County of Albemarle
Department of Community Development
Memorandum
To: Elizabeth Marotta, Current Development Project Planner
From: Phil Custer, Current Development engineering review
Date: 30 September 2008
Subject: Airport Road Office Plaza (SDP- 2008 - 00136)
The preliminary site plan for Airport Road Office Plaza has been reviewed. The engineering review for
current development cannot recommend approval to the plan at this time. The following comments are
provided.
1. Please provide a benchmark on the plan.
2. The retaining wall along the western property line should be moved farther from the
undisturbed buffer. It is unlikely that construction of the wall in the location shown will not
disturb the buffer. Between the wall and the buffer, the applicant should also provide for drainage
from offsite so water does not flow into wall and create long term erosion issues. The applicant
should also provide for a 20ft screening area between the wall and the sanitary sewer easement.
[18-32.7.91
The conceptual stormwater management plan is insufficient.
a) The applicant has not provided an analysis of the proposed stormwater management
facilities compared to the required removal rate of the site. The next submittal should
include a modified simple removal rate spreadsheet and a map of the drainage areas to
each facility. Each facility must meet or exceed the required removal rate.
b) A water quality swale will likely not meet the required removal rate for the site (see
above). Additionally, as designed, it appears the facility would not be able to hold the
required WQv.
c) A large portion of the site does not appear to pass through a water quality treatment
facility. In the applicants' critical slope waiver request and on the cover sheet, filterras
were mentioned as a method of treatment but none were shown on the plan. Please show
the location of proposed filterras and modify grading so that all parking lot runoff has the
opportunity to pass through these facilities. Facilities must capture as much runoff from
the site as possible.
4. A critical slope waiver from the Planning Commission must be approved. The applicant has
submitted a request. The engineering review of the critical slope disturbance will be given in a
separate letter.
5. Please show the existing entrance across Timberwood Blvd. The centerline of the office plaza
entrance should be aligned with the existing entrance of the Baptist Church. [18- 32.7.2]
6. Please provide safe and convenient pedestrian access from the spaces in the southern lot to the
building. [18- 32.7.2]
7. Are there existing sidewalks along Timberwood Blvd. and Airport Road? If so, please label
Current Development
Engineering Review Comments
Page 2 of 2
them on the plan. If not, please provide new sidewalks along the VDOT ROW.
The following comments are final site plan comments provided to the applicant as a courtesy.
1. An analysis of the downstream channel will be required before approval of the WPO plan can
be given. Depending on the condition of the downstream channel, additional detention may
be required per state law.
2. The maximum slope allowed in parking lots is 5 %.
3. Retaining walls adjacent to parking and travelways will require a VDOT guardrail.
4. The plantings in the biofilters do not appear to meet the requirements listed in the design
manual.