HomeMy WebLinkAboutARB201300103 Staff Report 2013-08-05ARCHITECTURAL REVIEW BOARD STAFF REPORT
Project #/Name
ARB -2013 -103: GAC Upgrades for Crozet Water Treatment Plant
Review Type
Preliminary review of a Site Development Plan
Parcel Identification
057000000029BO
Location
4675 Three Notch'd Road, on the south side of Route 240, approximately 650' west of Plains Drive
Zoned
Light Industry (LI), Entrance Corridor (EC)
Owner /Applicant
Albemarle County Service Authority /Hazen & Sawyer (Maggie Hennessy)
Magisterial District
White Hall
Proposal
To construct a Granular Activated Carbon facility at the Crozet Water Treatment Plant, including a pre- engineered
metal building.
Context
The immediate area has an industrial character. The surrounding area is a mix of rural character and suburban
residential development.
Visibility
The proposed building will be readily visible from the Entrance Corridor, but the narrow width of the road, the curve
of the road, and the trees on nearby properties limit visibility to an approximate 500' length of the corridor directly in
front of the property.
ARB Meeting Date
September 16, 2013
Staff Contact
Margaret Maliszewski
PROJECT /SITE HISTORY
DATE
APPLICATION /REVIEW TYPE
RESULT
3 -1 -1999
ARB- F(1999)BP -02: Rivanna Water Tank
The ARB approved the installation of two antennas on an existing water tank,
Antenna
subject to conditions.
8 -1 -2006
ARB- 2006 -82: ACSA Water Tower /Cingular
The ARB approved the installation of flush - mounted antennas on an existing
Wireless
water tank, with related ground equipment, subject to conditions.
PROJECT DETAILS
A new building is proposed to house a granular activated carbon (GAC) facility at the Crozet Water Treatment Plant. The proposed structure
is a pre- engineered metal building with metal siding, metal roofing, translucent fiberglass wall panels; single, double and roll -up doors, and
a loading dock. Chain link fence is proposed around the building. Several trees would be removed from the site to make room for the
building and for truck access. The gravel drive would be expanded. No new planting is proposed.
ANALYSIS
REF
GUIDELINE
ISSUE
RECOMMENDATION
Structure design
1
The goal of the regulation of the design of development
The proposed building does not reflect
Consider alternate building
within the designated Entrance Corridors is to insure
the traditional architecture of the area.
locations and /or orientations
that new development within the corridors reflects the
The color of the metal panels for the
to reduce visual impacts and
traditional architecture of the area. Therefore, it is the
walls and roof of the proposed building
to increase landscape
purpose of ARB review and of these Guidelines, that
might help establish a minimal level of
opportunities along the EC.
proposed development within the designated Entrance
coordination throughout the site, but no
Corridors reflect elements of design characteristic of the
colors have been chosen. The primary
Identify for review, and on the
significant historical landmarks, buildings, and
material of the existing water treatment
plan, the color of the metal
structures of the Charlottesville and Albemarle area,
plant is red brick. The brick color is
panels for the walls and roof.
and to promote orderly and attractive development
repeated in other buildings on site.
The wall and roof color shall
within these corridors. Applicants should note that
Representative colors for the type of
be compatible with the
replication of historic structures is neither required nor
metal building that is proposed can be
primary color of the existing
desired.
found at:
water treatment plant.
5
It is also an important objective of the Guidelines to
htlp://www.cecobuildings.com/color-
establish a pattern of compatible architectural
charts.htinl
characteristics throughout the Entrance Corridor in
order to achieve unity and coherence. Building designs
The translucent wall panels are not
should demonstrate sensitivity to other nearby
expected to have a traditional
structures within the Entrance Corridor. Where a
designated corridor is substantially developed, these
appearance. Images of the panels
Guidelines require striking a careful balance between
installed in similar buildings suggest
harmonizing new development with the existing
that they don't appear fully coordinated
character of the corridor and achieving compatibility
with the buildings, but rather have a
with the significant historic sites in the area.
tacked -on appearance. One
manufacturer of this type of panel can
9
Building forms and features, including roofs, windows,
2
doors, materials, colors and textures should be
be found at: http: / /www.kalwall.com/
compatible with the forms and features of the
Kalwall panels are fiberglass- reinforced
significant historic buildings in the area, exemplified by
translucent faces bonded to a grid of
(but not limited to) the buildings described in Appendix
interlocked, structural aluminum/
A [of the design guidelines]. The standard of
composite, thermally broken "I" beams.
compatibility can be met through scale, materials, and
forms which may be embodied in architecture which is
The building would have less impact on
contemporary as well as traditional. The replication of
the EC if it was oriented with the short
important historic sites in Albemarle County is not the
end facing the road or if it was placed in
objective of these guidelines.
a location that allowed increased
planting along the EC.
12
Architecture proposed within the Entrance Corridor
should use forms, shapes, scale, and materials to create
a cohesive whole.
3
New structures and substantial additions to existing
The proposed building has a utilitarian
See other recommendations.
structures should respect the traditions of the
appearance that is not out of place with
architecture of historically significant buildings in the
its industrial use or the general character
Charlottesville and Albemarle area.
of the site, but it is not a typical
10
Buildings should relate to their site and the surrounding
appearance for the ECs. The utilitarian
context of buildings.
appearance is emphasized by the metal
wall panels, the loading dock facing the
EC, and the roll -up door. The utilitarian
appearance could be offset somewhat
with appropriate building colors and
landscaping.
11
The overall design of buildings should have human
The translucent wall panels provide
See other recommendations.
scale. Scale should be integral to the building and site
some scale for the building and help
design.
relieve blankness, although they may
not appear to be a fully integrated
13
Any appearance of "blankness" resulting from building
design should be relieved using design detail or
feature.
vegetation, or both.
The metal panels of the west elevation
and the east end of the north (EC)
elevation are not relieved by any
features or details. The west elevation is
expected to have minimal visibility from
the EC. No planting area has been
provided in front of the north elevation,
and planting to relieve blankness in this
location may appear out of place.
Accessory structures and equipment
17
Accessory structures and equipment should be
The applicant wishes to move the
Revise the plan to include the
integrated into the overall plan of development and
existing shed to a new on -site location.
new location of the existing
shall, to the extent possible, be compatible with the
The location is not specified on the plan,
shed. Consider moving the
building designs used on the site.
but could be directly across the
shed to a less visible location
driveway from the current location.
than the current one.
Roof vents are proposed for the front
and back slopes of the new GAC
facility.
18
The following should be located to eliminate visibility
The existing water treatment plant is
Provide a fence detail in the
from the Entrance Corridor street. If, after appropriate
enclosed by a fence of black chain link
plan. Indicate fence material,
siting, these features will still have a negative visual
with razor wire at the top. New chain
height, and design. The black
impact on the Entrance Corridor street, screening
link fencing is proposed around the
finish is more appropriate for
should be provided to eliminate visibility.
GAC facility. The fence would be
the EC. Revise the fence
a. Loading areas,
located approximately 5' from the sides
location so that it does not
b. Service areas,
of the building and 6' from the front
cross in front of the proposed
c. Refuse areas,
(facing the EC). It would join existing
building.
d. Storage areas,
chain link located south of the proposed
e. Mechanical equipment,
building. The fence would be visible
f. Above - ground utilities, and
from the EC. Its close proximity to the
g. Chain link fence, barbed wire, razor wire, and similar
building would result in an awkward
security fencing devices.
appearance. The chain link would be
less visible and have less impact on the
EC if it did not cross the front of the
building and, instead, attached to the
building at the corners. Typically,
fencing with less of a utilitarian
appearance has been required when
safety fencing is needed in the ECs.
Given the extent of chain link already
existing at this site, this may not be as
important at this location. If chain link
fence is to be added, a black finish
would be more appropriate because it
would match the fence at the main
building and the black finish is
somewhat less obtrusive than the
galvanized finish. There is no fence
detail in the plan.
21
The following note should be added to the site plan and
Drawing M410 shows the proposed
Clarify which new equipment,
the architectural plan: "Visibility of all mechanical
piping associated with the GAC facility.
if any, will be visible from Rt.
equipment from the Entrance Corridor shall be
It is unclear which features /equipment
240.
eliminated."
will be visible above ground, from the
EC.
Lighting
No site or building lighting has been
Confirm that no new site or
proposed.
building lighting is proposed,
or show the proposed lighting
on the plan and provide all
related details.
Landscaping
7
The requirements of the Guidelines regarding
No new trees or shrubs have been
Add tall shrubs among the
landscaping are intended to reflect the landscaping
proposed anywhere on site with this
group of trees identified as to
characteristic of many of the area's significant historic
application.
remain in the area north of the
sites which is characterized by large shade trees and
GAC facility. Ensure that the
lawns. Landscaping should promote visual order within
A group of trees — a mix of 3 evergreen
shrubs are planted in a
the Entrance Corridor and help to integrate buildings
and 6( ?) deciduous - stands adjacent to
natural, informal pattern and
into the existing environment of the corridor.
the EC and is surrounded on site by
existing gravel and asphalt pavement.
that they provide low level
screening for the site.
32
Landscaping along the frontage of Entrance Corridor
streets should include the following:
The evergreens would be removed to
a. Large shade trees should be planted parallel to the
expand the gravel travelway. The
Clarify the level of tree /shrub
Entrance Corridor Street. Such trees should be at least
remaining trees would still constitute a
removal proposed for
3'/z inches caliper (measured 6 inches above the ground)
substantial stand of trees, but the
installation of bio- retention
and should be of a plant species common to the area.
spacing and composition do not meet
area 42. Add new plants to
Such trees should be located at least every 35 feet on
the EC requirements. Tall shrubs added
achieve a natural, informal
center.
b. Flowering ornamental trees of a species common to
among the trees to remain could help
appearance.
with lower level screening of the GAC
the area should be interspersed among the trees
facility, and could help establish visual
Include a plant schedule with
required by the preceding paragraph. The ornamental
order along the corridor. In this location,
all standard information on
trees need not alternate one for one with the large
a frontage treatment that blends with the
the plan.
shade trees. They may be planted among the large
existing rural setting rather than the
shade trees in a less regular spacing pattern.
standard EC frontage planting would be
c. In situations where appropriate, a three or four board
more appropriate.
fence or low stone wall, typical of the area, should align
the frontage of the Entrance Corridor street.
A wooded area of varying width stands
d. An area of sufficient width to accommodate the
west of the group of trees to remain and
foregoing plantings and fencing should be reserved
the existing driveway. It would be
parallel to the Entrance Corridor street, and exclusive of
impacted by the installation of a bio-
road right -of -way and utility easements.
retention area. No details on tree
removal or replanting are provided.
The grass area in front of the existing
water treatment plant contains no trees.
It is the location of a septic field, the
exact extent of which is unknown, so the
opportunity for planting throughout the
area does not exist.
36
Landscaping of buildings and other structures:
The west elevation of the proposed
See other fencing and planting
a. Trees or other vegetation should be planted along the
building is a blank metal wall, but
recommendations.
front of long buildings as necessary to soften the
visibility of this side of the building is
appearance of exterior walls. The spacing, size, and
expected to be minimal. The east end of
type of such trees or vegetation should be determined
the Entrance Corridor elevation of the
by the length, height, and blankness of such walls.
building is blank. Some plants in this
b. Shrubs should be used to integrate the site, buildings,
area could help relieve the blankness
and other structures; dumpsters, accessory buildings
and soften the overall appearance of the
and structures; "drive thru" windows; service areas; and
building. However, plants would be
signs. Shrubs should measure at least 24 inches in
located in the narrow area between the
height.
building and the fence, and this would
likely result in an awkward appearance.
37
Plant species:
A plant schedule was not included in the
Provide a plant schedule in
a. Plant species required should be as approved by the
plan.
the site plan with all standard
Staff based upon but not limited to the Generic
information.
Landscape Plan Recommended Species List and Native
Plants for Virginia Landscapes (Appendix D).
38
Plant health:
The note does not appear on the plan.
Add the following note to the
The following note should be added to the landscape
site plan: "All site plantings
plan: "All site plantings of trees and shrubs shall be
of trees and shrubs shall be
allowed to reach, and be maintained at, mature height; the
allowed to reach, and be
topping of trees is prohibited. Shrubs and trees shall be
maintained at, mature height;
pruned minimally and only to support the overall health of
the topping of trees is
the plant."
prohibited. Shrubs and trees
shall be pruned minimally and
only to support the overall
health of the plant."
6
Site development should be sensitive to the existing
The expanded gravel travelway is not
Consider alternate travelway
natural landscape and should contribute to the creation
sensitive to the existing landscape. Its
layouts and building locations
of an organized development plan. This may be
layout requires the removal of several
and /or orientations to reduce
accomplished, to the extent practical, by preserving the
trees along the EC frontage. Additional
visual impacts and to increase
trees and rolling terrain typical of the area; planting new
trees would be removed at the proposed
landscape opportunities and to
trees along streets and pedestrian ways and choosing
building location. An alternate
reduce impacts on the EC.
species that reflect native forest elements; insuring that
travelway layout and building
any grading will blend into the surrounding topography
location /orientation could result in a
thereby creating a continuous landscape; preserving, to
more appropriate appearance for the EC.
the extent practical, existing significant river and stream
The applicant has indicated that the
valleys which may be located on the site and integrating
travelway expansion is required as
these features into the design of surrounding
designed to accommodate trucks at the
development; and limiting the building mass and height
site, and alternate building
to a scale that does not overpower the natural settings of
locations /orientations are not possible
the site, or the Entrance Corridor.
due i conflicts with utilities and other
39
The relationship of buildings and other structures to the
Entrance Corridor street and to other development
site issues.
within the corridor should be as follows:
a. An organized pattern of roads, service lanes, bike
paths, and pedestrian walks should guide the layout of
the site.
b. In general, buildings fronting the Entrance Corridor
street should be parallel to the street. Building
groupings should be arranged to parallel the Entrance
Corridor street.
c. Provisions should be made for connections to
adjacent pedestrian and vehicular circulation systems.
d. Open spaces should be tied into surrounding areas to
provide continuity within the Entrance Corridor.
e. If significant natural features exist on the site
(including creek valleys, steep slopes, significant trees
or rock outcroppings), to the extent practical, then such
natural features should be reflected in the site layout. If
the provisions of Section 32.5.6.n of the Albemarle
County Zoning Ordinance apply, then improvements
required by that section should be located so as to
maximize the use of existing features in screening such
improvements from Entrance Corridor streets.
f. The placement of structures on the site should respect
existing views and vistas on and around the site.
20
Surface runoff structures and detention ponds should
Two new bioretention areas are
Provide verification from a
be designed to fit into the natural topography to avoid
proposed to the west (42) and northwest
certified arborist that the
the need for screening. When visible from the
(41) of the GAC facility. The
proposed fill, grading, and
Entrance Corridor street, these features must be fully
installation of 42 would require some
digging required to install the
integrated into the landscape. They should not have
clearing of an existing wooded area
piping and other site work
the appearance of engineered features.
located west of the existing driveway.
Individual trees in this area are not
will not be detrimental to the
health of the trees designated
41
No grading, trenching, or tunneling should occur
within the drip line of any trees or other existing
identified on the plan and tree protection
to remain. Provide an
features designated for preservation in the final
is not shown in this area.
arborist's plan outlining
Certificate of Appropriateness. Adequate tree
measures to ensure the health
protection fencing should be shown on, and
Grading and utility work are proposed
of the trees throughout and
coordinated throughout, the grading, landscaping and
within the dripline of trees to remain. It
after the work. Include the
erosion and sediment control plans.
is not clear to what extent this work will
arborist's measures on the site
negatively impact the trees. Information
plan drawings.
from a licensed arborist could help
clarify this.
Identify on the plan the size
and species of the trees to
remain in the area at the
middle of the gravel drive and
in the area west of the
SUMMARY OF RECOMMENDATIONS
Staff recommends the following as the primary points of discussion:
1. Utilitarian appearance of the GAC facility /loading and service areas
2. Blankness of the building
3. Color of the building
4. Appearance of the translucent wall panels
5. Visibility of equipment
6. Lack of new trees /shrubs
7. Landscaping along the EC
Staff offers the following comments on the preliminary plan:
1. Consider alternate travelway layouts and building locations and /or orientations to reduce visual impacts and to increase landscape
opportunities along the EC.
2. Identify for review, and on the plan, the color of the metal panels for the walls and roof. The wall and roof color shall be compatible with
the primary color of the existing water treatment plant.
3. Revise the plan to include the new location of the existing shed. Consider moving the shed to a less visible location than the current one.
4. Provide a fence detail in the plan. Indicate fence material, height, and design. The black finish is more appropriate for the EC. Revise the
fence location so that it does not cross in front of the proposed building.
5. Clarify which new equipment, if any, will be visible from Rt. 240.
6. Confirm that no new site or building lighting is proposed, or show the proposed lighting on the plan and provide all related details.
7. Add tall shrubs among the group of trees identified as to remain in the area north of the GAC facility. Ensure that the shrubs are planted
in a natural, informal pattern and that they provide low level screening for the site.
9
driveway along the EC.
42
Areas designated for preservation in the final Certificate
No tree conservation plan or checklist
Provide a tree conservation
of Appropriateness should be clearly delineated and
has been provided.
plan and checklist. Provide
protected on the site prior to any grading activity on the
tree protection in the areas
site. This protection should remain in place until
impacted by the construction
completion of the development of the site.
of bio- retention area 42.
43
Preservation areas should be protected from storage or
movement of heavy equipment within this area.
SUMMARY OF RECOMMENDATIONS
Staff recommends the following as the primary points of discussion:
1. Utilitarian appearance of the GAC facility /loading and service areas
2. Blankness of the building
3. Color of the building
4. Appearance of the translucent wall panels
5. Visibility of equipment
6. Lack of new trees /shrubs
7. Landscaping along the EC
Staff offers the following comments on the preliminary plan:
1. Consider alternate travelway layouts and building locations and /or orientations to reduce visual impacts and to increase landscape
opportunities along the EC.
2. Identify for review, and on the plan, the color of the metal panels for the walls and roof. The wall and roof color shall be compatible with
the primary color of the existing water treatment plant.
3. Revise the plan to include the new location of the existing shed. Consider moving the shed to a less visible location than the current one.
4. Provide a fence detail in the plan. Indicate fence material, height, and design. The black finish is more appropriate for the EC. Revise the
fence location so that it does not cross in front of the proposed building.
5. Clarify which new equipment, if any, will be visible from Rt. 240.
6. Confirm that no new site or building lighting is proposed, or show the proposed lighting on the plan and provide all related details.
7. Add tall shrubs among the group of trees identified as to remain in the area north of the GAC facility. Ensure that the shrubs are planted
in a natural, informal pattern and that they provide low level screening for the site.
9
8. Clarify the level of tree /shrub removal proposed for installation of bio- retention area 42. Add new plants to achieve a natural, informal
appearance along the EC.
9. Provide a plant schedule in the site plan with all standard information.
10. Add the following note to the site plan: "All site plantings of trees and shrubs shall be allowed to reach, and be maintained at, mature
height; the topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to support the overall health of the plant."
11. Provide verification from a certified arborist that the proposed fill, grading, and digging required to install the piping and other site work
will not be detrimental to the health of the trees designated to remain. Provide an arborist's plan outlining measures to ensure the health
of the trees throughout and after the work. Include the arborist's measures on the site plan drawings.
12. Identify on the plan the size and species of the trees to remain in the area at the middle of the gravel drive and in the area west of the
driveway along the EC.
13. Provide a tree conservation plan and checklist. Provide tree protection in the areas impacted by the construction of bio- retention area 42.
TABLE A
This report is based on the following submittal items:
Sheet #
Drawing Name
Drawing Date /Revision Date
C40
Existing Conditions and Demolition Plan
March, 2013
C41
Erosion Control and drainage Plan
March, 2013
C42
Site Plan
March, 2013
A4652
Architectural — Elevations
March, 2013
-
Photos: site and examples of metal buildings and translucent panels
-
10