Loading...
HomeMy WebLinkAboutWPO202000053-5553-Full Inspection ReportV NOTICE TO COMPLY Hand delivered Project: WP0202000053 PLEASANT GREEN PHASE II - VSMP - DIGITAL Operator/Contractor: Contour Construction STANLEY MARTIN COMPANIES LLC Issued Date: 3/9/2023 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the referenced project and to immediately take corrective measures to address erosion and sediment control deficiencies on this property. This Notice to Comply is being issued because of the following deficiencies: Deficiency: Coverage letter, permits or contacts posted at entrance Corrective Action: Must have coverage letter permits and contacts posted at entrance. Deficiency: Fill dirt is being exported off site to a non permitted site. Corrective Action: Must submit an ammendment to County of Albemarle showing new off site borrow area and increased distribuance activities. Deficiency: exported soils have not been recorded in SWPPP Corrective Action: Must record, in SWPPP, any exported material to permitted or non permitted site. Unless subsequently amended in writing by this office, it is expected all of these corrective measures will be completed by. Reinspections as a result of this notice to verify corrective measures will incur a $170 fee for the first reinspection and $270 for each subsequent reinspection for single-family dwelling units (§ 17-207). Reinspections as a result of this notice to verify corrective measures will incur a $283 fee for the first reinspection and $383 for each subsequent reinspection for VESCP and VSMP permits (§ 17-207 and § 17-208). Failure to take effective corrective measures will result in a Stop Work Order upon reinspection. A 4% technology fee is due with each payment. County Inspector Name: John Yerby County Inspector Phone Number: (434) 296-5832 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: PLEASANT GREEN PHASE II - VSMP - DIGITAL project/WPO Number: WP0202000053 Project Address: DEQ Permit Number (if applicable): VAR10M834 Project Operator: Contour Construction Operator Telephone #: (434) 244-0001 Project Contact: STANLEY MARTIN COMPANIES LLC Contact Telephone #: Contact E-Mail: odonnellgp@stanleymartin.com Qualified Personnel (QP): Gregg O'Donnell Inspector: John Yerby Qualified Personnel (QP) Email: Disturbed Acreage: Weather (Wet/Dry/Rain): Sunny Single -Family: Inspection Date & Time: 3/9/2023 Stage of Construction: Grading Other Email: backstromC@stanleymartin.com Re -Inspection: No Other Email: ShifflettSD@stanleymartin.com Bond Inspection: No Other Email: rushdw@stanleymartin.com COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? Yes Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) Yes (9VAC25-870-310)(Alb. Co. Code §17-300, 17-302) A copy of the notice of coverage letter is posted conspicuously near the No Coverage letter, permits or contacts posted at 2 main entrance of the construction activity? (CGP Part II.C) entrance Notice of the location of the SWPPP is posted near the site's entrance, if NIA 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the 7 construction activity, including the function of the project? (CGP Part II A.1.d) Page 1 of 6 The SWPPP includes a legible site plan identifying all appropriate 8 measures and that includes the locations of support activities and the onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) 9 The SWPPP contains the name, phone number and qualifications of "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III K? (CGP Part II A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part II A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? Yes Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the No discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that No existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are Yes identified? (CGP Part II B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major N/A 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part II B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? N/A (CGP Part II B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final N/A stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer N/A had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and N/A measures taken to prevent the recurrence of any prohibited discharge? (CGP Part II B.4(e-f)) (9VAC25-870-54.G) 24 Amendments, modifications, or updates to the SWPPP are signed in N/A accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? No Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) Page 2 of 6 26 Inspection reports are completed and signed in accordance with CGP Part II F (3-4)? (CGP Part II F (3-4)) 27 Corrective actions are taken consistent with the requirements of the CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? No Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the plan? Sequencing of the project is implemented in accordance with the 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization been stabilized, and have stabilization requirements for impaired waters, 30 approved TMDL(s), pollutants of concern and exceptional waters, when applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are sediment traps and basins installed in accordance with MS-6 and the 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? 38 (9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are stormwater conveyance channels adequately stabilized with channel 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are soil and mud kept off paved or public roads to minimize the transport 45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Page 3 of 6 Have all temporary control structures that are no longer needed been 46 removed and disturbed soil resulting from their removal permanently stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately 47 protected from erosion, sediment and damage in accordance with the standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? No Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) 53 Concrete wash water is directed into a leak -proof container or leak -proof settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from 54 storage, handling, and disposal of construction products, materials, and wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential 56 pollutant -generating activities not addressed above, when applicable? (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 6 Notes: CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT REQUEST FOR CORRECTIVE ACTION Project Name: Permit Number (if applicable): Date: Regulatory Occurrence Observation/Recommended Corrective Action Checklist # Citation/Legal requirement' Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: Observation: Recommended Corrective Action: 1 Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Page 5 of 6 Corrective Action Deadline: Re -Inspection Date: Comments: The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for ensuring compliance on the above project. Page 6 of 6 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 2 (CGP Part II.C) Coverage letter, permits or Must have coverage letter contacts posted at entrance permits and contacts posted at entrance. 16 (CGP Part II B(1)) Fill dirt is being exported off Must submit an ammendment (9VAC25-870-54.G) site to a non permitted site. to County of Albemarle showing new off site borrow area and increased distribuance activities. 17 (CGP Part II B(2)) exported soils have not been Must record, in SWPPP, any (9VAC25-870-54.G) recorded in SWPPP exported material to permitted or non permitted site. Recommended 3/16/2023 Corrective Action Deadline: Targeted Re- 3/16/2023 Inspection Date: Comments: post required permits and contact info. Have record of permit for receiving site for export, maintain export log as required, cease all export until permitted site is identified. *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 2 Ti m e P h oto_20230309_ 102812.j pg.j pg Photos for Item 4 Photos for Item 10 511.36KB ._ RA n Photo Description: Example of no permit or contacts Photo Description: Photo Description: Photos for Item 17 TimePhoto_20230309_102623.jpg.jpg 176.28KB Other Photos Photo Description: Activity log Photo Description: COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Inspection Date: 3/9/2023 County Inspector Charlottesville, Virginia 22902 434 296-5832