HomeMy WebLinkAboutSDP200800078 Review Comments Preliminary Site Plan 2008-07-25*-&A
County of Albemarle
Department of Community Development
Memorandum
To: Summer Frederick, Current Development Project Planner
From: Phil Custer, Current Development engineering review
Date: 25 July 2008
Subject: Montalto Restoration (SDP- 2008 - 00078)
The revision to the preliminary site plan for the Montalto restoration project has been reviewed.
Engineering review has no major issues with the plan as submitted and has no objection if approved. The
following comments are provided for the applicant as the project continues to the next phase:
1. The applicant will need to submit an application for a WPO plan when the final site plan is
submitted. A preliminary assessment of the SWM concept plan has been performed with the
preliminary site plan review.
(Rev. 1) A complete WPO plan review will be performed when the WPO application is
submitted with the required fee. A quick preliminary review of the ESC plan yields a few
comments which should be adjusted before the application is submitted.
-Silt fence must be installed parallel to contour lines. As currently designed, the silt
fence will be acting as a diversion in many places when installed. Please either adjust
placement of the silt fence or replace with diversion dikes and sediment traps. A
sediment trap at the base of the fill adjacent to the southern parking lot will likely be
required.
-The construction entrance should be placed at the edge of where work is taking place.
(Why are the limits of construction so wide ?)
- Please show tree protection fencing to the standard in VESCH. Currently, site
improvements are shown within the fencing. Are there any trees required to be
protected through the rezoning process?
-The three parking spaces to the east appear to need protection measures during their
construction.
2. Engineering review realizes that the impervious area around the existing house and barn
structures in the post - development condition is nearly equal to the pre - development condition and
will not require SWM quality treatment in this area. SWM treatment and detention will be
required for the parking lots to the south of the site where new impervious area is added over
grass. Please provide treatment measures in this area that meet or exceed the required removal rate
computed using the county's modified simple spreadsheet. Please contact me if you need a copy
of this spreadsheet.
(Rev. 1) The conceptual BMP adjacent to the southern parking lot is acceptable to engineering
review as shown in this plan. At this time, we are not convinced that it is not required. When
the WPO plan is submitted, please provide a diagram showing the impervious areas of the pre
and post development conditions if the applicant still wishes to contend that total impervious
area is reduced.
Please note that there is a discrepancy between sheets C1.4 and C2.1 regarding the cisterns in
the basement of the main house. This does not affect engineering review.
3. Please note on the plan the date of the topographic and utility survey. The survey does not
Current Development
Engineering Review Comments
Page 2 of 3
appear to accurately show the existing entrance onto Route 53. A blowup of this entrance should
be provided in the plan showing adequate sight distance.
(Rev. 1) The date of the topographic and utility survey has not been added to the plan. This
must be shown on the final site plan.
4. The plan has been designed to parameters less stringent than the standards listed in the County
ordinance. It is unclear what design standards were waived during the rezoning process and what
were left to be waived administratively. The waivers needed are:
a. [18- 4.12.15.a] Surface materials.
b. [18- 4.12.15.c] Maximum grade in parking lot.
c. [18- 4.12.15.g] Curb and gutter.
d. [18- 4.12.16.c.1] Minimum parking space size and aisle widths.
e. [18- 4.12.16.e] Bumper blocks.
f. [18- 4.12.17.a] Maximum grade for a travelway.
g. [18- 4.12.17.c.I] Travelway width.
An engineering analysis of the pending waivers is as follows:
a. [18- 4.12.15.a] Details for each modification from standard asphalt paving should be
included before a waiver is granted. Details were not included in this set.
b. [18- 4.12.15.c] It appears that the 5% maximum grade can easily be achieved in most
locations.
c. [18- 4.12.15.g] Stormwater runoff is always more efficiently transferred with curbing.
d. [18- 4.12.16.c.1] Room is available for the expansion of the travelway in the southwest
parking lot to the standard in the County Code.
e. [18- 4.12.16.e] Bumper blocks should be provided in parking spaces adjacent to
sidewalk that is narrower than 6ft.
f. [18- 4.12.17.a] All travelways that exceed the maximum grade requirement are existing
travelways on the "farm road ". All existing travelways appear to have grades
shallower than the maximum allowable slope that can be traversed by emergency
access vehicles. Though, this cannot be confirmed until a survey of the entry road is
provided in this set. Engineering review recommends approval of this waiver if some
additional safety barricades are proposed and topographical information on the entry
road is given in the set.
g. [18- 4.12.17.c.1] Travelway widths are difficult to confirm for the farm road from
Route 53 because it is not shown in this plan. All two -way traffic is recommended by
engineering review to be at least 20ft in width.
(Rev. 1) The results of the waiver requests are as follows:
a. The use of alternative pavement in parking and travelways is allowed. Please
include these section details on the final site plan.
b. All parking areas are under the 5% maximum. A waiver is not needed. Though,
the complete grading for the parking lot areas should be shown for the eastern
three space area and the southern 9 space lot on final site plan.
c. The curb and gutter waiver has been granted by the Zoning Department.
d. A waiver has been granted by the Zoning Department for the minimum parking
space size and aisle widths on the condition that the parking adjacent to the bus
parking area is realigned so that it is at a 60 degrees to the travelway. Please refer
to section 18- 4.12.16.c and the design manual for the required dimensions.
e. The county engineer has granted the waiver for bumper blocks. I recommend
Current Development
Engineering Review Comments
Page 3 of 3
placing a bumper block in the spaces in the courtyard of the main house to prevent
drivers from dropping the nose of the car over the wall.
f. The county engineer has granted a waiver for the maximum grade of the travelway.
The county should be provided with a letter from Fire and Rescue stating that the
entrance drive meets their minimum requirements before final approval is granted.
g. A travelway width waiver has been given by the Zoning Department.
File: E2_psp_PBC_sdp200800078