Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: IThursday, May 15, 2014
Reviewer: Johnathan Newberry
Department /Division /Agency: Planning
Reviews
Received approval from Jeremy Lynn at ACSA on 4- 30 -14.
Review Status: Approved
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Friday, February 28, 2014
Reviewer: Jay Schlothauer
Department /Division /Agency: Inspections
Reviews
Based on plans revised December 9, 2013.
No further comments or conditions.
Review Status: No Objection
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, January 15, 2014
Reviewer: Robbie Gilmer
Department /Division /Agency: Fire Rescue
Reviews
Review Status: No Objection
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Friday, December 20, 2013
Reviewer: Johnathan Newberry
Department /Division /Agency: Planning
Reviews
Review Status: No Objection
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, December 18, 2013
Reviewer: Michael Koslow
Department /Division /Agency: Engineering
Reviews
all site plan amendment comments have been addressed; however, amendment requires an approved WPO plan
(currently under review)
Review Status: See Recommendations
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Friday, December 06, 2013
Reviewer: Margaret Maliszewski
Department /Division /Agency: ARB
Reviews
Review Status: Approved
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Monday, December 02, 2013
Reviewer: Margaret Maliszewski
Department /Division /Agency: ARB
Reviews
Additional clarification on the up- lights is needed. Applicant has been contacted.
Review Status: Requested Changes
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Monday, December 02, 2013
Reviewer: Robbie Gilmer
Department /Division /Agency: Fire Rescue
Reviews
Based on plans dated 11/12/13
The required fire flow for this project will be 1500 gpm @20 psi. Please submit the proper paper work showing the
results of the fire flow test.
Review Status: See Recommendations
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, November 27, 2013
Reviewer: Alexander Morrison
Department /Division /Agency: ACSA
Reviews
Please instruct the applicant to submit 3 sets of plans directly to the ACSA (ATTN: Jeremy Lynn) for construction
review. I will send the official sheet when our offices open again on Monday with this comment for your records.
Thank you.
Review Status: Requested Changes
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: ITuesday, November 12, 2013
Reviewer: Johnathan Newberry
Department /Division /Agency: Planning
Reviews
Received revised copy of plan dated 11/12/13.
Review Status: See Recommendations
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: ITuesday, September 17, 2013
Reviewer: Shawn Maddox
Department /Division /Agency: Fire Rescue
Reviews
1.Thank you for the addition of the FDC location and associated fire hydrant assembly.
2. Please provide the total square footage of the structure so that the required fire flow can be determined by Fire
Rescue staff. The design engineer must provide documentation verifying the presence of the minimum required fire
flow.
Fire Rescue will not require an additional submittal as item number 2 can be satisfied via email. SNM
Review Status: Requested Changes
OF ALg
vlttcmi�
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project:
Plan preparer:
Owner or rep.:
Plan received date:
(Rev])
Date of comments:
(Rev])
Reviewer:
Review coordinator:
Old Trail Village Block 2B: Rutherford Hotel SDP201300011
Collins Engineering
Rutherford Hospitality, LLC
6 February 2013
9 September 2013
19 March 2013
10 September 2013
Michael Koslow
JT Newberry
[tel 434- 293 -3719]
The second major site plan amendment submittal (SDP201300011) submitted 30 August 2013
has received Engineering Review and does not appear to meet Albemarle County minimum
checklist items for approval. This review does not include a review of Erosion & Sediment
Control or Stormwater Management. Please adequately address the following comments for
major site plan amendment approval:
A. Existing Conditions Information
1) Please identify existing 20' private drainage easement shown on sheet 5 by deed
book and page number. Recommend same for existing 20' sanitary sewer easement
shown on sheet 5; however this is an ACSA easement.
(Rev]) Comment remains.
B. Proposed Plan View Information
1) Please indicate a temporary grading easement or VDOT right of way permit for
proposed entrance modifications along Claremont Lane in VDOT right of way.
(Rev]) Comment remains.
2) Please either widen sidewalk along north end of parking lot to 6' or include
bumper blocks for ten proposed adjacent parking spaces on sheet 4.
(Rev]) Comment has been addressed.
3) Please provide a number label for proposed 6" drain connecting proposed trench
drain to EX- STR -26 on sheet 5.
(Rev]) Trench drain detail on sheet 6 no longer appears to be included in plan view
on sheet 5. If trench drain is no longer proposed, please remove this detail from sheet
6.
Engineering Review Comments
Page 2 of 3
Please also adequately address the following comments for major site plan amendment approval:
C. Application Information
1) Owner is required to provide a completed copy of the standard stormwater
maintenance agreement and fee for recordation for any stormwater management
facilities (could reference an existing agreement with a comparison of proposed vs
previously approved impervious surface).
(Rev]) Comment remains.
2) Prior to final site plan approval, a separate set of Water Protection Ordinance
plans must be approved including: stormwater management plan and erosion and
sediment control plan (could reference an existing plan with a comparison of proposed
vs previously approved impervious surface for SWM).
(Rev]) Comment remains.
3) Prior to final site plan approval:
• water protection ordinance — erosion and sediment control and stormwater management
and
• water and sewer
bonds must be calculated by the county (water and sewer bonds are calculated by ACSA)
and paid by owner after receipt of a Bond Request Form from owner (could reference
an existing SWM bond or county accepted SWM facility with a comparison of
proposed vs previously approved impervious surface).
(Rev]) Comment remains.
4) Prior to final site plan approval, pro -rated share for this site which drains into
Lickinghole Basin is required.
(Rev]) Comment remains.
D. Plan Detail Information
1) Please provide traffic generation and distribution summary (ADT's).
(Rev]) Comment has been addressed.
2) Please provide calculations for pavement section thicknesses for the proposed
entrance pavement section on sheet 4.
(Revl) Please provide calculations to show Dp of 9.30 for drive aisle will
support loading of 445 ADT as indicated on sheet 6.
3) Please include sidewalk and dumpster pad details meeting requirements per 14-
422 and Albemarle County Design Standards Manual.
(Revl) Comment has been addressed.
Engineering Review Comments
Page 3 of 3
E. Drainage Profiles
1) Please include drainage profiles for all proposed pipes and ditches.
(Rev]) Comment has been addressed.
F. Drainage Computations
1) Please include drainage computations including for proposed trench drain outlet.
(Rev]) Comment has been addressed.
Community Development Engineering is available from 2:30 -4 PM on Thursdays to discuss these review
comments. Please contact Michael Koslow at 434 - 296 -5832 ext. 3297 or email mkoslow @albemarle.org
to schedule an appointment.
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed:
Reviewer: Ron Higgins
Department /Division /Agency: Zoning
Reviews
Ron is reviewing the revised parking analysis submitted by Scott Collins.
Review Status: Pending
.vim. err'
y }
P-.
COMMONWEALTH of VIRQINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper,Virginia 22701-3819
Gregory A.Whirley
Commissioner of Highways
March 20, 2013
Mr.Glenn Brooks
Department of Engineering and Development
401 McIntire Rd.
Charlottesville,VA 22902
Subject: Site Review Meeting Comments March 21"site review meeting
Dear Mr. Brooks:
Below are VDOT's comments on the Site Plans for the March 21st,2013 Site Review Committee Meeting:
SDP-2013-00008 New Hope Community Church(Phase I)-Initial Site Plan(Megan Yaniglos)
1. The posted speed for Route 606 in this section is 35 mph. The necessary sight distance for 35
mph is 390 feet in accordance with the VDOT Road Design Manual Appendix F-35. Please
include a vertical profile of the sight line and existing ground.
2. Final site plan will need to include the entrance profile in accordance with the CG-11 standard.
3. A Land Use Permit will be required for construction within the Route 606 right of way.
SDP-2013-00009 Seminole Trail Fire Station—Major Amendment(Ellie Ray)
1. Show sight distances for proposed entrances in accordance with the VDOT Road Design Manual
Appendix F.
2. Entrance profiles in accordance with the VDOT Standard CG-11 need to be shown for both
entrances.
SDP-2013-00011 Old Trail Village Block 2B—Major Site Plan Amendment(Johnathan Newberry)
1. The minimum effective entrance radii are 25 feet. This plan shows a radius of 15 feet at the
entrance and does not appear to properly tie into the drainage structure. The drainage structure
needs to be relocated and the radius increased.
2. Show the entrance profile in accordance with the VDOT CG-11 Standard.
If you have any questions,please contact me.
Sincerely,
Joel DeNunzio,P.E.
Area Land Use Engineer
VDOT Culpeper
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, March 20, 2013
Reviewer: Joel DeNunzio
Department /Division /Agency: VDOT
Reviews
Review Status: Requested Changes
Review Comments
Project Name: OLD TRAIL, BLOCK 213- RUTHERFOORD Final Plat
HOTEL - MAJOR
Date Completed: 1wednesday, March 20, 2013
Reviewer: Johnathan Newberry
Department /Division /Agency: Planning
Reviews
The revised site plan amendment must meet all the requirements of section 32.6 of Chapter 18 of the Code.
Please make the following revisions:
1.[General Comment] Where applicable, please label the plan as a "Major Amendment' instead of an "Initial Site
Plan."
2.[32.6.2.h] On Sheet 1, please provide signature panel for each member of the Site Review Committee.
3.[32.5.2.a] Please note that "ZMA200800005 — Old Trail Village, Block 2" applies to this site.
4.[18 -4.12] On Sheet 2, please update the parking calculations to match the information attached to the 2/4/2013
letter to Ron Higgins regarding the Block 1 and Block 2 shared parking agreement. If necessary, please update
this information and the current shared parking agreement based on his pending comments.
5.[32.5.2.n] Please show the location and dimensions of the proposed "43 room hotel and 1,000 sf restaurant'
including maximum footprint and height.
6.[32.5.2.n] Please show additional information for the island in parking area by labeling and its features and listing
the height of any feature that is above 4 feet.
7.[32.5.2.n] On Sheet 4, please show the height of the brick walls that encompass the trash compactor and shied
the loading area.
8.[32.6.2.j] On Sheet 8, please revise the number of Cherokee Princess Dogwood trees in the plant schedule. It
appears that 3 "CF" trees are shown, but they are labeled as 12 "CF" trees. The plant schedule shows a total
quantity of 4 "CF" trees.
9.[32.6.2.j] On Sheet 8, please label the type of trees located in the island and update the planting schedule.
10.[32.6.2.k] If any outdoor lighting is proposed in the revised plan, then please submit a photometric plan with
location, description and photograph or diagram of each type of outdoor luminaire.
Review Status: Requested Changes
OF ALg
vlttcmi�
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: Old Trail Village Block 213: Rutherford Hotel SDP201300011
Plan preparer: Collins Engineering [te1434- 293 -3719]
Owner or rep.: Rutherford Hospitality, LLC
Plan received date: 6 February 2013
Date of comments: 19 March 2013
Reviewer: Michael Koslow
Review coordinator: JT Newberry
The first initial site plan and comps submittal (SDP201300011) submitted 4 February 2013 has
received Engineering Review and does not appear to meet Albemarle County minimum checklist
items for approval. This review does not include a review of Erosion & Sediment Control or
Stormwater Management. Please adequately address the following comments for initial site plan
approval:
A. Existing Conditions Information
1) Please identify existing 20' private drainage easement shown on sheet 5 by deed
book and page number. Recommend same for existing 20' sanitary sewer easement
shown on sheet 5; however this is an ACSA easement.
B. Proposed Plan View Information
1) Please indicate a temporary grading easement or VDOT right of way permit for
proposed entrance modifications along Claremont Lane in VDOT right of way.
2) Please either widen sidewalk along north end of parking lot to 6' or include
bumper blocks for ten proposed adjacent parking spaces on sheet 4.
3) Please provide a number label for proposed 6" drain connecting proposed trench
drain to EX- STR -26 on sheet 5.
Engineering Review Comments
Page 2 of 2
Please adequately address the following comments for final site plan approval:
C. Application Information
1) Owner is required to provide a completed copy of the standard stormwater
maintenance agreement and fee for recordation for any stormwater management
facilities (could reference an existing agreement with a comparison of proposed vs
previously approved impervious surface).
2) Prior to final site plan approval, a separate set of Water Protection Ordinance
plans must be approved including: stormwater management plan and erosion and
sediment control plan (could reference an existing plan with a comparison of proposed
vs previously approved impervious surface for SWM).
3) Prior to final site plan approval:
water protection ordinance — erosion and sediment control and stormwater
management and
water and sewer
bonds must be calculated by the county (water and sewer bonds are calculated by
ACSA) and paid by owner after receipt of a Bond Request Form from owner
(could reference an existing SWM bond or county accepted SWM facility with a
comparison of proposed vs previously approved impervious surface).
4) Prior to final site plan approval, pro -rated share for this site which drains into
Lickinghole Basin is required.
D. Plan Detail Information
1) Please provide traffic generation and distribution summary (ADT's).
2) Please provide calculations for pavement section thicknesses for the proposed
entrance pavement section on sheet 4.
3) Please include sidewalk and dumpster pad details meeting requirements per 14-
422 and Albemarle County Design Standards Manual.
E. Drainage Profiles
1) Please include drainage profiles for all proposed pipes and ditches.
F. Drainage Computations
1) Please include drainage computations including for proposed trench drain outlet.
Community Development Engineering is available from 2:30 -4 PM on Thursdays to discuss these review
comments. Please contact Michael Koslow at 434 - 296 -5832 ext. 3297 or email mkoslowgalbemarle.or�
to schedule an appointment.
Review Comments
Project Name: OLD TRAIL, BLOCK 213- RUTHERFOORD Final Plat
HOTEL - MAJOR
Date Completed: ITuesday, March 19, 2013
Reviewer: Alexander Morrison
Department /Division /Agency: ACSA
Reviews
I have reviewed the above referenced plans. These plans may require full construction review. If Fire and Rescue
requires another fire hydrant, then 3 copies of the plan must be submitted to the ACSA for construction review.
Also, please include a grease interceptor and provide fixture counts.
Review Status: See Recommendations
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: Imonday, March 18, 2013
Reviewer: Margaret Maliszewski
Department /Division /Agency: ARB
Reviews
ARB approval of a Certificate of Appropriateness is required prior to final site plan approval. The applicant shall
submit an application for a Countywide Certificate of Appropriateness for a structure located 750' or more from the
Entrance Corridor. The applicant is advised that 1) building mass, roof form, building materials /colors, blank walls,
equipment, and landscaping will be the focus of review of the Countywide Certificate of Appropriateness, and 2)
there are discrepancies between the plant schedule and the landscape plan that require correction.
Review Status: Requested Changes
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: lFriday, March 15, 2013
Reviewer: Josh Kirtley
Department /Division /Agency: Health Department
Reviews
Review Status: Approved
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, March 13, 2013
Reviewer: Victoria Fort
Department /Division /Agency: RWSA
Reviews
As with all new developments in the Crozet service area, RWSA will need to issue a sewer flow acceptance prior to
site plan approval. Please let me know if you have any questions.
Review Status: Requested Changes
c411(' Ai,4
Apar"
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
MEMORANDUM
TO: Architectural Review Board
FROM: Margaret Maliszewski,Principal Planner
RE: SDP-2013-11 and ARB-2013-18: Old Trail Village Block 2B Rutherfoord Hotel
Major Site Plan Amendment
DATE: March 1,2013
Background and Requirements
SDP-2013-11: Old Trail Village Block 2B has been submitted for review as a major site plan amendment.As a result of a
Zoning Ordinance amendment that became effective on January 1,2013,the ARB,as a member of the Site Review
Committee,is required to review and comment on this plan(32.3.3 and 32.4.2.2). The purpose of this ARB review is to
determine consistency of the plan with the EC design guidelines pertaining to 1) size and arrangement of structures,2)
location and configuration of parking areas and landscaping,and 3)preservation of existing vegetation and natural
features(30.6.4(c)(2) and(3)and(5)).This ARB review is limited to the information provided in the initial plan under
Sections 32.5.2-5.As a result of this review,the ARB shall transmit to the agent 1)its requirements to satisfy the design
guidelines,2)recommendations regarding the plan as it relates to the guidelines,and 3)recommended conditions of plan
approval,including conditions to be satisfied prior to issuance of a grading permit.
Review and Recommendations
Staff has reviewed the plan and has determined that it is eligible for staff review as a Countywide Certificate of
Appropriateness for a structure located 750' or more from the Entrance Corridor. Consequently,staff recommends that the
ARB forward the following recommendations to the agent:
• Regarding requirements to satisfy the design guidelines as per 30.6.4(2),(3)and(5):
None.
• Regarding recommendations on the plan as it relates to the guidelines:
None.
• Regarding recommended conditions of initial site plan approval:
ARB approval of a Certificate of Appropriateness is required prior to final site plan approval. The applicant shall
submit an application for a Countywide Certificate of Appropriateness for a structure located 750' or more from
the Entrance Corridor. The applicant is advised that 1)building mass,roof form,building materials/colors,blank
walls, equipment, and landscaping will be the focus of review of the Countywide Certificate of Appropriateness,
and 2)there are discrepancies between the plant schedule and the landscape plan that require correction.
• Regarding conditions to be satisfied prior to issuance of a grading permit:
None.
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: IThursday, February 28, 2013
Reviewer: Shawn Maddox
Department /Division /Agency: Fire Rescue
Reviews
1. If this is to be a sprinklered building the fire department connection location must be shown on the site plan. The
fire department location shall be on the address side of the structure within 50 feet of a hydrant. The fire
department connection and hydrant will not obstruct access to the building for other fire apparatus.
2. Please provide the construction type for this structure to allow for the appropriate fire flow calculation. Once
calculated documentation must be provided to the Fire and Rescue Department that the minimum required fire flow
is available at the site.
Review Status: Requested Changes
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: 1wednesday, February 20, 2013
Reviewer: Andrew Slack
Department /Division /Agency: E911
Reviews
No Objection.
Review Status: No Objection
Review Comments
Project Name: OLD TRAIL, BLOCK 2B- RUTHERFOORD
HOTEL - MAJOR Final Plat
Date Completed: IThursday, February 14, 2013
Reviewer: Jay Schlothauer
Department /Division /Agency: Inspections
Reviews
Based on plans dated February 4, 2013.
Relocate the CG -12 curbcut in the main entrance sidewalk to a location closer to the barrier -free parking spaces, or
provide another curbcut at the closer location.
Review Status: Requested Changes