HomeMy WebLinkAboutWPO201300022 Review Comments 2013-03-27Project Name:
Date Completed:
Reviewer:
Department/Division/Agency:
Reviews
Comments:
Review Status:
Review Comments
Whittington Subdivision - Phase A
Monday, September 09, 2013
Ana Kilmer
CommDev-Central Ops
Erosion and Sediment Control Plan
8/29/2013- SWA received today. SWA needs corrections.
9/9/2013 - SWA recorded in DEED BOOK 4409, PAGE 660
Approved
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
WPO Plan Review
Project: Whittington Subdivision - Phase A
Number: WPO201300022
Date: 7-11-2013
Reviewer: Max Greene Phone: 296-5832 ext. 3283
This is an abbreviated review comment notice. County engineering staff is available every Thursday
afternoon to discuss details of review. To schedule, please call your reviewer for an appointment.
Erosion & Sediment Control:
(Code Chapter 17, Article II)
Y N
x State standards followed, and Design Standards Manual notes and details
x Adequate limits and perimeter measures out of work areas
x All stages protected adequately
x Adequate channels
Simplify limits of construction, Provide a sediment trap at lot 79 area
Stormwater Management:
(Code Chapter 17, Article III)
Y N
Enough capture and treatment for on-site areas
Enough detention storage for on-site areas
Sealed hydrologic and hydraulic computations provided
No fee, no review
Mitigation:
(Code Chapter 17, Article III)
Y N
Buffers and disturbed areas adequately shown
Adequate plantings at 2:1, or other mitigation provided
N/A
This review attempts to encompass the larger compliance questions. County staff does not assume
responsibility for any calculation or plan details, and cannot cover the intricacies of every plan submitted.
Each plan and calculation must have a professional seal and signature to assume these responsibilities.
This plan is
Adequate
x Not Adequate
Adequate
Not Adequate
Adequate
Not Adequate
Approved (please see attached Approval Fact Sheet)
x Not Approved
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project: Whittington Subdivision – Phase A WPO201300022
Plan preparer: Dominion Engineering [fax 434-979-1681]
Owner or rep.: TRIUMPH WHITTINGTON LLC [8230 Leesburg Pike]
Plan received date: 17 June 2013
Date of comments: 10 July 2013
Reviewer: Max Greene
The Erosion Control Plans (WPO201300022) submitted 17 June 2013 have received Engineering
Review and do not appear to meet Albemarle County minimum checklist items for approval.
Please adequately address the following comments for final approval:
A) Stormwater Management and Mitigation Plan
1) Please post the review fee for SWM along with an updated WPO application form.
B) Erosion Control Plan
1) Please remove the little “No Disturb” areas from the plan. Should the contractor be found in
violation of entering a “No Disturb” area then the project will be delayed until the violation is
abated. The Limits of disturbance should allow for the free flow of construction equipment and
supplies to facilitate expedient grading and stabilization of the site.
2) Please widen the limits of construction for the water and sanitary sewer line installations. The
contractor/operator will most likely require a minimum 40’ temporary construction easement to
install the pipes and manholes.
3)
Once these comments have been addressed, please submit 2 copies of the revised plans, calculations, and
narratives to Current Development Engineering along with the required review fee and transmittal form.
Current Development Engineering is available from 2:30-4 PM on Thursdays to discuss these review
comments. Please contact Max Greene at 434-296-5832 ext. 3283 or email mgreene@albemarle.org to
schedule an appointment.
[17-204.f] An application for an erosion and sediment control plan that requires modifications, terms, or conditions to be
included in order for it to be approved shall be deemed to be withdrawn if the owner fails to submit a revised plan addressing the
omitted modifications, terms or conditions within six (6) months after the owner is informed of the omitted information as
provided under paragraph (B).
File: Document5
Project Name:
Date Completed:
Reviewer:
Department/Division/Agency:
Reviews
Comments:
Review Status:
Review Comments
Whittington Subdivision - Phase A
Wednesday, April 03, 2013
Max Greene
Engineering
Erosion and Sediment Control Plan
Per 17-204.E WPO plan cannot be approved without an approved site plan or Plat. Please submit a preliminary
plat for review and approval.
Application appears to be for the rong parcel. TMP should be 09000000000300
Denied