Road bond inspection
Bond Title: Whittington Phase B (Phase 133)
File Number: SLJB201400193
Date of inspection: 02/16/2022
401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
Telephone: 434-296-5832
WWW.ALBEMARLE.ORG
Original Bond Amount: $852,540
Reviewer: John Anderson Current Bond Amount: $852,540
Phone: (434) 296-5832 -x3069 Updated Bond Amount: $170,510
Bond Inspection Checklist date: Feb 19.2022
Your bond inspection request has been processed. This list contains an update on the items received and approved.
Received
Y N
■ El
El
❑ ■
❑ ■
■ ❑
■ ❑
■ ❑
■ ❑
■ ❑
■ ❑
❑ ❑
❑ ■
■ ❑
Approved
Y N N/A VDOT
Completed inspection request and fee
As -built plan, updated, sealed to current date, per As -built policy*
Copies of recorded plats for right-of-way, easements
VDOT approval AM-4.3, or partial completion via punch]ist
Letter from P.E. certifying improvements to date are built to plan
Current certification form completed by owner/developer (for release)
CBR test reports for each road; Also, item 2.- below
Stone depth and material inspection reports (or core tests)
Pavement depth and material inspection reports (or core tests)
Compaction test reports for fill areas under road
Pipe trench inspection reports (if available)
Pipe interior inspections reports and video
Concrete test reports for structural concrete, curbing, aprons, etc.*
Structural inspection reports for any bridges or box culverts
County road name signs and posts, or a sign agreement for alt. posts
Road Name signs installed- but also, item 4.- below.
' No concrete curb or sidewalks.
.. RGA As -built is not sealed, but stamped Progress Aunt -this is unusual (wracceptable).
For bond release:
1. Acceptance of public streets by VDOT (Phase B3 street/s, Cottontail Wavy.
2. Provide As -built pavement design using (as -built) base /surface asphalt values /depth and F&R
CBR values.
a. F&R reports for Sta. 13+00, 19+00, 24+00: CBR values 7.4, 4.0 and 17.5, respectively.
b. Ref. 12/15/17 F&R Asphalt report (report d. 12/27/17), 4" base.
c. Reference and revise/resubmit as needed F&R report No. AND:7121-05040, test d. 7/23/21:
Revise asphalt course column to read asphalt surface. 2" layer thickness. (asphalt base
should read asphalt surface, since placed in 2021).
Engineering Review Comments
Page 2 of 3
d. Ensure As -built condition meets design (DP > D,). Ensure As -built drawing captures /reports
this information (As -built pavement section meets design, though layer depths may vary).
3. Install guardrail per approved Road Plan, sheet RP9, RP10. Guardrail is mandatory at locations
shown, is approved by VDOT, and is required for bond release /public street acceptance.
4. Sheet 10: Install pedestrian bridge similar to bridge depicted in photo below (bridge in Phase B1),
since road design directs runoff via 36" RCP beneath the road then across riprap to a point not
served by a pedestrian bridge, with trail subsequently severely eroded and unacceptably impacted.
This road design anticipated a pedestrian bridge without which road design impacts an amenity
feature, and drainage design itself unacceptable. A pedestrian (trail) bridge at this location, at
approx. Cottontail Way Sta. 25+00, is required for bond release. Photos, below.
5. Ensure county road name signs /posts meet requirements at Road Naming and Properly
Numbering Ordinance and Manual, rev. Oct-20, 2021, especially sign /lettering reflectivity:
https://www.albemarle.org/home/showpublisheddocumentl 11175/6377196493 33400000 ; ref.
TIDE pg. 16 /document p¢. 11.
Engineering Review Comments
Page 3 of 3
Please refer to on-line content at Engineering Applications (
https://www.albemarle.org/govemment/community-development/applly-for/engineering-applications ) for road
inspection checklist and public /private road acceptance procedures.
bond inspection checklist _SUB201400193_Whittington_Phase B-B3_021922.docx