Subject: Biscuit Run Park Phase 1 Entrance and Parking
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Hi Kevin,
We submitted the revised SDP plans for the Entrance and Parking Lot project this afternoon. For reference, we also
included the Rt. 20 Road Plans that were prepared by Kimley Horn.
As Steve mentioned yesterday, the revised Plans are very similar in scope to the previous SDP submission back in 2021.
However, some of the details have changed including:
• Kimley Horn is preparing the Rt. 20 Road Plans. We attached their plans to the submission for reference.
• The parking area and landscape was simplified based on the current construction budget.
• The design was adjusted in order to avoid existing delineated wetlands on the site.
• The Stormwater Management strategy includes three water quantity basins and covers both Park and Road
improvements.
A link to the downloaded submission is attached for your convenience.
https://www.dropbox.com/sh/ak3mbeabrOw6sd5/AMFKFRCxvh uw3iwKFOacT7a?dl=0
Please let me know if you have any immediate questions or concerns with the submission.
Thanks and have a great weekend.
David