HomeMy WebLinkAboutSUB200800106 Review Comments Easement Plat 2008-07-08Flow waiverFrom: Amy Pflaum
Sent: Tuesday, July 08, 2008 1:02 PM
To: kirsten @collins - engineering.com
Subject: RE: Flow waiver
Kirsten, we just checked over the easements. The widths are fine, however due
to the depth of the 24" pipe south of MH- EX2, the easement will need to be
shifted into the Crown property, or the pipe shifted toward Flow. Using the
diagram in the Design Manual outlining easement requirements, estimate a 5'
vertical trench from the bottom of the pipe, starting there at the outside edge
of the pipe, add 1' horizontally, then another horizontal foot for every foot of
depth to reach the finished ground elevation. I think you'll find that the
easement needs be shifted to the Crown side. -Amy
--------------------------------------------------------------------------------
From: Kirsten Munz [mailto: kirsten @collins - engineering.com]
Sent: Monday, July 07, 2008 2:02 PM
To: Amy Pflaum
Subject: RE: Flow waiver
Ok - I assume its ok that we've widened them in the direction of 78 -15E as shown
on the attached exhibit?
Also, you made a comment about the width of the strip to be dedicated along
Route 250 being inconsistent with the site plan. The plat is actually correct,
so we will correct the site plan and incorporate this into the final site plan.
Thanks!
Kirsten
From: Amy Pflaum [mailto:apflaum @albemarle.org]
Sent: Monday, July 07, 2008 1:54 PM
To: Kirsten Munz
Subject: RE: Flow waiver
No, the parcel numbers are not transposed. SUB -08 -15 is on TMP 78 -15E and SUB -
08-17 is on TMP 78 -15. I made these two comments to ensure that you knew that I
realized that the proposed drainage easement was overlapping the parcel boundary
and was not stating that the width was too small because each parcel only showed
a portion of the easement. Regardless, the comment is directed to the one
easement that overlaps the two parcels.
-Amy
--------------------------------------------------------------------------------
From: Kirsten Munz [mailto:kirsten @collins - engineering.com]
Sent: Monday, July 07, 2008 1:49 PM
To: Amy Pflaum
Subject: FW: Flow waiver
Amy,
Just double checking that your comments # 1 & 4 on the attached were intended to
be the same comment? The parcel numbers are transposed and I think that may
have been a mistake. If not, let me know. Thanks.
Kirsten
From: Amy Pflaum [mailto:apflaum @albemarle.org]
Sent: Tuesday, July 01, 2008 11:46 AM
To: Kirsten Munz
Subject: RE: Flow waiver
Kirsten, thank you for sending that. Mike asked me to check the status of the 3
Flow easements. I made comments on them on 6/11 and sent them to the project
planner. I'm terribly sorry, but I just found out that they did not get sent to
you - I thought our planner would do that. Here are the comments, they will
require some revisions. -Amy
From: Kirsten Munz [mailto:kirsten @collins - engineering.com]
Sent: Tuesday, July 01, 2008 11:30 AM
To: Amy Pflaum
Cc: Scott Collins
Subject: Flow waiver
Amy,
Attached is the parking waiver we submitted previously for Flow Auto. Please
let me know if there is anything else you need. Thanks.
Kirsten Munz, P.E., A.I.C.P.
COLLINS ENGINEERING, LLC
800 East Jefferson Street, Suite 300
Charlottesville, VA 22902
phone: (434)566 -3013
fax: (434)293 -3719
kirsten @collins - engineering.com