HomeMy WebLinkAboutWPO200600050 Review Comments Stormwater Management Plan 2008-08-06Northtown Center - Phase 1From: Amy Pflaum
Sent: Wednesday, August 06, 2008 9:05 AM
To: 'Todd Philipp'
Subject: RE: Northtown Center - Phase 1
Todd,
This is the final comment on the Northtown Center WPO Application
(WPO200600050):
These plans are finished and ready for approval when the Army Corps and DEQ
permits are received.
Amy D. Pflaum
Senior Civil Engineer
Albemarle County Department of Community Development
(434) 296 -5832 x3069
apflaum @albemarle.org
From: Todd Philipp [mailto:tphilipp @ddrva.com]
Sent: Wednesday, August 06, 2008 8:54 AM
To: Amy Pflaum
Subject: RE: Northtown Center - Phase 1
Hi Amy,
Any word on the approval of this plan?
Thanks,
Todd Philipp, P.E.
Senior Project Manager
Dominion Development Resources, LLC
172 South Pantops Drive
Charlottesville, VA 22911
T: 434.979.8121
F: 434.979.1681
--------------------------------------------------------------------------------
From: Amy Pflaum [mailto:apflaum @albemarle.org]
Sent: Wednesday, July 30, 2008 4:50 PM
To: Todd Philipp
Subject: RE: Northtown Center - Phase 1
2 sets please.
--------------------------------------------------------------------------------
From: Todd Philipp [mailto:tphilipp @ddrva.com]
Sent: Wednesday, July 30, 2008 2:44 PM
To: Amy Pflaum
Subject: RE: Northtown Center - Phase 1
Thanks Amy,
How many sets should we bring down?
Todd Philipp, P.E.
Senior Project Manager
Dominion Development Resources, LLC
172 South Pantops Drive
Charlottesville, VA 22911
T: 434.979.8121
F: 434.979.1681
From: Amy Pflaum [mailto:apflaum @albemarle.org]
Sent: Wednesday, July 30, 2008 1:42 PM
To: Todd Philipp; Glenn Brooks
Cc: Pat Enright
Subject: RE: Northtown Center - Phase 1
Todd, in an attempt to focus our effort on plan review and work through all
plans in the queue, the engineering team is not taking meetings this week. If
you submit the Northtown plans today the idea is that they will be reviewed (and
hopefully approved) by Friday. Please submit the plans with Jon's comment
letter and your responses. You will hear from us on Friday or Monday regarding
their status.
-Amy
--------------------------------------------------------------------------------
From: Todd Philipp [mailto:tphilipp @ddrva.com]
Sent: Wednesday, July 30, 2008 11:36 AM
To: Amy Pflaum; Glenn Brooks
Cc: 'Pat Enright'
Subject: Northtown Center - Phase 1
Glenn, Amy,
Jon Sharp had two remaining comments on the plans for this project, one on the
SWM and one on the E &S plan. We just needed to add a detail to the site plan to
address the SWM comment. The E &S comment is addressed by inserting County -
supplied design sheets into the plan. Understanding that Jon is not available
to look at these when I bring them in, can I bring the plans in and meet with
one of you to demonstrate that the two comments have been addressed and get the
plans approved? This shouldn't take long and we can get this project off both
of our plates.
Thanks,
Todd Philipp, P.E.
Senior Project Manager
Dominion Development Resources, LLC
172 South Pantops Drive
Charlottesville, VA 22911
T: 434.979.8121
F: 434.979.1681