Subject: Engineering Review of Airport Electrical Vault (WPO- 2008 - 00053; SDP - 2008 - 00080)
Goodmorning,
The Erosion & Sediment Control and Stormwater Management Plans (WPO- 2008 - 00053) submitted 12
November 2008 have been received by Engineering Review. Approval of the plans has been granted with the
condition that the standard County notes for ESC and SWM plans be added to sheet 7A (Sheet 13 did not
include the lists) and the biofilter mix be specified as "State approved mix" rather than "Luckstone Biofilter
mix ". Once these revisions have been made, please submit 7 sets (sheets 1, 3, 4, 6, 7, 7A, 22, and 22A) of the
WPO plan to Current Development Engineering.
The E &SC bond amount is $21,000. The SWM bond amount is $7,000. The forms and
instructions to post the Water Protection Ordinance Bond can be found on the Community Development
Department Web site on www.albemarle.org.
A completed copy of the Standard Stormwater Maintenance Agreement and fee for recordation for the stormwater
facilities is required prior to final approvaQ 17 -304E] The forms and instructions can be found on the Community
Development Department Web site on www.albemarle.org.
You may contact Pam Shifflett (Albemarle County Department of Community Development) at ext. 3246
for further information on bonding procedures and Maintenance Agreements.
Once the E &SC bond and the SWM bond have been posted, the SWM maintenance agreement recorded, and the
site plan approved, you may contact the Department of Community Development to arrange a pre- construction
meeting with a County Erosion & Sediment Control Inspector.
In addition, engineering review recommends approval to the minor site plan amendment (SDP- 2008 - 00080).
Please contact Bill Fritz of Current Development at ext. 3242 regarding approval of the Site Plan. The sheets
needed for the site plan approval will likely differ from the sheets needed for the WPO set.
Please let me know if you have any questions.