a d_ZZS W< 8mQ dwg011 °fwn OQm 0Zr< OW V O wz az �o <� mZ rml Wm5 zo ° 1rSi r� No °Ah < za J a v wyy z Z U < opA1: o <0,0 m 1°gyp Q 3m a� em0 Cn 228 > aW S N 5 03 mN <ZSJ�`' M • Z OWf? I w in ,�A 00J ° rc z�W� �Z'• a13fo m, OWNO N3 WmQ� zoo t, L. m mid F� DJU Nw Wt�f= Wz oWl.AN oF d W.: WEi!3ww}fr< wN.. Off dd V a °pO mK W_W W�N a V1< NI- U�dZ ON3 W� N z�<oXm J UW} Z ° N Q N W <m m�<O W� '� i od °°W °w ° z °< � � <ZO k mpd� Jr �poz o 0 O 3 Z IJN J �7z Jd' °�N W O U NpW Z 2 3� fin- 6S^',W fY Z -F i`p mQ d'<>�xw�OJJ °Ow OU0 Q ?_r 3 a m P• W my 0w�0 0 °NW g ma -4 ° O ° L-° Ned NW2�N NWdd��BQ Zz_} O Off' mZ7 W� N f=/1 d ° ° � m y z _�� m°ZW mm ra< CO <<f"m • I:5 I'd Zv'�f?O c°imW<m3aw DfR '� diai r°ci00 °��m Wm m , F > aF<F p _Q m wo U OZ <-- a tc- Z N • zde N°UW Z ° Or W2m 8= 3<C> 0 Q' (/��Z JZO ZN� < �y'< < O���Or m00 NZZ�(5'00m CeFw= QM °Z i ZmZ -MOO °< F-WW O W°O 3F� Ux eO! Z 08W<0 <ZW WdUBW UNZoIal P.1 W Q3m oI_ Nom~ yf > < ` u W W ° Z J W N Vi < V) 2 O W Z S 8� W o< o° 3 F m NO°<p Nz °< vim z wwo $ a o QOeZ Foy 'cep- - - tom °N Z�M''< W W �'zo�2 zoF o-0°1" �orZf-' 3mc>< .w f woJ j0. c� Ar NJm F wl�. �a JJ �1°c> Uom< z�l"m°my?3 ° Z3.: E8°p aoo <a�J k'3 � °?4 w 76Uia m% <� (� < NOO wQ o mxt?i °ooAdilmwzNV1 o w_c> Ow ° N a 0 ?gCi< W W aaw ofr fr a<_ -(� m� 4i 010no >w, OT3 W <38 w°F xI°,•j ozm ~ Q<�00 Wido ZoZ o �a4uf<���3F= fYOao ,gm o<<g oz o WF^ ap°w LL ooa 300 az m_< m F- U8 mrr ZW7 c°>v' a v�jo°� =°zw? '6amo 'z'dc°>z U d wiZZ mmFo p 0 - O o�W now wF }�1!1 co ZO zUwWi'li"d. m�� }in W mozNONa�° �NW< omw� oomz <O N W....2 3 0 �Z0 Z3 <�Y moo Z U NfYN83p{.� yz0 <��=WO Wp�Um1.1°WdN° fYU3U NO.0 UKUQ E M p° yd Z° Z <zo <§i.: 0..' d °< W Z NZNV) 0 U p°,<10n3r W'mZaWpW1y<j� NEW1!1 ¢m<W0111 1�NfYN N dpWw ^U WZZZUm Q WJ-N 3l.�80 O �0<00 zy°`�� Wz�.ApOem <=fe ln�f� �N �a��`�S a<a>w O Zm �m y3d.�A7� z N Z ml o=W m0U ~JO¢7 LU 0 0 owe*" 'f-F`'O rJUNa d NQ_ UfYN m OF WO FWO dZ Z_ O Uw y0� 2W m 0ZQ Oa WdZ 17 N_EZ0zFF IW °me dHW JV'H < Nm00 Or m U FN(-i<< QQ�3 Z QN m3U �SO d5 � Z W K friwN aNZ Q�N Z W Nl.� 0-- w } Q cQ O ° < LL J«OO W8d m N N• N C m Q m ^ N M1 C O 7 N 1171 W W X_< .- l4 1M w Q g-5,^O C 5 2 WN o a o=I o > Z L . 1� C: 17A NY Z R r Nr < 0 p M ZOUqO 08 o K W ? „w. ° } Z W Z z I E. r g O, M a W 8 > w r O 5 ° 0 J t .. } ° N J S W Z O d U W Z N1n . ^ p0 <' WZrz, LL N_ Z a > W xK O_ 111-'j NW w 0 F" W Z Ode pa d O>i-ij 8 3 04 Or N ZNK z�G�YN U �tiZ = m m -3 ° rc No 3 v=i a z d .N d z tr 5Nw w� 2 aw° �nU - zo i, w0 o m w oz - O .„. ap r,.0 8 Wmf-n �j Lig°W r o o �`' z oa o m 30 - CWdr o t �moc>�° vwiom f71 dOm sa c>w 9F oz d 3u Za J° d Ea- m D 0 W w w 3<1n !OI! °owvdi ,0p N ° � w p a o03 f� o o °W J dN31iU Q"- US wm c1 o p w wWO mo y w W ° ^ ? w 8 ccw w- W Wax 3=• 2 m Z q W 7 40 U W N Y 1- w 0 0 z 1 3 O U 0 W 3 0 1- 0 oor �1d71s5 w 0 z0W - °z m 8V d o �o �.didW3 dz sNw¢�z �m� om�8 3 ° NxF 0 o ° ° _ zo ° w z o ° ow3 1no �o ap Uo , z W �owl- 37x5° w N Fo ° d o �' ad N/1 0a o=' o �'� fr mo Jz d ° _� ,. N 0m N w1,„ I2ilN W O�N <~ 0 Z Op Z� U ?W p NNZ}w0 w.5oo�N= 3 N 3- Fd� W W 3 d �j� V m U O w ° Zed' y mm �1�v0_ w a1� ¢1 0 w wo J K o� ¢ m f.�f d o zr UZdo Ow1Od < dw w I a0 W°01il d� O z d Y o f� EN l-. p 4 z°wz < <m ° 3 dLL Q 03n r OW 0 Q Z▪ rOZ LI 3 3 O a �°° rcv ZW Jn ° 3W0 0 332^� pO mr0 a momm W co jOW K3yZ 0 23 Kz=n, edZ zm a Zf�i1 w mm� ZOw m°7) W Wm �i1 `'OU 7mZ< �mU p0, zzdw ° o g 3 z ° N ° �� 3 �� Np x wz w WW � ozaz r_m Z l.i° °-7W v1F �5- Wr 2 1- o fj ra o m- �1!1� m Ao0mw o WOo3P0 Z �- !=Z° $Z°o Uz rc� 2(.6 P m �i° m ° � z �Z w mZ WFO W m0 W> �pz Z Zman (a r °w0 <Or WON J KWZ W y1 N OD O WU • Y O <U mO d' °J6 < �K UW3 U Q O„ 3 N fQ� Z < r _N Q d0 T < FwN W < m dZa mw 1W„ m-oz dM <�C W OU° WJ < Jd' aW W°Z d' _Z Ow ryN <W <d0'�O em NKIi 1i 3� NO°SN< .0 (fl.„ U I- <Z 3r aZ 3U op c> %3O w z w d w rc z z o z U I ° Nwa r Z o c>~z z oo� rczd F do duo m N� cWi Nw Fz dN z Jt °a° 3Z Ow°a°mo w O Z_o 0320 PN'- zz o .mw �? 0 Noah ' o WW N = ��xz d FozF �°ro °8 z p30 d w 6,0g 3r 3 r 1� 3N nd AB zd 3U 3 U cn >p 0mov1 0 zF WN riw -max zd m r o �m wm w °I UW3 Z H EEm <c°>0R Ginn w 3 ° oa wo zn & W ° LUo m mZwm wao� a^ nU o as � my� rn�<�3 0 O Z om� z °w z �o O7� °�j P"Nf-ii a�i �`' Wv_; 3m �W Hp d oo °°a U2 �z o ° dwz m zm 0 z rvlr 1:i rxW in U W o gm W° U 3 3 zl 0 20 m �o o aw m oOO < -w _� �� o > c>� w 5 �,8<3 �� oW pw�oJ� �Zo c� w ww °Z U w N AJrNw<J�w �Ug N ° w Q 7�- oao o z rf�.. o- `A�� o w m z� Grump m� >aoo 3>dm J mo z & wJ d 0 N W 'W O z J 3 W 3 3 ZZ W d E o w a rc U o f z Oz a 3 w zN zx Z▪ Z -j 0 CC w CO J m m O w I- V7 J ZO W r z _ I- _ Q5O N =M W --I!wY Ud ly1 N vm >Z 03 F (n MwM m JJZ Q O J J Z =0 ce w d ce =y 0 M IX \ W <. Z w Q Z 3 3 J w ¢ 0 X° I Q J MO Z O - Z M 0 Z • n 0 u•,•;._0 a ¢ M Q 0 _ = U \\ I 0 U Z a o < Q F-650100.ll o III , Ilitirlirtg < a.*, 7. .8/04•444111011‘10 ■•• ' r wir,Ws, < N i%ic1Lc % • z cc z g 11111106.111, .-61:6_., (OM 0 .> ill,!Al INA it, 6, 41 Tit INN 00/11. p molA litiv p(e4104\01' U � J i *;� J / � (A ' ��f � �� �� a Q a � CI) 3 -II, rsOks Lam/ 1J1. O NNVB 13NNVHD /\ W Z \\\ x m l p °'t \\ i t% \ d 1 Whoa p& Q ?, ,,'.3 Y a! V`c ❑47 W �/ Vii .-Z .d 2A' O W 41 x�. I/Ol N I J� .� ,r,S V 'T 51 1.F 1 Wa I- 1 r z . Vfl I 4 i . I .r r ..„ . 0. uIt j; i 'Q O J O o O C , f. LiY _ ` z _ i ♦ A L v E x U W U W W o l�� J �, y a o Q cf J f Li —� *' Z T•7:--l' a Q . ~k lid V 3a v 3 °z O dQ CI d �R sv f 1 o or °3 �' '' O = m _._ . + s I t a a 4, •' (�5 .$ U W Q z La { WW• WO CC I .��'1 tJ.z h 0. - _ jar ,.y 1... ,,, /� /O0 �,J < < 8 Z , i.._;•.- i- 11 L 4 R LL LL w .0 Lt4 V,.v .Pr: CCI-2 m t J > aW r Q a ZQ° D `J` I-al • a U I- `t o o °2 I wet a i 0 1°v v/i M � O p M N m } m H ao o� ¢ ZZ U N a Z Y M U 3 h O< U Q CC U Q N ��• 4 1/ 11.' )I W Q - ` 0 1 • • �• U v 0 A, 1ti f1,► s rol Z Z 2 U 4**;!f E Q Cr Z w m P' Z Q Z I f4li f-4 f-$.� Z Z O > win b ./'/',.-4X/ O wdQ • w �^ `!1► 11,4.8;4•/447 F w HO U Y o �4m10 1:1;,�,,,, w•-,- 1` = 0 w J o zoa w (n ~rmi Ys r < tl•�0�? mom Z Z OQww r m aZ �y �'4 Mom > z O Z 1'�i 1 b () UOZ 3 _i OW MF y�bj !-Z N< `r Q°a a m oJ� ao (na °w°� dz.Z o O 0 m -iul a°sIW a° ∎ I m Z Q UWI- ol-° wy-W woZw 0 �n Q �1..I H Z- cc oSk'Q °zi-L- ,z00ws°.om `''0 Q ~O G 1-0¢ �oUaoaa??wmLLO or "� al 1 x U r a KUY V1 °0= O O li bm O Q CD �- LLL0... D=W -wiz •¢OI° 2w 1--�cnZQ mi-o qq C O Z W Umwow?Owwo-zFN �Fa F 27 G �(nQ �m<cd YdZYaOZNw ¢ ()WU p Z r.-- a�n=zov'Jm¢=cF�a° oopl o n� oa<� w H UO W �Y^=Z?F-w3 Q_¢NaJ2�¢a Z0¢U U�aS I-F�'Q QUyC5p2Zlal1 In -JZI-FUZ U w Z°Ml/1 S U Z a W M ILIW0 >OZW°0<Z <WWZZmO K Q`-' ��y1JJ <K WW U�a QOmao°,m J°(/IW�ZZ LU(fl >m w I.1 'zoom a a O O Z z0 5u, °=>1--"<wo- u°F XRW W 0 0 0 o W w N �azmo J°�z°mo��A zr w ao z ¢ Z U CC I-m Ji JwaUZmamOJw2,_Fmwm°za w W .-: N M d n z 0 aul teloioony puo woH-Re,w!1 0,Rl!1igo�l lnoyl�x eq IIOW'ul'eeleiaoesV puo wofl- I.H Rq uoyoldopo puo uo�lozuoy,m ue,lux lnoyli.luewroop eiyl u •uoip. edoiduu puo to.envy peiodeid eoe,!ya!yx. o(luoyu puo eeadind ay�aeds eyl,off Rluo pepwlu!s, ee�a luewnlsu!a eo erey paluese�d sub�eap puo s,deuoa eyl qIT.,eyle6oI•�uewnaop e!yy Z 6mp-STIV130 1Vi33N30 S\sgoogS uold\00VO\Rlll!o03 oalomw,olS oP...91V o4l09£0£ll\AN3 BVA\:N Ludsk.Lz 90 Pgoz '61.oonr S31V130 10211N00 1N301103S Td N0150113 e- Ino,(.,-1 ,alomwiols.1,...91V4109£0£Ll,loS loops s!.y3'galpuoyO:RH Pallold • • w w co m Z N EL,- r w N h J k 0 w y } i : I°— 4A t y 3-A ix ,., .1 ,,,,..4-4 jg,,,„-20..... it,1,4k.,.4‘ 0 * ( 0 o W w "'mod E F 91I R eJ� e W∎ o s 1 '•i m g o . w U SIP d (7 y ""°4 1L" fn w w i w /F, N U r 4 O e* .s{.',/e;41....*". •• W W 06 rc w z a - . Lu � -� e o w Ir.X } g w Ct y 101f.2: o 00 :_�j (±) .r ..� ,..,. ? .s, i r: z a ,�H r ♦♦,, o a '` i W,....„ Ez. _ itig.9 i .1_,_',1 E-q., z 3 Ida, tie_ w" o m ci 1r Nrore Q , V�io • O r } W v �..♦�/ ?SD',O x a \ S � o ., n � u cFi s a i A z' o 0-2 • Wy �•NN N O o m z °4A/oar Q a u FF W Z Z N WKom o o o Z ° o _ Cl m v Ln a aFzR H t W N m LL W W s F — F— g Q }} 3fa 1m �X1 I1 G F 1w to; - II p Fa „= O — w O . � aa4 aXZ i H J 2O �4. \ ,. P "<o (/) 0 w W ri I /A$✓i � a o `a> v a H a a a z o\ a d zw;/ • fill a o ❑ r m 0 a 0.. �1/1�Md11=1111111= < EC IMUSitit I (/r�;�.�� g x_..111111 P , ! = a o s,!•1 1111111— � •- o w ':• I Ifll� 'in'w Uz Le < I k III 1 6 ah rn U w 3 w X2 0 a 2 C5 \ ! a '2 7 z ; m a n r a o x o n W N (T, 3.9 W o M m Q 0 ° o m an w < — g \\ ill— _ o o u ■W 'J ������°• ` r • l r W N yy `\ a 1.1.. `y1 :�.��•� �`AA♦'^ (J �� 1� K \\\ W U m V, \1 KEE fill . E ci =r� QS G _ _-, $ Z W N LL 0 VI ,4 W Z ` III i' �� II ,- Xz A 0W 6 ���I v a '-T11 a wm3 IS �y W J EF; LAJ LO :: \\c�= _ . f, U �\ m W gip`0 zi, a_ti,r `` v = V \U . o a ,H N N UZ — •t. II_� 7 Z 1 W O \__ . gR ■. :�� \\ 0 z *o �i \ 0 z `W 1\1\ �> l r es I-L---.6g 4 :: \\ _1 . —T;-,-... 2<Z ' ' —' a � ct • ;1111 Z� Q o 11 Q a _ Z_S ;11111 IQw �i'i ;111111� w N z w 2 \�� LII1I— \\\,ll�l. 0 9W� > 0� - 1 —`L 71 i' if-i1 I-0 EN•F A \\ k -dta :::::: - a 6 ui 14 Ca �k II W z Sul•eelorooeey puo woH-AalwrH of A�ri�gerl�noylrx eq Ilpye'aul•eeloiuwey puo woH--IeIw!N Aq uoyoldopo puo ualozuoyl.w uellue Inoyl�e�uewnaop cry,uo•uorp�iedo�dux puo,o eeney pe�odeid eob Ir ya�yn gal lue�la puo eeadind a�l:aeda cy�ion Rluo pepuelu:si ee la luewn�lcu;a eo e�ey pe�ueceid cu6;cep puo eldcauo�eyl yirn�eyle6ol•luewn�op e!U1 Z 6.PS1Iy130 1tl213N30 S\.155,-IS .61d\00VO\4I!oo3-.1.5n o1S a 1powagly410Bcoc \AN3 9yw\:N wd64:LZ 50 510Z •61..Unf S1Itl130 1O211N00 iN31,4103S,P NOIS0213 - Zl 1n6(01 -.10,...,45-.1,...,11Y ttO9cOrll lay hays sl.10'-alpuoy0:,(g po41o1d .I I I Lu W co w a D CO = gpO N Z Nz Orr rWe F I- 2 r cr°1°a o �aa0 w� a = 9 m zz_`J�z o <oz pz •p• —mil ,.o -Jl,.r– In < 1 < 0-0 z BYO .6-10- WN w �® n °eu m °. °�� U • °o° ° $• O m€ rO title °owa��w�, .a aoe T-- •.e V T liI W1+a 5w5 QW �iN �n' �t > p O , po °t °°Z - o•• mW Qmm QO J n ' .', oe!J r - iI V I I- m og. <�lzi oz ? o ym $ / / /p w ¢ ∎ i Ulilo0 m02 `8g � o aZWr I Ca O g ^ ��o�q g l- a'm▪ 2 V» 6<< g�5 W FF o� O° I I y nWriGi �� 2s� �> 1 <¢aw opt 0_517 mQ< W zazi to ° nW � � $ ? 0_ a' w U t 3 W ¢ 13 W Lf' y� �a R �` m{u-so w mo w ma3 m s An .r 4• U 0. . Oyv. ®rN xbo< k'.0_ 0 x0_ S5 w=!QQ r, !h; � W ^ � l �Z' > $ h n rc 3Y� N 0_o 7 I� � ~L�NJ `�� 1 I I Z i ;Wtz ; wgCC°11C =O<V O' i M* f�'9 o°"i '=m o rc CO- a k 0 fft F ° 1 �poe Q a° & NWZ ¢a N Y> < ' ° ie V° W O Nz1iY ,�, z am 8 sW m < m m<8 z53o a o�� a '4(a °y 1rJ °W m 81 m dr "v �+$ 9 �� z^y-'°p%0 °<� o <�J Eka ' 43 g 3n- Q - m �D�' m y°1 cgs $ zzff w !!! Uoi�w ai8 uPimr r yy g�+< W g xp y4' ow5 4�TUP 4'533 <c°� ia`drc 3a�� �� scyr mz, �W°oo 5 w r zo ® ® ao� () '^ Wy'tp lw I<�yaV� tai imm y'�yQb_�Z c°�r � o> ®—w i i $ VJ Q. N O v°m Vl ? ,.;',-,Dig' N m D 1NOBY 1V01N13WWAS 3ONdN1N3:310N � _ Z 3 Z ;q' z I31p1 il31N33 30ptVtl1N3---� a x x x I— O w a o o zz 1y a z°� di a 3 ° pajzngLa <WrF F $ i W ;_ I e.p ::� 0_O a 0< o II l po X11 o O w 5 I, ii � Y o: Q µfH .1 o 0• ,N to °�zv 6% R § ° R' 0 v® ;.° loc�sto y� 3 El L"Ww i N= itri CSR 4 i oo ° a r0 �N3Lwz yqy U0_ z0Z �/ u- j ' 0_o o° a N •- Z 1. N�NCO�3 _"H� �W� 7 R/ -2 V-4 °oo in o �; tltltl^ 1,. '0615 ii 3'Y <avz� <<ag wW w : z acj oo 4',.._. W Lohly`oa p�04 m�m ?pr mumz �Oe, ._ a (z��iy Z Z (�— op �Q °.NNN ix Q �r4W°e ��Q< <<L' J ° T 'I p 4 a-• 3WOj N<V,p NKZ z 0_9 yYj Q o0 I I-- tniEe'Q zwi-'swwi zwO< ° T og w r 0_L a° I �/ LL z w to a ,0 o a a A ; �a Lij O mzaoa °ppnm ° w yo W® < W — , 0_ zFu, 330. lz 9 y •O U p < < F g a p 3 1/1<~p iq •o z m N < rc a CI`� rLL i1�ty, Jo 0_,W JrO� wmz 49 h�0 • grz 0_ga Al 0_1, ^ U �je NwW< NpF w J ° ▪ ��rrFLL NN yy�� ZZp N Nf/17p zo wozz Sgo p6� 0 Q 0 a` 1-maa F J l.� _<opma IU W r z - N m 4 � U 2 212 o 6 CC W1 x e_; ct z w LJ t Z LLJ m I a5 a m U in < z M w m p� Q Q t5 _J z<F 2 W LCL I p0Z J iooj o't azt� U : Q m w O FWN3 a alt¢ �La" I ,— o _ �-�O y to va<� m r m a � = 3 0 N o >wo " V 0_o ¢° a m ' m ° m <---i 14%SL I Zv 0vZ W< 0_J?in I pZ I m w y- a Z =�F Opy h w o u ° wES nEwzw 111.l14 T1 � !Pi wit- I <z N ii W I W o ! • a . N • 0 � m Ca II co o // I E. _ 6a) � w N Fiji ° LL// m I w / v n� ° ajw Y ajw 2Otn NUo / / I ° NJ U Zi.z 0°Iro as°x °' 3° ,` -7 0 0 ¢a 0_¢x o< / / e e,¢z ]Z 10_ S LL o 1111, IMP Sam I m a o.wwpa to " I'll' I m_0_OQ°U ,-,.7 Z w F ll►�. II 4° O vri/ �/ m �i d ¢o N• z> zz�ocFi < / /y` <I� o Ym 1111 N0_ w inZ Q,-2atipw I` w I YW a. a aim° 3287z� / w ° o°00_.C.)I- / /Y z a w /v n w w� �md�z< wz�trig° °Yq�M°iw a„a F-. NoN Y W Li z s '_ t- �i a ¢ w a v2 Q o -3 ,—.- - �� 3 C m Z °am 1:°6 ( _Wp= O �_ U a < Y QOy <ZUZ LLWx ____7 Y ° Jam° NO W E. Y ° to Oa8 --"oz t.,1 w o o K < ° h 7 <w w wLL o z P S 7 a m m m m . �; w p 0 g _ , __ ° m Z 0 �x r 3 a o P F ° �� F� % Nzo 7 N 3 Z U U) (APLL N m�aj 0_X o o w ,Li Oq7 .c a o G=�• o ZmN� IC m o �JJi J°J a o8 X08 i,@ �� m Ftr/pLL<f N W o U J J ow U< <g ON SN N 0_w az3 S0_ a o z z av�i 0_w w?°x 0_ i az3o dFNF� CI N N - ct IM Y N t0 Z N VI7?t/IU -� O nut 4eio!oa•ey puo u.oH_,(elw!y,o,40o!1 Ina,,•1 Iloy aul ke,ao•ay puo woH-Ileln!N A9 uo!,o■dopo pm uo!loz!roy,ro P•apIP,noyt!t luvwnaop•!y,w PP.!,.cda.dun P.,a...el perode.d aox 1!ya!yi.Po/Iueilo P.oead.nd P!1!aode•4I.off Aluo pepuelui,e, ,ev to tuawnysu!u eo e.ey pelueae.d eu6!aep Iwo e1deauoa eyl II!...ayIe6o1•0uewvop.:Iii Z 6MP'SlIV130 1VN3N30 S\s,aauS uold\OOV3\Al!I!ood.a,o.mwuotS al.owagtp b108c0£I l\AN3 13VA\:N wd£S:LZ:SO Y IOZ 'al aunf SliA130 aNO11311211SNO0 u fl:lna(ol a 1omwuo,5 aluowaglV'4108£O£l l:1aS ,aagS sug3'ualPuoy341 Pallold- i, . .c._ 1.1" , w „, . li -8 r,, i 4:‘ 0- In ; INNIII., . 03(.1 „. ..., , ,:„.,,...„.„ a z z < ,.., ,- _., ,_ in . . v 2 Q. 1%4CN. - . ... ,, ... , 0) a < = z c,-, _, < a. H M 0 0 Z Iiii / 6 [-T 9 , : ,.. ..; N D / CO EL 0 ,, / a „, <.,..,,. .' /.' I c'si P ',.. / E • , I i; ,- A 0 ,.._ . . . 1 ...0. „ , . . 0 . *.' ' , , tat. * ' .011 0 W 0 Z ''<fCb A ...: . -= L;,1 !;• iA .It , :. ,,, f.•..,,, l',',', .. ,,..... .. .......„ .„:...::. . , .., i.,.., -1/4.......... ,. . . < , . H > ,.. z L., 1-- , .!.'a';,44'' 1 •''' ' i ,•',4/•,•>, ,,.",;`.'-;;").4.f,';:,%;.•••' ' '•' --,.1'.':::,,.•..2.s.,'•.:',:'; P a. < U---. , C•Q W 0 , ;,•,,,,, I,, ' ;,.',....,,,"/`,/,..''''''''.7::•,;;;:',A7,::::',” .- ; .‘,:.:Y:l.'''', i.,'',I2",','''; ,.•,„, .• ci_ L.Li u j .. , ,.:;!-!,;•!"-..,•"::::i!,`:"..(,;::„!!,,,,5;! :::::•;:;:ii !):!!!:;.. ,! "• • ' '' :' f .< I-7; ,.. ,..;,;, ,,', ,,:: -,.*;3,.1.,,-, : , ' 0 Lcti ›- D I' (g, tY ., . ,, fi, ,,' ', ''•'i.i ,,'',';‘::.. .....',-. 4., 0 =_, 0 ' '',:' ',••,..',.:,!':':,:,,7:,•..;,-'.`,1'.'-'.`:',., .'i .. , -.:..,, ,, N cri tiij .1 (17). .)” a Lu li , I± 1 ' < ce ' ;A 0 .„,_ z ,,, ', .,'' , A: ',k ;;,,,, ;„: A, ..7v,,A.,, - . „,;,.:::',._; ,.,\, O• H cl- 2 , . , , ,. , ' ',\:::,,,,'.c.i ', ' ',,, .'‘ ', " 'c, ": .\-.,:;, ,,..,-. .',' 1-' : ,';',I.1.,:::::::,:,,,.',,,..\ \ ,..: • z in w m i 2 7i /1-./.!„,:/.?,!:1, i , \ \ ''i:,,,',',,,i-\ , ,,,i',:',„:::,,:-',..‘; ', ,\., ,, ,. ''':, ;,.:'.,. , -'-'' , , , O Lu D ,.\ ': k ; i •,,. ' , 2'.,,..::',,..' ', ,..:;, , Et' ' , ;',,..„.::. s, ,:.,.„ , ec 0 . D : i : : " ! ! .! :: ' ' - ... ': - . ...:. •• . -.-.': I Z . < .-: -, ,i ;-"!1-•.::::.: , : ; : ': ' : 1 . i ', - . . - "..: , .. . , •-'•:,-::' , ,,... : ••••:.,! \ O < ' ' ' ! ! ' • -- ' :, - '‘''' ,, '- '-qt.?! ..., . , !: , , !\ I ; .-f-'.: H : : ' ' ' : : , : \ \ '''' ..''‘ ,,,,,. '11";."41, 4kfitikkiMs"tt.,, ' ' '.,., .:' 5.;•••::''fik'' .''''", •.,•it.,' r, 11,ii. ; , , '2'1 i i : : .: ' .. ' ' .*:;1-,;%::".;__'°;:'''',...hi47.,,,L7-4-3, 4%'■41.,+* '',:- -E',',.f-'-''''' . . - ,i , ._ 11,1;liji ',., •. '. . -.: . : : , , / ..,,,' , :;::$,T*1.7k; .:',... ":71# ,;',,,, 41 4',4*■ N. ', '::": \\• g 11 ,c3.,, ; ; : (4 •/ ,:i,,.:..!i t :, ' , `:: : :•.';' ', 4,:,..007,:44;!,)'.,,',••• ' ':.4. *.., ,!,-,...;`,:•. , P.•., ‘ ,\ .•'' ,,.2.' \\ t..,- N 0 , ii oc3 W i .' '' ' ':'`.. ' ' ' -- - '. •. .. ...*• ,- •-,',' ', ::...:N:',:- ' * - '-/t'', A,7, A 41,,,!, ' , ,,,... .,;:,,, , • , , ••'t ***44 t( %,\, %%.%.%; $% ,"%■%.....!..,' % , ')t t 't ' . \\ 0 5 i lf •,;If;! ;•'; • ,. i r!:,'" '','''''';1 #.,4;"1, 'i: 4*. \', <, ., '' +.::'* ...' `. ';',....:%..•1::::• ';..': 4+.4r, , ,•,\, , , „,, \\\ <- i, • i: (:.< ',,d '.■%-$,A*,..f:' . *4:4 ' '''"'" '''' *i' '''''':: :•3..'''... J 14'0v,.::,.•,. . '' , T- f!:1 !41 I!4,:,i! :,,•i'. ' II:!i; , ;;;ii ; 4 .**SiTe,•':,.#2,k .... 1 • '..• 4, ' . ,'''::::: ..!. ;„ *..,:\,,.' , ,', ,' \ . ,■••■Af: ,-.--• 1.-, < .+,....• :, .,,,,,.,,,,-..„,,, , * •-...::....;:....:,.....4-........,:„:.,„,:: 4- *,,,4;,,,,,,' ' \\ :,.' ?:; 1/,'I„,''4VV-41%. i 4;4*** \ ,‘,,',,,,'••■ 3, 4 '',.::'• v., '' • \ . • ' '' :; ':' '' '' •' : .t,i' 3 4,' - 14:4**■.''',''','''':':, 4 ,4 ..i:N::::4 ', '''":::, \ :• ,' '', ,`,.:•,•i, I 1 I i .'i'' ''i ,: i,1; ',!, ' ::: , . ::I frott, ' • + ****44 .\ .0*:4.,- , ,..., „ ,,:':F, 4 ••••,,,:' • \\ \■ ''':''''''''''%i:':''''''''•-•Fkt''' 1' i S'''''''., - 1 iii ;1 i I f::';:. , ' ' .I.4*$ -4 .' >, . ',;:.;t:* ' :\:' , : . : \ _.1 \ d I l';'il.':',A .4 . " ,,.:(.'1:: I['': I:.:::..4 , 4 ***::' . *:,,,,,t," ',.,'Z,-,":".<,„,',,e,'■,' 4 '':'N. :;., 3 ‘ttl' ... „, ,\ • . 1--.77.7.77,,,,,:. 1 `, = n — <a 1: T'ir• ''',ii,:i 1:, . ,, 4 t f:!!/!:!'1,1 '; ...4 * ** i ; A -:4*. '''''; '''%\ * '',. ..::{:, t ' '', \-$,---"----. ..-,..,"4■7it k \ ce >2 4; ,,,,p1;.;,:i ',:,,,, i:,,i; ' :..: , :i;:: ; , , ,...:. e: * ... :,,. ,. .. .„--...„ .• .,' , - .4.: A \ 2 A g co d z., ,,, i,:1 1 .,..,:d igf q•!, i ; ' : • ,,,,',.•, .:** 4 ,„,4-' * ■:**4 - .,. * i,4 ,, ,'4. • ., ,•',,•,•,', 3.*F,,',1;\ \Y'. ' .8--. `,8,J, J, I.!.',::I',-;.,:''',:\ft:! V: ': ! 4.4' _. , I •' ' ‘,.• • ',., I.< ',-,;:-211ir.-:* . •44,41.1-f' \ l'o Ic-L'''8. i.;.; c ,, , ; i- .4, . . „ :,:.{.„,.'.... . ,.. .. ,, .., .„ •,:, ,.: ., : :, i .. 1 i v(' -/,.. : ;:: 'J.': ,4 4,:i): ;.;,;,..:$i„.*:. ,...;:, :4 *,*4%t,'C *4 •••■,::•;,■ ,' ',,',', ,''''''''','.1:.4.'.*4'I:4'S: '',1,,•;:',',,:: :::::!",',1:/"; ' \ i-0') P.1 ' :''''' ',:,1'.;..<';'.;.'.-:7<';'''''''''' ']; :. 1 ,.'-i,..,:":!•.Z.;',,,''''.44:' , * y %.,.Itt: ';,-:%-..::::4,: • •<.,it:;. '■•.4...* :, vi•::::-.,:,:/ ' ' 7 S7 l '': iri.'(1','', ,';;;;,1-i-,-;.-- ?,: //,,i.,"./,(:;,,•,,I.',1;,..:::1 '-::',Y.i:,.:',. .?.;');:-.9',' -'...q....: 4 *t: ,,, ■:::,;:,•; 4:,,,,..i,1::::';;,:. • - ' Eik.;,: *.:::::,,: •- ;;//:: ', ,/ w,7, 1;',';4':,:t;`.';';',":::;,,i,!.,;.T'ti;;;;'1,'.:•;!!, I ::::,11 ! ;';'.'"; '' .:,.:•;:. .. ,. /:: ,,,,•:" ',:; , .; , ;,ti....:.':1;..,,) ';:::',1'. ',, ': / \ E .1 RFA 7 ,,L"g t•,,.. 1 ,.. ,i ,,,,,o,>2:4..,,,4 , „74,',':!, y,i,,:, 4,. osti ,....,...;...460 0'040 o■■• • • 4 441; ,■4, ..: N ,, , ,',.,•;,;: •iff.,..//::,, ,• '' /'c E i 1, '=„j I i ';:, : :1,4 ,•;: '...,.,...s...„?.,,,9.,9 0 0 4,.'' 4 3i 4 , , •.' 'e" ', ...1.,,,,.+7/,;,,, / 11111- E Li ..;. '1; '.,,,;;;;: „,,,, ; ; , „„....,... 8,.;,...,,,...,,,. : ) . •;.4., ' „ ; ,.;11 I:h:' ' ..i, , , ......: ', * ......f;.-.\,■ ;”; ,” " .","" . "- ,o :. -.' ; ! +4■.: ) .* ' )".. 4- ;) 11j''■ '1 ,, "" "."""."";;r":",". '":, \ i :. ,,:';,..., , I : ; !I":i i i !':\,.;,,; ,*4 ' + :-t -: ':4 „,.‘14:••-•t: \ I-•"]t,. !- - :• ,, I.::-.,.-,:.--: °!:'!!!!! ; ! // :. :: :' :4? 1! ,!, -'',.!!',.;.H! :I', - l i i!i',;i:':, :-:-,,4*,*:*: \ 4 _,_ vig4ititr44-• • 1 : : .1 : :"V:,:,":•:"1 il'.! i:"i: ' -‘,...',,......4,444■■•••••44.+- - - ,,,,, :„.!:::,•:,: : : ! : :!!! ,,,,.!! ,. :: //v : , .:<,..r.',11.,: !, 11::"•.,!0':i : : " :,.....t. '-- '-'..- :',:: : 0:'-,•,',i: 'I .' :, i ' : ': : ' ' ' '. '- - : -"''' -""! •'- ! v ! '!!! !.: 1 11:1 f:1::il:',,!;::!': I:1.! ! : ::!:1: ,!:.„.‘,.\:-:::‘'.„,.., —...!... '''!";'.,,,,!•••."..: ""-: . •:(:: :::,, :-: . , :, , : - ::::, J::: 1:1,-11L1:1\',.,!["1:1[:\'';:"\\\:\:'1,,,\A ''•,,,\:',.:::!---•!!!".,:::::!:11, - ,, :: `,.•!!...!:'' ' .• :::-:'!!! ! ' ' : !!! , :. , , ... - ' _ '!.I' ' . ' ' —i; ; I'd 1::‘, 1,%'.W:;',.'":":1 .: '::. '', ' '•----,--- ...._ _ .., _ ,i-I": !!! i'.Y,''''''.\''' ' ' • '' • . ,, 3, %), % ' .'%' %%. '•, .. ........e.'"'..... 1 ' 't t 1 1 i t t %t% %.. %% ' , ,3 ' ....* t .. iti,t3 ' ',%'' •• .%,t, %t ,,,33%%:%%%'t :',1':%%'%'%% % 't ', ........ .......'..".'....' • 3 ' %. . % ' .-- 3- " -.3, , ,,....•••„.• . .,, 3. „ ... (/) t ''i 4.1' i t t%% 1 , tt',.., ' %• ' 3'''' . 1". 't%„-:,:'.3::;,:•,tt ''-,''' t,'„ 3,. ::', "; ' 3.'t ...'''.. (7) ,,, •,, .!'7 __ i : •„ . , „... ,_. ,,,„ .„ ., , • • .. . .,•..,.,.,„„,,,,, 4 ,, i--;:::,,••-•.:Iii .„.,,,...„.,:i,,:l''',4„,4.',.•,.-4f, ,,,1„... .:„,„,,:';',;4:'77--, -•' nomATIO" _____,t- ,4 i ........ - ..---- • _ - .. , ,.. ,.. . / •-• 1 I '..i '\ - • L i i '' ,, d ___.-_- ii z ''''''''P " "e'•,=,-i's-'-':'11.,:iiv-i,,,04120i'LL.1 11 HI ,..1 Ii 4q p .--0-0..''''''''''''''1, '0': - IS .1,.,-.91Y-41.073C0 ,,,,,,,1 01,,),1,1.,1 In.4,,IPS.",, ' I ■ I , CC w m Z I- w w In C d Wg co= N C/ ) Q z N 2 Uh I- >. tl R e Z z U w f O ¢ zz CC U w 0 LL= ° ] O =D 0 U , O ° O 0 <~c O d (n> p Z O-1 0 < uiza q - sn } _ • W z W w0 (J) �o o l`i O V �o � M z >� w J Z•F . . 0 o. oc DQU w F �j p0 z a, wo? �0w <} a ^ y�+ y 10 Z u O ,n 0 1- J l j Z Q Q co m O td mJ m ¢ a, M Z Z U w Q v9 q 36 r3L[?N �p *o v dFg go F¢Oo J .-w <RH Ow . '$ Ot w L_ �t a3 E 3 W�w co ',° ...:o=0' Z:� wr.. u qew o a CL w iii ¢U� p N 0 < Z O Q z 0 �qqZ+O ,°,115 c7 pp(ov)< J J 9tj <Z m i 2 n p.,P, N M M J Z � J Z LL Z J�Q_ a¢ .� C O c o J Q �'� U I_ a o000 WUm= aU wU Z ¢oc} <' c Wo> D w� oI- z wo_ w< m< 0 2-z uo0 Z, p dJJ O2a d Q. mtn�a mN �� w .4 i. ~LL Z? °<3%8 C7a_ � O r � . .o ^ ... � o� �w <W U) o v.g i wZ0 W� m w0 wzF- off Fwd w a QU 2U v. " m > �0 J<ZF- 111 ¢O F, � a� LL 2 2 � m<gt =< N< >_ OF-,-, O j oCCF-0 U W WLY u, O U a L� MX L�LL�,I O Z NN O Z m ¢ ¢ ° InNF > m> Q U§I- W0 °Oco? < JJO U °`N)A �9 oww� � o o cii �zz z =z O iL zwa <_ o = }zw0 F_ cta__ o °,� ~ _ ,,., n ,. .� oa�4'P >�f°�, i = � aaoa '-< cna 0 y A e I- Opt JF- 0 m <0 z Lww0 % 40''66. x y 1 a 0 L,J 0 dJO 00 n awJz < ww �. . z z • • • I- z 00)0 ml- 2 <Zm< 2 CC CC W _ .� ,`�• ° ww0.] f1 •64.10 1 I- 2 o_ o_ .. . . W 1 I W (�/ LL O O N m 0 0m (n J¢ F Z t } a CO U F- Z LL x= n E w G U a a a s P_ ..j Z Z a W o Z X o o K H co> o N 0 0 0 Ln Lin M N F- 2 Do XU W o z =Z O W RLL = ¢¢O > g.�� &W 3rg Ce= mw =o Z mF-F 4+. ei 1. aU 2LLLL ¢F- �Ln F-J LL ZU Z V' ao.mGG G GGGGu � a� coz =c �a oo - °c¢n, v 0 > D ccE _ a� 2�ir ¢z ¢¢a as 0 how x v N 3 N a) N O O O .= 2O C=7=a wiz �� >th w- w�� v v v 3 �a J W U = Jo =Ln Y w OF-u Jw z Z. o d Z Lm E v on °n O o W la d r oz �mJ WZZ ZZ g W�z d Y a, O w ° ¢ Uz -w wo a O -w to E c 'c 0 Q C2 _I E v o Y ? z¢ LUW F- w¢ azg >n na. = o o m L1 n ` m ¢ CK z o L ° w ww°mc? c�U- m°\n a�a WO w ¢¢ e E a a �� ° co ° o Q w c o m0 a h a O m pLJU E nm °0 c 7 c ° o ° v 1-1-70 wmw O� W o z mg �F (7 `m 0 0 c 'c - E v > E m Q i E ° Y E va` - ,co a z a x Z w¢ J a a) Lo . 2 vtm A m °° 3 nI ¢ ma J� - ¢- U a E m 3 O ° = e o. v° .°'. 3 H O c 3 v 50z, O Z Lr_ g x .-:Q <w O -0 a K a) x".+ co O a) 1 7 N lA u m co m ¢ ° v w 'c a(� ° °, aww zg0 Li F- ¢Ma x3o x l-W cc _. _ > a U m z < LL Z w 'a E 'c 3 �, v o a E .n ,� wzm a '''r x co=W m LnHw w C a o .m n ° ., ,, ° 10 = 0 3 m= z o _J a0O xwz Nww cool- w Sao m = C- m (p R K V 5 v1 a ,) 0. m ..7.: u in m = m O -10_D 7 Z 10 Ln J m X w¢ W¢ w J a U J r d a oma ¢a= ¢z� om� �_° ~ ¢wm € U W < Z _ `n - o wv mc�m o a E o N rrnn I- d = = �? �_1 n ¢Zw =w0 w¢o= a a Wv~)w Lu a a a V o w o. c .°u_ ..°u_ c o o ° ao a U07� aQLY 0E, Darn .�'9 J zn= E o ,n u v LJ E n ° c E c v ° o ° _`o " E d �xo TKO =a¢ zcaw< ¢z0 ¢ <2z co Ly c .- a a h = Z o a 0 c o :14 o IY cn¢ ,° U O U Z E o o C . •c• Z ' 'c o 32 '`3 0 8 2 8' a :o l'c It 1, W.Mz vl-iova gF_m :-°Lxn N W LwaCO l� ^ c t ti E a� c 4A coo- u�,z wzo °wz�' o max a E c o +a v CC .t �•� ¢QF.. Jaz J¢g 3aF- NaLL'i N ~i)Wgw a .o .` 3 'rn` o o v G m c c 2 F-W¢0 F-=F- Z O U D LU c0 v ,v u n ¢ Lil n ° x3 ¢ ¢LnW Zw w I- 0 2zoz Ln t > E a C G 0 O E u r w Z!n(� W fn N Z W(n 3 z J Z Z a. J J W J U O N > C w o a a o 2 a ° oo O0 u)�Z LnWL.I� LnW J ¢2a Q¢w ¢O m�W� u a t o c UU a ., z 3 m a ,c° t o c°, .r ` ° .� u v 3 F.W., (32<U o z o U¢ Ln a F-o:a F-z =W m w ' zs E v "E. ` o . .r o c o u v v v 0 0 o > i, o LL ri u O Ox a=O 1 a 0 w Q w O a¢ a = Z w R v") va) (W W 2 a > Q oo° o Ln amu ; aaa cruah Gva Z 8-_"6-55 onF o 0(01 aim O O ¢- n(n� n ff2 A'a Ln M ¢.- Q } mZ T Qf' °W 6 3 8 r z wJ R U < 2 N � � U w O w o x w F-J Z 1- w 2 u) W m < LLDU'' F}- wQu) �� W W w w W < , u) OF-R w z� z aa =' wZ ¢ J a -- 2 z << w o � ¢a0 MR0 wO >w < Q OwM 0E m m J < c N } U O ww _i N a — = -J)U _1M F U - Z - U (n ¢ a o ZLn m Z 0F.- WUr' �F W =Y wW 07 - W0 -' 0 0(n I '0 �O '� • Czoi-? ¢? U F-w �Fa > o J0w E F- < < <~ -p E. 6� Z � �Q' z (n a JO 2wOZ J ¢ gw z z W ~u) F-z =� ? w I W ¢ Fj- � �3 FW wg a F- a J w > OZ F-z e N Ol N O W ll'1 111 lfl V M N N N N i--1 [/j mn� ›I- 21-1> J J_ > (] a O> O a a 2 •J a F_Q Z O_ z U 00 0 a-1 a-I ci . Z r 8 w llaz °JU Om o> Zx m N0• M (Ow g~ gQ ga E o �Qi cn _ w << OU` wo > Jw MZ W Z O - 00 Z W 2Z W z W� W a o°°o Ham- m Fu)O m W LL_ww0 J IOC ro F-0 �i0 O K ° ° 3amc.,o wQa --- w FW UZ 0 a3U ww < ON = J m_ wz 3 a Vim. mreF- _ 2 W og3 I Jm (q - F- ¢ F_O 2U` 0 CO z n4 � JW Wz l' u)O m0 <W � O HQ w7a dZ <C F_ w � wZ F- Z v m s o NN3 U�> am 00w Ow actw (n COW 0O¢ wF= wu) E-- 00 00 Oa ), v . � ° v aa)) 3 v I w� OwZI- oOw �m NmW< a < Wm --1 CO wZ >- wC7 b Qo a LEo u ao a) oan n v cc m 3 ra > wF- o ¢ c9 c� a d z Z'v c L J Zw< W< 0 }z w (n 20 O w W d u ,� v 3 v v v o m W N V) W O N W J W Z O z < z z m H to c .c c Ln (n > v ,n - LA,c,- a�w WOJ (n � = F- ao W O OF m�V) OZ U (7QZ u) � �< < ¢ E a n2i va)i L °°1p c N c 3 -o c i sa Z O a Z Z J a' (`')0 U(n a < U < ml w - W } W F_ L- ~ O F-lL W iJ O O Ol C O N a) E 2' ON O al (� (° N =Qm�u ¢ < 20 OJT W Qa Qm ��? Iz OZw zw <O QO a) U MI ° x E .E n ° 3 Y a OWwa.> Z(n3 22 (nv) 0W K ¢ u) W a< m2 u) Ludo O ¢ U' W 00w a: co > N _J U U in U ef S 3 ef Z � w w <x zQ O_1� �0 m 0 - = O � W Q ¢CC 2 00 O o o < a u W w w w al ZJaWQ mOzo CC<0 0E- 1i -- JJaO Z ¢ a NQ < WO W ' ooh ZFUF-CC wFCOw =w OY < Luz W W H< g � co F-3; NO N� waz a E v c v m w U-1/- "-j° <m Ca o Z a 0 w ' N J o m o w w a = F o F} x } < ? n v c v o n t- (nwJwz ac7 ¢ oz OF 0 OO w , mw Jw z LL0E- , } m F-ma a o , ° p = v a a a a aZ wz�z2 aF �V 00 0. 0 = W � NI-O aid w ma i0 CL ai0 =O JOO m o c o a o E v o o ° „ a Omzaw OgZZ V!= L2N j� !w g < QWgW � w Z ¢ LL ¢ Q L: 2. Q > U) E E Q ? v > ? a c o I Z 2Fwmo re CL ww< OFF-- 0< m J w< z ww < < Mw izz >Z wZ0 c 'c I- _ = c L. .a v c W wCO wOL>! 52 Oa.-1 xa? X< < `- W CC F- W O = a J a0O 00 o wow 0 0 0 a a v 3 -- o o u _o a ( F-ou)F- a au. ow F-(OLL w 2 2 0 < 0 F- (naz F-07 a E = m = ? J ❑? a a a w v v 2 z v v ., Lr N z 1 0 o S 0 ..,=,...v puo...,..o,n 4.0.l p0,09,.q Ipyc-x000.n,puo wory-.(.,L.! (4.09n.po puo uooyloo u.m,,,,,i.,......p.m uo.w�p,rnm puo p,.cosy px,o.A cox,! .m.,o,1.11 puo.od,od o o,d,xy,,o,.(luo pxpue,w c. ,.c,o l.-,,ew u ., ,.,xy m...o.,c:.p puo e0,..�ey,w.,xylafin 1...- 9 ciyl z 6/LP"SiIV130 ONLLNVId 9L\87..4S uoId\00V0\(7111.0J-,540Aw.o35 el,ow.g15 5 LO9SO IL\AN3 9VA\164 wdoZ IRS 150 5105 '61.ear satoo ONINVld o SI Ilo.Xol ..7oMw.o75 01....gly 4 10 9 50511 17*S 1..4S OI.4O'.OIP4.4O+(9 P011041 CC W D CO Z F W W 2 N 0 61 44 0 G €l a! E s s% . w J g a ws Q„ III II I III l IIII II 1 iiol 10 lll lll m H ,\ \ Timsnixt4k- 1I Z Z_ill s Z it11` I i 1 W < r W Uj I S ul li S fit u 4 C7∎i 71NY7.z. I 0 CC \ III-11111=D'i 1 Z ° l --1 11 Z w CI- � J�5 =IIII II III= A 1 III II I!! CC WA 11 a_, s a a � s1 lz g w n▪ X” g o 3w i x Oa 6 d I� ,la� Z 'r a Z v ti O Z Z Q a 3F (A l Tx z a 3 0',pho; A'° z <• K 0 1}Z ♦M11N Q o O zQ Q J 3 w O a O O O N m a N a 41 W 1 1 w ° N -N a Z O a W 2 Lai Z U O W a s w H W 2 61 Z Q N K V m rc < H 0 aF w o o°,, LL Y ° °N Q N L Z z Q �a N w z a N ` ' D I �z LL } m wa ww a c""1--k n Q x• O u2° W Q j a-0 H � W Wi ¢ zw �a a a f z (O V W W F O Y YO O C1/ 1 O W O FW t,J 1.0WA W 1-a s \ Fk J Z ce N N K a'J Q: Q J m Li_ a Ct N Ni <' vi ,U O H d G Z � W W co I . Qr CC C7 Z U 17 W L J Ucr Q LU w I I z ; a Uw? `� O Y 3 O f = Q N N O O i N n p °f Q m M W a ZZ U _ 3 8 o o 3 O J li ail �� � 2 a F em gC 411 5 _(,� L 1 1 11 16 111I •s 0 1 a ° o El = l on co I � 5 �gg 00 w° '° ~ N Qa z^o 112 i m EIii! i eilir i §§ !I wo= p= �w° °�wo==� N� o Z E-2 0 8888 O O O O ® ® ® ® c p �..; rN=s-, o=Q � wohm t.'": °° IIo: O sgLig PJPJ t z7 Z Pu Q °coo 04.-Y0 i- . 1 w =w k mF s m z v oi�o N a�\ i � �p 0,V1 Y Z O wO „,,, z 16 E Ni W ° / � . Q J � a L zEZz ,,w rc O a O GObWw z O Aligt W a ' J '' “2'6 i W u ° aLL w NiN w I II_Il i.. o m U N Q ,1 ti .2,,, e Swim o 3 °F� m� zoa l oT _Fw_ o ooi ' !zoa i1HI ~ „. m w O_ ° _ J I- _ W 1,0,\ e o 0 2 \I } t1# ~ © O © O'O z z 0 w 5 a w aul'celo!aoccy puo waH—Relwiy of AIIVgo!I 1^oyl!x aq Iloye'aul'ecloiaoccy puo woH—Ralur:)4 Aq uo!,oldopo Duo uoyoz!,owno ua11uM,noVl!a luewnaop c!Vl u e uo�g,,edo,dwl da,d co co O puo,o acnay'pa,o M 1!4aiyM,ol lue!la puo acod,nd ayiaedc eyi,ol Aluc pepuclui,c! ac 10,uawn,lcu!u e,ay peluacaad cu6!cep puo cldaouoa ay1 41!a,ayla6ol',uawnaop cryl 2 9.9 SlIV130 ONILNVld 91\91994S u91d\00VO\41111.oj•alow,wAOIS ayowagIV b109f0f11\AN3 BVA\N wdlZ 9Z 90 1,LOZ'61 aunf S1IV130 ONONVId o 911,,a(ol 0IS aIAOwagly 4109£O£lt.I n laags a)Ay3'Aalpuoy):6e 991101d—• • APPENDIX H SWPPP CONSTRUCTION SITE NOTICE AND SITE SPECIFIC VPDES PERMIT AUTHORIZATION FROM THE VIRGINIA DEQ The SWPPP Construction Site Notice must be completed and be made weather proof by lamination or other means by the Operator and prominently posted by the Operator in a manner so as to be readable from a public right of way at the job site. The size of the SWPPP Construction Site Notice shall not be less than 8.5" x 11". The project-specific VSMP Permit Authorization for the construction site shall be made weather-proof by lamination or other means by the Operator and prominently posted by the Operator with the SWPPP Construction Site Notice. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 SWPPP CONSTRUCTION SITE NOTICE FOR THE VPDES GENERAL PERMIT Project Name: Church Road Stormwater Management Facility Retrofit Site Operator Information: Name Office Phone Number Cell Phone Number VPDES General Permit Authorization Number and SWPPP Location Include number obtained from DEQ Coverage Verification Note actual location of updated SWPPP book on site Project Description: The project site consists of 4.01 acres with a disturbed area of 1 .73 acres. The ultimate outfall of this site is Chesapeake Bay. Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 APPENDIX I STORMWATER CALCULATIONS Church Road Stormwater Management Facility Retrofit September 5, 2014 Storm Water Pollution Prevention Plan KHA Job #113038014 a ' . I'i 4 ?, 1 *c" LL z ,t• 1:1-:' y tt ° �, +»; _ , ,s, t.,..r, iR ^ ` +` M ei x u get _4 n' 1 '` : . { 4 Yom OI v x W O 4 J — .. q , r . _ aa to Iti4 N\. v r •�. °u X s -..ice J l ,; '� 2 W m i r w , $,; d 0 U- . � �.- � :, .,1 o IP Fs- s 4 1,* / in " Jr ` 411.--.1, F .0. a i ci of at o II52 Ev Ka Y 43 ito Virginia Runoff Reduction Method New Development Worksheet--v2.7 Revised April 2013 Site Data Project Name:Albemarle County-Church Road SWM Facility Retrofit Date:November 2013 data input cells calculation cells constant values 1. Post-Development Project&Land Cover Information Constants Annual Rainfall(inches) Target Rainfall Event(inches) 1.00 Phosphorus EMC(mg/L) 0.26 Nitrogen EMC(mg/L) 1.86 Target Phosphorus Target Load(Ib/acre/yr) 0.41 Pj 0.90 Land Cover (acres) A soils B Soils C Soils D Soils 'Totals Forest/Open Space(acres)-undisturbed, protected forest/open space or reforested land 1.08- 2.53 11.89 0.45 14.86 Managed Turf(acres)--disturbed,graded for yards or other turf to be mowed/managed +f r. °.+"- ,, a..-. 20.82 Impervious Cover(acres) 83.90 Total 119.58 Rv Coefficients A soils B Soils C Soils D Soils Forest/Open Space 0.02 0.03 0.04 0.05 Managed Turf 0.15 0.20 0.22 0.25 Impervious Cover 0.95 _ 0.95 0.95 - 0.95 Land Cover Summary Forest/Open Space Cover(acres) 14.86 Weighted Rv(forest) 0.04 %Forest 12% Managed Turf Cover(acres) 20.82 Weighted Rv(turf) 0.23 %Managed Turf 17% Impervious Cover(acres) 83.90 Rv(impervious) 0.95 %Impervious 70% Total Site Area(acres) 119.58 _ Site Rv 0.71 Post-Development Treatment Volume(acre-ft) 7.08 Post-Development Treatment Volume(cubic feet) 308,513 Post_Development Load(TP)(Ib/yr) 207.23 Post Development Load(TN)(Ib/yr) Total Load(TP)Reduction Required(Ib/yr) 158.20 I. /Min Kimley-Horn ■ and Associates,Inc. Project:Church Road SWM Facility Project it:113038014 Date:11/14/2013 Locality:Albemarle(County) Drainage Area Stormwater Treatment Area Percent of Drainage Pre-Retrofit Total Drainage Area 119.58 ac n/a Runoff Storage Volume 0.70 ac-ft Impervious 83.90 ac 70.2 % Stormwater Treatment(ST) 0.10 Forest/Open Space 14.86 ac 12.4 % Phosphorus Removal Rate 14 % Managed Turf, 20.82 ac 17.4 % BMP Dimensions Phosphorus Removal Existing Increased Phosphorus Removal Rate 14 % Wetland Area 0.55 ac Phosphorus Load 207.2 lb./yr. Average Depth(Bottom) 1.28 ft Phosphorus Removal 29.0 lb./yr. Wetland Volume(Total) 0.70 ac-ft Cost Estimate $ 184,000 Cost Efficency $ 6,350 lb./yr. Total Phosphorus Re al for RR and ST Stormii ester Retrofit Practices a1. _1% 7 'e ,lµ 4444.. Y ST 3 I il W S N.r`a `' ' • ,--(Church Road Constructed Wetland 1 ,4 0t ui .3 o3 4,1 .- .v 4444 1 t1 i_ t s; Ii . 1- 4. _ .. _.. _ __ H ITlmplle Tr iih d per itxpen io..:trre I invite.) Figure 3. Retrofit Removal Adjustor Curve for Total Phosphorus