Project:
Luxor Commercial Center [SDP200800004]
Plan preparer:
Justin Shimp, DDR [email: jshimp@ddrva.co
or rep.:
Luxor, LLC
Plan received date:
14 Jan 2008
07 April 2008 (Revl)
28 April 2008 (Road Plans)
15 May 2008 (ESC Plans)
12 June 2008 (Rev2 Final Site Plan)
15 July 2008 (Rev3)
27 August 2008 (Rev4 Final Site and Road Plan)
Date of comments:
22 Feb 2008
15 April 2008 (Revl)
18 June 2008 (Rev2 FSP, ESC, Road Plans)
04 Aug 2008 (Rev3)
13 October 2008 (Rev4 Final Site and Road Plan)
Reviewer:
Jonathan Sharp (Revl)
Phil Custer (Rev4)
After the fourth review of the plan, the remaining comments are listed below from Jon Sharp's August 4t'
letter. The fifth submittal by the applicant contained just the road and site plan.
A. Final Site Plan
3. Please provide all necessary offsite easements for parcels 78 -12, 1213, and 55D.
Rev]: It appears construction easements are needed from 78 -12B. Easement plats should be
approved and deeded prior to final site plan approval.
Rev2: Grading easements are required. Use of the adjacent pond for ESC and SWM requires
easements. The second interconnection to Eckerd should be shown on the plans. Access
easements should be provided to Aunt Sarah's at the entrance locations provided.
Rev3: All necessary offsite easements are required prior to final site plan approval. Any
pending on site easement plats must be approved prior to final site plan approval.
Rev4: Approval of all of the offsite easements listed above is still required.
13. VDOT approval is required.
Rev1: comments not addressed.
Rev2: comments not addressed.
Rev3: We are currently sending a copy of the plans to VDOT for review.
Rev4: Comment has not been addressed.
B. Road Plans
.ital curve and vertical curve design of the roadway should meet VDOT requirements.
Rev3: Design speed for proposed roadways are based on ADT values. With an ADT of 1000
vehicles, the minimum design speed is 25mph. See requirements in VDOT Road Design
Manual Appendices B and C.
Rev4: Comment has been addressed.
Albemarle County Community Development
Engineering Review Comments
Page 2 of 2
34. A road bond will be computed by the County once the plans have been approved. The bond
must be posted prior to the approval of the pending subdivision plat. A schedule of
completion and bond estimate request must be provided once the plans have been approved.
Rev3: A road bond will be required for the pending subdivision plat if the proposed Luxor
Road is providing adequate frontage for any of the proposed subdivision parcels. If Luxor
Rd is not required for access /frontage, no road bond is required.
Rev4: No road bond appears to be required.
C. Erosion and Sediment Control Plan
40. An ESC bond will be computed by the County once the plans have been approved.
Rev3: An ESC bond will be computed by the County once the plans have been approved.