COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: SDP - 2008 -00102 & WPO- 2008 - 00051, Mt. Calvary Baptist Church
Plan preparer: Tom Muncaster, DDR [fax: 434 - 979 -1681 ]
Owner or rep.: Mt. Calvary Baptist Church
Plan received date: May 13, 2008
Date of comments: June 27, 2008
Reviewer: Andrew Lowe
The final site plan for Mount Calvary Baptist Church, submitted on 5/13/08, has been reviewed.
The plans cannot be approved as submitted and will require the following changes /corrections
prior to final approval. Engineering is available from 2 -4 PM on Thursdays to discuss these
review comments. Please call Andy Lowe at 434 - 296 -5832 ext. 3860 or email
alowe @albemarle.orc to schedule an appointment.
Please note that Albemarle County has updated the Design Manual [DM]. The DM and
Engineering Review Final Plan Checklist can be downloaded from the County's web site under
the subtitle "Design Standards ".
A. Final Site Plan (SDP- 2008 - 00102)
1. VDOT final approval is needed before engineering can recommend final approval.
2. Please provide an entrance profile.
3. Provide sight distance triangle.
4. Provide specific detail and dimensions (outside footer to inside guardrail) for the retaining wall
and guardrail at the parking spaces. It may not meet minimum requirements for parking overhang
of 2 feet. [18- 4.12.6.C.6]
5. Show guardrail at the upper parking lot near the building.
6. Clarify the location where the wall begins and ends. It does not appear to end at the location
shown.
7. Provide temporary grading easements on parcels 58A1 -17, 58A1 -23 & 58A1 -24.
8. Show curb throughout the parking and travelways.
9. Provide stormwater pipes details and profiles.
10. All parking rows must be protected by minimum 3' curbed island. [18 -4.12]
11. There appears to be slopes steeper than 2:1 at the culvert crossing Morgantown Road. Please show
a blow -up detail with additional topography in this area including the grading for the new ditch.
12. Additional comments may be forthcoming during next review due to revisions.
B. Erosion and Sediment Control Plan: WPO- 2008 -00051
1. Please provide a diversion dike from the sediment trap along the east boundary line to direct flow
the rest of the site.
2. Provide details for all ESC practices per Virginia Erosion and Sediment Control Handbook.
3. Additional comments may be forthcoming during next review due to revisions.
Engineering Review Comments
Page 2 of 2
C. Stormwater Management Plan: WPO- 2008 -00051
4. Please provide manufacturer's approval letter for the Filterra units.
5. Please provide manufacturer's approval letter for the Raintanks.
6. Provide Minimum Standard 19 Adequate Channel information for the concentration of stormwater
from structure #1.
7. For drainage area #2 show the grading work necessary for the level spreader installation and
provide detail with comps. The slope from the level spreader must be 10% and adequately
stabilized with grass to prevent erosion.
8. Additional comments may be forthcoming during next review due to revisions.
File: El_fsp _ esc_SWM_ADL_Wpo- 2008 -00051 Mt Calvary Baptist Church.doc