The revision to the preliminary site plan amendment for Hollymead Towncenter Area C -9 has been
reviewed. The engineering review for current development recommends approval of this preliminary site
plan.
Temporary easements will be necessary in order to construct this project. Please provide
letters of consent from adjacent property owners giving permission for temporary construction
on their parcels.
(Rev. I) Comment has been addressed.
2. The parking lot should have no grades greater than 5 %.
(Rev. I) Comment has been addressed.
3. A loading space appears to be needed in the new parking area.
(Rev. I) Comment has been withdrawn.
The following final site plan comments have been provided as a courtesy to the applicant and will not need
to be addressed to receive preliminary approval.
1. An analysis of the downstream stormwater conveyance system will be required during the final site
plan per MS -19.
2. In order for the SWM plan to be approved, an analysis of the existing pond will be required to
confirm that the pond will meet the quality and quantity requirements for the project.
File: E2_pmj_PBC_sdp200800146.doc
Memorandum
To:
Gerald Gatobu, Current Development Project Planner
From:
Phil Custer, Current Development engineering review
Date:
1 December 2008
Subject:
Hollymead Towncenter Area C -9 (SDP- 2008 - 00146)
The revision to the preliminary site plan amendment for Hollymead Towncenter Area C -9 has been
reviewed. The engineering review for current development recommends approval of this preliminary site
plan.
Temporary easements will be necessary in order to construct this project. Please provide
letters of consent from adjacent property owners giving permission for temporary construction
on their parcels.
(Rev. I) Comment has been addressed.
2. The parking lot should have no grades greater than 5 %.
(Rev. I) Comment has been addressed.
3. A loading space appears to be needed in the new parking area.
(Rev. I) Comment has been withdrawn.
The following final site plan comments have been provided as a courtesy to the applicant and will not need
to be addressed to receive preliminary approval.
1. An analysis of the downstream stormwater conveyance system will be required during the final site
plan per MS -19.
2. In order for the SWM plan to be approved, an analysis of the existing pond will be required to
confirm that the pond will meet the quality and quantity requirements for the project.