HomeMy WebLinkAboutWPO200800069 Review Comments Bond Estimate 2009-03-05BOND ESTIMATE - EROSION CONTROL Spreadsheet last revised:12 -5 -01 PROJECT NAME: Moores Creek Sewer and Water Extension, Phase 2 PROJECT NUMBER: WPO200800069 DATE OF ESTIMATE: 03/04/09 ESTIMATE BY: MRG BASED ON: Approved plan WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 5 1500 7500 SILT FENCE LF 2600 5 13000 SAFETY FENCE LF 0 3 0 TEMPORARY FILL DIVERSION LF 0 3 0 DIVERSION DIKE LF 150 3 450 TEMPORARY SLOPE DRAIN LF 0 20 0 SEDIMENT TRAP 1 ACRES 0 1000 0 SEDIMENT BASIN 1 ACRES 0 1000 0 Utility Stream Crossing EA 2 1000 2000 CULVERT INLET PROTECTION EA 0 500 0 INLET PROTECTION EA 0 200 0 OUTLET PROTECTION EA 0 200 0 EC -2 & 3 DITCH PROTECTION LF 0 10 0 RIP -RAP LF 250 55 13750 CHECK DAMS SQ.YD. 10 30 300 PAVED CONSTRUCTION ENTRANCE EA 2 2000 4000 SUBTOTAL 41000.00 CONTINGENCY & ADMINISTRATION LS 25% 10250.00 TOTAL 51250.00 BOND AMOUNT REQUIRED 51300.00