HomeMy WebLinkAboutWPO202200033 Review Comments WPO VSMP 2023-03-10�q oe atg 401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
A County Of Albemarle Telephone:434-296-5832
m COMMUNITY DEVELOPMENT DEPARTMENT WWW.ALBEMARLE.ORG
VSMP Permit Plan Review
Project title:
LOTA-13 BUNDORAN FARM
Project file number:
WP0202200033
Plan preparer:
Justin Shimp [Justin@shimp-engineering.com]
Owner or rep.:
Enoch Snyder [enoch@snyderdesignbuild.com]
Plan received date:
July 22, 2022
Feb. 8, 2023
Date of comments:
August 26, 2022
March 10, 2023 (Rev.1)
Reviewer:
David James [djames2@albemarle.org]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied/approved.
The rationale is given in the comments below. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP
must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. You are only required to complete the SF SWPPP. View template here-
https://www.albemarle.org/home/showpublisheddocument/2662/6378655379265000
00
(Rev.1) Update with approved plan.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Provide PPP measures. (Rev.1) Appears complete, update to match approved plan.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is denied, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-
403.
1. Cover: Add WPO# to title. (Rev.1) Addressed.
2. Level spreaders:
Ensure design meets water quantity standards per BMP Spec. #2, Sec. 6.3. Including but
not limited to:
a. A bypass/overflow to pipe/channel will be necessary for design flows greater
than the 1-in/hr storm or consider an alternate (LS) design.
b. Provide a minimum 6' channel width from c/I to lip.
(Rev.1) Level spreader designs appear to be adequate. Provide LS maintenance plan.
3. Level spreader C should be relocated outside of the stream buffer. Provide justification
Engineering Review Comments
Page 2 of 3
(of reasonable use) to keep it there otherwise. (Rev.1) Addressed.
4. Sheet C3, etc.: Ensure fill disturbance will be no more than 30 LF of stream. [17-604 C(3)]
(Rev.1) Acknowledged. More information about the installation is requested, see
comment D.3.
5. Calcs: Sh. 26, Revise: I noticed the 10-yr ditch velocities are lower than the 2-yr. (Rev.1)
Acknowledged.
6. Provide analysis of ditches specifically 4 &5: It is preferable to use more current and
conservative rainfall values for ditch design and wondering how you arrived at those
values. (Rev.1) Addressed.
7. (Rev.1) Provide predevelopment land cover information (Not shown on plans or with
calcs). Need predevelopment information to make evaluation of how much increase in
postdevopement runoff.
8. (Rev.1) Provide postdevelopment land cover with percentages of each cover type.
9. (Rev.1) Water quality requirements will need to be met.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
1. Provide county's paved construction entrance detail per ACDSM, p. 9. (Rev.1) Not
addressed.
2. Provide culvert inlet trap design (DA>1ac) & detail. [VESC HB, 3.08] (Rev.1) The DA
received to the CIP is a bit high. Please provide check dams along ditches 2 & 4.
3. Provide utility stream crossing (USC), VSS, SSS for culvert installation and bank
stabilization & details. [VESC HB, 3.22, 3.23, 3.25] (Rev.1) Not fully addressed. Provide
more information about the culvert installation. What will prevent culvert from moving
if not embedded? Provide photos of stream bank & ex. culvert. Cofferdam is mentioned
in USC specs. Provide that installation and stabilization are met per the spec.
4. (Rev.1) Provide photos with measurements of existing crossing width and rock cover
diameter. The existing crossing should meet the minimum specifications of 3.24 (SC) for
construction vehicles.
5. Revise: Sed. Trap - The weir width should be 6 x D.A. (12.42-ft). A & C elevations should
be swapped in the table. [VESC HB, 3.13] (Rev.1) Addressed.
6. Provide silt fence around proposed drainfield and downhill of sed. trap. (Rev.1)
Addressed.
7. (Rev.1) Sheet C2: Show existing treeline.
8. (Rev.1) Note: Disturbance is over an acre and prior to land disturbance will need a DEQ
SF CGP, SF SWPPP approved, ESC/WPO plan approved, SW AGMT signed, and posted
bonds.
https://www.al bemarle.org/home/showpubl isheddocument/2710/637867521357670
000
F. Mitigation Plan (MP)
1. Appears to be adequate but may need to be revised to address all comments. (Rev.1)
Acknowledged.
Engineering Review Comments
Page 3 of 3
The VSMP permit application and all plans may be resubmitted for approval when all comments
have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete
permit package with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a
meeting to discuss this review.
Process:
After approval, erosion and sediment control and stormwater management improvements must
be bonded. The bonding process begins when the plan is approved, and the applicant submits a
bond estimate request form and fee to the Department of Community Development. A plan
reviewer will prepare estimates and check parcel and easement information based on the
approved plans. The County's Management Analyst will prepare bond agreement forms, which
will need to be completed by the owner and submitted along with cash, certificates or sureties
for the amounts specified. The agreements will need to be approved and signed by the County
Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and
forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and
recorded. The County's Management Analyst or other staff will prepare the forms and check for
ownership and signature information. The completed forms will need to be submitted to the
County, who will record the agreement.
After bonding and agreements are complete, county staff enters project information in a DEQ
database for state application processing, if a DEQ permit is required. DEQ reviews the
application information based on local VSMP authority approval. At this time, the DEQ portion of
the application fees will need to be paid directly to the state. For fastest processing, this is done
electronically with the emails provided on the application. DEQ should notify applicants with
instructions on how to pay fees. When DEQ approves the application, they will issue a permit
coverage letter, which must be posted at the construction site.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction
conference. Applicants must complete the request for a pre -construction conference form and
pay the remainder of the application fee. The form identifies the contractor and responsible land
disturber, and the fee remaining to be paid. This will be checked by county staff, and upon
approval, a pre -construction conference will be scheduled with the County inspector. At the pre -
construction conference, should everything proceed satisfactorily, a joint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
https://www.albemarle.org/govern ment/community-development/apply-for/engineeri ng-applications