BOND ESTIMATE - EROSION CONTROL PROJECT NAME: PROJECT NUMBER: DATE OF ESTIMATE ESTIMATE BY: BASED ON: Airport Electrical Vault W PO20080053 11/14/08 PBC Plan dated 11/12/08 WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 3 1500 4500 SILT FENCE LF 200 5 1000 SAFETY FENCE LF 0 3 0 TEMPORARY FILL DIVERSION LF 0 3 0 DIVERSION DIKE LF 650 3 1950 TEMPORARY SLOPE DRAIN LF 0 20 0 SEDIMENT TRAP 1 ACRES 1.2 1000 1200 CULVERT INLET PROTECTION EA 1 500 500 OUTLET PROTECTION EA 2 200 400 EC -2 & 3 DITCH PROTECTION LF 130 10 1300 RIP -RAP LF 70 55 3850 CHECK DAMS SQ.YD. 4 30 120 PAVED CONSTRUCTION ENTRANCE EA 1 2000 2000 SUBTOTAL 16820.00 CONTINGENCY & ADMINISTRATION LS 25% 4205.00 TOTAL 21025.00 BOND AMOUNT REQUIRED 21000 last revised:12 -5 -01