Justin Shimp
Dominion Development Resources
172 South Pantops Dr.
Charlottesville, VA 22911
RE: ARB2007 -00108 Rivers Edge Furniture Store
Tax Map 78, Parcel 58G
Dear Justin:
I have reviewed your recent submittal for the above referenced project, which included: Sheet A1.0 with
revision date of 4/21/08 and site plan sheets S 1 through S8 with revision date of 5/27/08. I have the following
comments based on our letters of December 7, 2007 and December 21, 2007:
1. Spillover exceeds .5 footcandles at the property line along Route 20.
• Revise the photometric plan to limit spillover to less than .5 footcandles.
2. The ARB stated that shrubs should be added to further screen the loading dock and the lower parking area
from the EC, and the ARB suggested that additional trees might be required at the end of the extended
parking lot. This area is on the north /east side of the building, not on the west side as suggested by your
recent memo. In addition, the existing cedar tree near the dumpster is now to be removed. This leaves a
gap in the proposed planting. Furthermore, you've reduced the northern parking lot by the requested 6
spaces, but you did not add landscaping in place of the parking that was removed, as the ARB directed.
• Add landscaping in the area that was previously occupied by parking near the EC. Revise the
planting to further screen the loading dock and lower parking area from the EC and to fill in the
gaps created by trees to be removed. Ensure that all landscaping is coordinated throughout.
3. On the east elevation, the height of the masonry opening for the front arcade was not revised.
• Correct the east elevation that shows a tall masonry opening at the front arcade so that the top of
the masonry opening for the arcade matches the top of the masonry opening of the first floor
windows.
4. The louver has not been increased in size.
• Revise the elevations to provide a much larger louver.
Please provide:
1. Two full sets of revised drawings addressing each of these conditions. Include updated ARB revision
dates on each drawing.
2. A memo including detailed responses indicating how each condition has been satisfied. If changes
other than those requested have been made, identify those changes in the memo also. Highlighting the
changes in the drawing with "clouding" or by other means will facilitate review and approval.
3. The attached "Revised Application Submittal" form. This form must be returned with your revisions to
ensure proper tracking and distribution.
When staffs review of this information indicates that all conditions of approval have been met, a Certificate of
Appropriateness may be issued.
If you have any questions, please do not hesitate to contact me.
Sincerely,
Margaret Maliszewski
Principal Planner
CC: Ron Carter
1340 Stony Point Road
Charlottesville, Va 22911
Free Bridge Land Trust; Charles Wm Hurt & Shirley L Fisher Trustees
P0 Box 8147
Charlottesville, Va 22906
Gerald Gatobu, Zoning and Current Development
COUNTY OF ALBEMARLE
Department of Community Development
REVISED APPLICATION SUBMITTAL
This form must be returned with your revisions to ensure proper tracking and distribution. County staff
has indicated below what they think will be required as a resubmission of revisions. If you need to submit
additional information please explain on this form for the benefit of the intake staff. All plans must be
collated and folded to fit into legal size files, in order to be accepted for submittal.
TO:
Justin Shimp
DATE:
PROJECT NAME: ARB2007 -108 Rivers Edae Furniture
Submittal Type Requiring Revisions ( ) indicates submittal Code
County Project Number
# Copies
Erosion & Sediment Control Plan (E &S)
# Copies
Distribute To:
Mitigation Plan (MP)
2
Margaret
Maliszewski
Waiver Request (WR)
Stormwater Management Plan (SWMP)
Road Plan (RP)
Private Road Request, with private/ public comparison (PRR)
Private Road Request — Development Area (PRR -DA)
Preliminary Site Plan (PSP)
Final Site Plan (or amendment) (FSP)
Final Plat (FP)
Preliminary Plat (PP)
Easement Plat (EP)
Boundary Adjustment Plat (BAP)
Rezoning Plan (REZ)
Special Use Permit Concept Plan (SP -CP)
Reduced Concept Plan (R -CP)
Proffers (P)
Bond Estimate Request (BER)
Draft Groundwater Management Plan (D -GWMP)
Final Groundwater Management Plan (F -GWMP)
Aquifer Testing Work Plan (ATWP)
Groundwater Assessment Report (GWAR)
Architectural Review Board (ARB)
ARB2007 -00108
Other: Please explain
(For staff use only)
Submittal Code
# Copies
Distribute To:
Submittal Code
# Copies
Distribute To:
ARB
2
Margaret
Maliszewski