HomeMy WebLinkAboutSDP200800135 Review Comments Major Amendment, Preliminary Plan 2009-02-04SDP200800135 BB &T Major Site Plan Amendment
Megan Yaniglos
From: Gary Whelan [gwhelan @serviceauthority.org]
Sent: Monday, February 02, 2009 11:57 AM
To: Megan Yaniglos
Subject: SDP200800135 BB &T Major Site Plan Amendment
Follow Up Flag: Follow up
Flag Status: Red
Megan,
Page 1 of 1
No plans are required for ACSA review and approval. Backflow prevention is required and projected waste water
flows will be needed to ensure that the pump station has adequate capacity. Other than these comments, the
ACSA takes no exception to the BB &T plan.
Gary
2/12/2009