HomeMy WebLinkAboutSUB201300149 Review Comments 2013-10-14Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: Thursday, May 08, 2014
Reviewer: Sarah Baldwin
Department /Division /Agency:
Reviews
Review Status: Approved
Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: Friday, March 21, 2014
Reviewer: Michelle Roberge
Department /Division /Agency: Engineering
Reviews
This cannot be processed until a road plan for 3B phase is submitted under a new SUB #. This is a placeholder for
this bond estimate until SUB app is submitted.
Review Status: Requested Changes
Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: IThursday, February 06, 2014
Reviewer: Michelle Roberge
Department /Division /Agency: Engineering
Reviews
Based on Plans submitted 1/27/14.
1) Approval of the plat can only be recommended when the road improvements are bonded for phase IIIB, per
section 14 -434 and 14 -435.
Review Status: Requested Changes
Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: Wednesday, February 05, 2014
Reviewer: Sarah Baldwin
Department /Division /Agency: Planning
Reviews
No objection; however ASCA jurisdiction change will have to occur for this sub to be approved.
Review Status: No Objection
Review Comments
Project Name: Hyland Ridge Phase 1116 - Final Final Plat
Date Completed: 1wednesday, December 04, 2013
Reviewer: Sarah Baldwin
Department /Division /Agency: Planning
Reviews
1. Please confirm the cumulative gross density for R -1 on sheet 1. 1 don't calculate it at 55.88, but at 56.48, which
would slightly alter some of the calculations.
2. It is not clear to me if some of these lots are proffered, they seem subject to various rezonings, but that could be
due to old boudary lines. If they are proffered the rezoning (ZMA #) should be reflected on the plan.
Review Status: Requested Changes
Review Comments
Project Name: Hyland Ridge Phase 1116 - Final Final Plat
Date Completed: Monday, December 02, 2013
Reviewer: Jay Schlothauer
Department /Division /Agency: Inspections
Reviews
Based on plat revised August 26, 2013.
No comments or conditions.
Review Status: No Objection
Sarah Baldwin
From: Robbie Gilmer
Sent: Tuesday, November 26, 2013 3:25 PM
To: Sarah Baldwin
Subject: Hyland Ridge Phase Ill B Final Plat
Sara,
I spoke with Keith Lancaster about my comment on Hyland Ridge Phase Ill B Final Plat.They have agreed to install NO
Parking signs around the cul-da-sac to address my comments. I have agreed to sign off on the plat with this
understanding. If you need anything else from me just let me know.
Thank you,
Robert Gilmer
Assist. Fire Marshal
Albemarle County Fire Rescue
460 StageCoach Road
Charlottesville,Va. 22901
Office 434-296-5833
Cell 434-531-6606
1
Service A6thkity
TO: Sarah Baldwin
FROM: Alexander J. Morrison, Civil Engineer
DATE: November 25, 2013
RE: Site Plan Technical Review for: SUB2013149: Hyland Ridge Phase IIIB- Final Plat
The below checked items apply to this site.
✓ 1. This site plan is within the Authority's jurisdictional area for:
✓ A. Water and sewer (Lots 49 -59 Are Currently Designated as "No Service. ")
B. Water only
C. Water only to existing structure
D. Limited service
✓ 2. A 24 inch water line is located approximately 140' distant (additional waterlines
are currently under construction by the developer).
3. Fire flow from, nearest public hydrant, located distant from this site plan, is
Gpm + at 20 psi residual.
✓ 4. An 8 inch sewer line is located approximately 900' distant (additional sewer lines
are currently under construction by the developer).
5. An Industrial Waste Ordinance survey form must be completed.
✓ 6. No improvements or obstructions shall be placed within existing or future
easements.
7. and plans are currently under review.
8. and plans have been received and approved.
9. No plans are required.
✓ 10. Updated utility plans are required for our review and approval prior to granting
approval for SUB2013149.
11. Final site plan may /may not be signed.
12. RWSA approval for water and /or sewer connections.
13. City of Charlottesville approval for sewer.
✓ Comments:
Lot lines for lots 59 -64 do not match the approved construction plans. Submit updated
utility plans for ACSA review to obtain plat approval (Utility plans required for sewer lateral
and water meter location verification as well as easement location in relation to lot lines).
Call out sewer easements as "New Variable Width ACSA Sanitary Sewer Easement."
Call out water line easement extending from cul -de -sac to TMP# 78A -04 -H as "New 20'
ACSA Water line Easement."
168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977 -4511 • Fax (434) 979 -0698
www.serviceauthority.org
Service A6thkity
Lots 49 -59 are currently located outside of the ACSA's Jurisdictional Area and are
designated as "no service." It is the ACSA's understanding that the lots lay within the
Pantops Development Area (Per the attached Pantops Master Plan Land Use Map)
which will require an ACSA Jurisdictional Area Map update by the County prior to the
ACSA granting final plat approval.
Water / wastewater service may not be available until the Hyland Ridge offsite sewer
easement is resolved and approved by the ACSA.
168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977 -4511 • Fax (434) 979 -0698
www.serviceauthority.org
M mo& Canty
Service uth rit
se
The Albemarle County Service Authority (ACSA) has no technical
comments on the SUB being reviewed. Engineering comments are usually
reserved for the site plan review stage. Subdivision plats should correctly
show ownership of properties and existing easements. Recordation of new
easements should occur before dedication to and acceptance by the ACSA.
The ACSA can review the proposed subdivision plat and determine if it
is included in the jurisdictional area for water and /or sewer service.
Water and /or sewer connections to the ACSA system are allotted on a first
come, first served basis at the time connection fees are paid. The ACSA
does not reserve capacity in its system for a specific project.
168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977 -4511 • Fax (434) 979 -0698
www.serviceauthority.org
Service Authobrity
z
| /~
�
~n
^�
At—
Ir—
Now
/
~
�
�
188Spotnap Road ^ Charlottesville ^VA22Q11^ Tel (434)Q77-4511^ Fax (434)07Q'86Q8
Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: 1wednesday, November 20, 2013
Reviewer: Robbie Gilmer
Department /Division /Agency: Fire Rescue
Reviews
Based on Plans dated 8/26/13
1. All roads shall have 20 ft unobstructed travelway.
2. Cul -da -sac's shall be 96 ft FC /FC
Review Status: See Recommendations
Review Comments
Project Name: Hyland Ridge Phase IIIB - Final Final Plat
Date Completed: Friday, November 08, 2013
Reviewer: Andrew Slack
Department /Division /Agency: E911
Reviews
Approved
Review Status: Approved
�pF A
�'717G1L31P
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project:
Plan preparer:
Owner or rep.:
Plan received date:
Date of comments:
Reviewer:
Hyland Ridge Phase IIIB — Final
WW Associates
Pantops - Lakeridge, LLC
10 Oct 2013
25 Oct 2013
Michelle Roberge
RE: Final Plat (SUB201300149)
The engineering review has been completed. Please see below for the following comments.
A. Final Plat (SU13201300149)
1. Approval of the plat can only be recommended when the road improvements are bonded for phase
II113, per section 14 -434 and 435, or when road is built and is accepted into the State System.
2. Phase IIIA has been bonded, but the road improvements will need to be built prior to the approval
of the phase IIIB plat.
3. Label Aspen Drive as "Public."
4. Show existing DB and pg number of temporary turnaround to be vacated.
Sincerely,
/Pi�
Michelle Roberge