HomeMy WebLinkAboutSUB200700077 Bond Estimates Bond Estimate 2008-07-09Stonewater Subdivision ROAD Construction Bond Estimate (roads, site work, storm sewer) Item Item contigency No. Unit Unit Cost Cost Number 107.4 cy $35.91 installed 2 blotted or prime &double seal Stonewater Drive 10 +00 to 22 +00 road length 1200.0 tt 644.4 sy $6.30 1 aggregate base 6.0 in d 1200.0 ft L 29.0 ft W 644.4 cy $35.91 $23,142.00 2 blotted or prime &double seal 1200.0 ft L 29.0 ft W 3866.7 sy $6.30 $24,360.00 3 asphalt base 3.0 in d 1200.0 ft L 24.0 ft W 403.2 tons $73.50 $29,635.20 4 asphalt surface 2.0 in d 1200.0 ft L 24.0 ft W 268.8 tons $81.90 $22,014.72 6 curb CG -2 200.0 ft L 4.0 ft W 0.0 ft $8.40 $0.00 7 curb CG -6 2400.0 ft $13.83 $33,188.40 8 sidewalk, asphalt 0.0 in d 1200.0 ft L 4.0 ft W 0.0 tons $73.50 $0.00 9 sidewalk, concrete 5' width 2400.0 ft $14.57 $34,965.00 10 ramp CG -12 6 $315.00 $1,890.00 11 street name sign 0 ES @D$3700 3 $65.00 $195.00 12 traffic control sign 3 $49.35 $148.05 13 guardrail (or rebuild wall in right -of -w 0 ES @D$3700 0.0 ft $16.80 $0.00 14 manhole or drop inlet 0 ES -1,2 $250 35 $1,365.00 $47,775.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 1104.0 ft $23.10 $25,502.40 17 pipe, rcp (15 to 48 ") 18.0 in d 0 ES -1,2 $250 0 EC -1 $200 451.0 ft $27.30 $12,312.30 18 pipe, rcp (15 to 48 ") 24.0 in d 0 ES -1,2 $250 133.0 ft $39.90 $5,306.70 19 pipe, rcp (15 to 48 ") 30.0 in d 0 ES -1,2 $250 0 EC -1 $200 110.0 ft $63.00 $6,930.00 20 pipe, rcp (15 to 48 ") 36.0 in d 1 ES -1,2 $250 1 EC -1 $200 66.0 ft $89.25 $6,340.50 21 rip -rap, placed 200.0 ft L 30.0 ft W 0.0 ton $31.50 $0.00 22 E &S fabric,EC -2,3 0 ft L 4 ft W 0.0 sy $10.50 $0.00 23 clear and grub (for wooded sites) 1200.0 ft L 30.0 ft W 0.8 acre $10,500.00 $8,677.69 24 grading (per cy for cut or import only; 1200.0 cy fill 600.0 cy cut 1200.0 cy $3.15 $5,670.00 24 CBR tests (1 every 0.1 mi. per road) 1200.0 ft L 2.4 inc of 500' 3 $157.50 $535.50 25 as -built drawings (1 k + price per 0.1 1200.0 ft L 0.227 mi. 3 $1,050.00 $4,150.00 26 survey and layout (price per 0.1 mi.) 1200.0 ft L 0.227 mi. 3 $525.00 $2,575.00 27 mobilization 1 $525.00 $525.00 28 VDOT surety (1 lane) 1200.0 ft L 0.227 mi. 2 Lanes $2,000.00 $9,090.91 29 VDOT maintenance fee (1 In rd, 1 yr) 1200.0 ft L 0.227 mi. 2 Lanes $150.00 $681.82 30 VDOT admin. Cost recovery fee(1 Iar 1200.0 ft L 0.227 mi. 2 Lanes $100.00 $704.55 cost surd $306,315.73 contigency 25% $76,578.93 Total $382,900 Stonewater Ct 0 +00 to 2 +00 road length 200.0 ft 1 aggregate base 6.0 in d 200.0 ft L 29.0 ft W 107.4 cy $35.91 $3,857.00 2 blotted or prime &double seal 200.0 ft L 29.0 ft W 644.4 sy $6.30 $4,060.00 3 asphalt base 3.0 in d 200.0 ft L 24.0 ft W 67.2 tons $73.50 $4,939.20 4 asphalt surface 2.0 in d 200.0 ft L 24.0 ft W 44.8 tons $81.90 $3,669.12 6 curb CG -2 0.0 ft $8.40 $0.00 7 curb CG -6 400.0 ft $13.83 $5,531.40 8 sidewalk, asphalt 0.0 in d 200.0 ft L 4.0 ft W 0.0 tons $73.50 $0.00 9 sidewalk, concrete 5' width 400.0 ft $14.57 $5,827.50 10 ramp CG -12 2 $315.00 $630.00 11 street name sign 1 $65.00 $65.00 12 traffic control sign 1 $49.35 $49.35 13 guardrail (or rebuild wall in right -of -w 0 ES @D$3700 0.0 ft $16.80 $0.00 14 manhole or drop inlet 0 $1,365.00 $0.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $23.10 $0.00 17 pipe, rcp (15 to 48 ") 18.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $27.30 $0.00 18 pipe, rcp (15 to 48 ") 24.0 in d 0.0 ft $39.90 $0.00 19 pipe, rcp (15 to 48 ") 30.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $63.00 $0.00 20 pipe, rcp (15 to 48 ") 36.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $89.25 $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 22 E &S fabric,EC -2,3 0 ft L 4 ft W 0.0 sy $10.50 $0.00 23 clear and grub (for wooded sites) 200.0 ft L 30.0 ft W 0.1 acre $10,500.00 $1,446.28 24 grading (per cy for cut or import only; 300.0 cy fill 300.0 cy cut 300.0 cy $3.15 $1,890.00 24 CBR tests (1 every 0.1 mi. per road) 200.0 ft L 0.4 inc of 500' 1 $157.50 $220.50 2/6/2009 Stonewater Subdivision ROAD Construction Bond Estimate (roads, site work, storm sewer) Item Item No. Unit Unit Cost Cost Number installed 25 as -built drawings (1 k + price per 0.1 200.0 ft L 0.038 mi. 1 $1,050.00 $2,050.00 26 surrey and layout (price per 0.1 mi.) 200.0 ft L 0.038 mi. 1 $525.00 $1,525.00 27 mobilization 1 $525.00 $525.00 28 VDOT surety (1 lane) 200.0 ft L 0.038 mi. 0 Lanes $2,000.00 $0.00 29 VDOT maintenance fee (1 In rd, 1 yr) 200.0 ft L 0.038 mi. 0 Lanes $150.00 $0.00 30 VDOT admin. Cost recovery fee(1 Iar 200.0 ft L 0.038 mi. 0 Lanes $100.00 $250.00 cost sum $36,535.35 contigency 25% $9,133.84 Total $45,670 Stonewater Ln 0 +00 to 5 +00 road length 500.0 ft 1 aggregate base 6.0 in d 500.0 ft L 29.0 ft W 268.5 cy $35.91 $9,642.50 2 blotted or prime &double seal 500.0 ft L 29.0 ft W 1611.1 sy $6.30 $10,150.00 3 asphalt base 3.0 in d 500.0 ft L 24.0 ft W 168.0 tons $73.50 $12,348.00 4 asphalt surface 2.0 in d 500.0 ft L 24.0 ft W 112.0 tons $81.90 $9,172.80 6 curb CG -2 0.0 ft $8.40 $0.00 7 curb CG -6 1000.0 ft $13.83 $13,828.50 8 sidewalk, asphalt 0.0 in d 500.0 ft L 4.0 ft W 0.0 tons $73.50 $0.00 9 sidewalk, concrete 5' width 1000.0 ft $14.57 $14,568.75 10 ramp CG -12 4 $315.00 $1,260.00 11 street name sign 2 $65.00 $130.00 12 traffic control sign 2 $49.35 $98.70 13 guardrail (or rebuild wall in right -of -w 0 ES @D$3700 0.0 ft $16.80 $0.00 14 manhole or drop inlet 0 $1,365.00 $0.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $23.10 $0.00 17 pipe, rcp (15 to 48 ") 18.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $27.30 $0.00 18 pipe, rcp (15 to 48 ") 24.0 in d 0.0 ft $39.90 $0.00 19 pipe, rcp (15 to 48 ") 30.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $63.00 $0.00 20 pipe, rcp (15 to 48 ") 36.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $89.25 $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 22 E &S fabric,EC -2,3 0 ft L 4 ft W 0.0 sy $10.50 $0.00 23 clear and grub (for wooded sites) 500.0 ft L 30.0 ft W 0.3 acre $10,500.00 $3,615.70 24 grading (per cy for cut or import only; 600.0 cy fill 600.0 cy cut 600.0 cy $3.15 $3,780.00 24 CBR tests (1 every 0.1 mi. per road) 500.0 ft L 1 inc of 500' 2 $157.50 $315.00 25 as -built drawings (1 k + price per 0.1 500.0 ft L 0.095 mi. 1 $1,050.00 $2,050.00 26 survey and layout (price per 0.1 mi.) 500.0 ft L 0.095 mi. 1 $525.00 $1,525.00 27 mobilization 1 $525.00 $525.00 28 VDOT surety (1 lane) 500.0 ft L 0.095 mi. 0 Lanes $2,000.00 $0.00 29 VDOT maintenance fee (1 In rd, 1 yr) 500.0 ft L 0.095 mi. 0 Lanes $150.00 $0.00 30 VDOT admin. Cost recovery fee(1 Iar 500.0 ft L 0.095 mi. 0 Lanes $100.00 $250.00 cost sum $83,259.95 contigency 25% $20,814.99 Total $1 04,080 Grand Total $532,650 2/6/2009