Loading...
HomeMy WebLinkAboutSDP200800123 Review Comments Final Site Plan and Comps. 2008-11-25COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 November 25, 2008 Atwood Architects c/o Ashley Cooper 250 West Main Street Charlottesville, VA 22902 Fax (434) 972 -4126 RE: ARB2008 -00074 Crozet Station Phase I — Final; Tax Map 56A2, Section 1, Parcel 29 Dear Ms. Cooper, I have reviewed your recent submittal for the above - referenced project, which included site plan sheets T1, C1.0 -1.3, C2.0 -2.1, and 1-1.0 -1.3 dated 10/31/08; architectural sheets Al dated 2/16/08, A2 dated 7/25/08, A3- 6 and A8 dated 10/16/08, and A7 dated 7/7/08 and 7/25/08. 1 have the following comments. 1. Comment #4 from our 10/9/08 letter stated, "Replace the White Pines with an alternate appropriately spaced evergreen." This change has not been made but is still required. 2. Comment #5 in our 10/9/08 letter stated: "Include the color of the shoebox fixtures in the schedule." This change has not been made. Note that even if the default color is bronze, the fixture /pole color should be included in the schedule. 3. Comment #5 in our 10/9/08 letter stated: "Coordinate the lighting plan with the elevations." This change has not been made. Note that the photometric plan and the luminaire schedule show 19 wall lights and the elevation sheet shows 22 wall lights. The locations on the architectural elevations are coordinated with the architecture of the building, but they are not on the site plan. Coordinated drawings are required. 4. Comment #8 in our 10/9/08 letter stated, "Add the following note to the site plan: `All chain link fencing shall be removed and replaced with approved fencing by final zoning. "' A similar note has been added to sheet C1.0, but the wording and arrow used refer only to the chain link along the frontage of the site. The purpose of adding the note was to ensure that all chain link will be removed from the site. Consequently, the plan must be revised to include the note as originally required. Ensure that the note applies to all chain link on the site. Please provide: 1. One full set of revised drawings addressing each of these conditions. Include updated ARB revision dates on each drawing and an ARB approval signature panel. 2. A memo including detailed responses indicating how each condition has been satisfied. If changes other than those requested have been made, identify those changes in the memo also. Highlighting the changes in the drawing with "clouding" or by other means will facilitate review and approval. 3. The attached "Revised Application Submittal" form. This form must be returned with your revisions to ensure proper tracking and distribution. When staff's review of this information indicates that all conditions of approval have been met, a Certificate of Appropriateness may be issued. If you have any questions, please do not hesitate to contact me. Sincerely, Margaret Maliszewski Principal Planner Cc: Crozet Shopping Center LLC P O Box 129 Crozet Va 22932 File COUNTY OF ALBEMARLE Department of Community Development REVISED APPLICATION SUBMITTAL This form must be returned with your revisions to ensure proper tracking and distribution. County staff has indicated below what they think will be required as a resubmission of revisions. If you need to submit additional information please explain on this form for the benefit of the intake staff. All plans must be collated and folded to fit into legal size files, in order to be accepted for submittal. TO: Margaret Maliszewski DATE: PROJECT NAME: ARB2008 -00074 Crozet Station Phase I - Final Submittal Type Requiring Revisions ( ) indicates submittal Code County Project Number # Copies Erosion & Sediment Control Plan (E &S) # Copies Distribute To: Mitigation Plan (MP) 1 Margaret Maliszewski Waiver Request (WR) Stormwater Management Plan (SWMP) Road Plan (RP) Private Road Request, with private/ public comparison (PRR) Private Road Request — Development Area (PRR -DA) Preliminary Site Plan (PSP) Final Site Plan (or amendment) (FSP) Final Plat (FP) Preliminary Plat (PP) Easement Plat (EP) Boundary Adjustment Plat (BAP) Rezoning Plan (REZ) Special Use Permit Concept Plan (SP -CP) Reduced Concept Plan (R -CP) Proffers (P) Bond Estimate Request (BER) Draft Groundwater Management Plan (D -GWMP) Final Groundwater Management Plan (F -GWMP) Aquifer Testing Work Plan (ATWP) Groundwater Assessment Report (GWAR) Architectural Review Board (ARB) ARB2008 -74 Other: Please explain (For staff use only) Submittal Code # Copies Distribute To: Submittal Code # Copies Distribute To: ARB 1 Margaret Maliszewski