HomeMy WebLinkAboutWPO200800037 Review Comments Stormwater Management Plan 2009-04-22Short Review Comments Report for: WPO201800079 SubApplication Type: Old Trail Drive Entry Feature ESC & SWM - VSMP Stormwater Management/BMP Plan Easement Plat Date Completed:11/06/2018 Reviewer:Emily Cox CDD Engineering Review Status:Requested Changes Reviews Comments: Division: Date Completed:11/14/2018 Reviewer:Margaret Maliszewski CDD ARB Review Status:Requested Changes Reviews Comments:Revise the plan to show existing wooded areas to remain. Division: Date Completed:01/15/2019 Reviewer:Emily Cox CDD Engineering Review Status:Requested Changes Reviews Comments: Division: Date Completed:01/04/2019 Reviewer:Margaret Maliszewski CDD ARB Review Status:Approved Reviews Comments: Division: Date Completed:01/18/2019 Reviewer:Emily Cox CDD Engineering Review Status:See Recommendations Reviews Comments:-submit 4 copies for final review and approval. Division: Date Completed:01/25/2019 Reviewer:Emily Cox CDD Engineering Review Status:Approved Reviews Comments: Division: Page:1 of 1 County of Albemarle Printed On:January 29, 2019 ALg�,�� �'IRGINZ� COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project: SDP200800061 & WP0200800037, Earlysville Business Park Plan preparer: Mr. Alan Franklin; Terra Concepts afranklin @terraconceptspc.com Owner or rep.: BBX Corporation Date received: 16 March 2009 REV]: 7 April 2009 Date of Comment: 22 April 2009 Engineer: Amy Pflaum - Current Development Engineering The final site plan and water protection ordinance application for the Earlysville Business Park, received by Current Development Engineering on April 7, 2009, has been reviewed. Current Development Engineering has the following comments: General Site Plan Comments Please specify on the plans that all slopes 3:1 or steeper will be planted with low maintenance ground cover, not grass. REV 1: Comment has been addressed. Road Plan Comments VDOT approval of Driller's Lane is required. REV 1: Comment has been noted. Per VDOT Standards of Entrances to State Highways, the curb return radius of a commercial entrance must be a minimum of 12.5 feet. The eastern entrance to the new parking lot is designed with a radius of only 5 feet. REV 1: Comment has been addressed. 4. The elevation of the intersection of Driller's Lane and Contractor's Lane contradict on the two profiles. REV 1: Comment has been addressed. 5. Steep grades between the proposed street intersection and the new parking lot do not provide for the 1 ":1' required shoulder shown in the street section, please revise grading. REV 1: Comment has not been addressed. Proposed steep slopes just behind back of curb (between roads and new parking lot) do not allow for 4-foot shoulder shown in street section detail. 6. Right -of -way dedication is required for the public and private streets. REV 1: Comment has been noted. 7. Please provide a stub -out for access to TMP 31-21B at the intersection of Driller' s Lane and Contractor's Lane. REV 1: Comment has been addressed. Drainage Comments 8. Please provide the sizing computations for the outlet protection at the end of pipes A, C, and D. REV 1: Comment has been addressed. Stormwater Management Comments 9. A full review of the stormwater management plans will be performed once a Water Protection Ordinance Application has been submitted. REV 1: Comment has been noted. 10. An analysis of the receiving channel on TMP 31 -21D and stream may be required to determine if the requirements of MS -19 are being satisfied. REV 1: Comment has been noted. 11. Project area (8.1 acres) does not match disturbed acreage (9.22 acres) in the Detention and Water Quality Compliance tables. 12. The pre- and post - development peak flow numbers in the Detention Compliance table do not match the pre- and post - development watershed calculations. 13. There is no number filled in for the Routed Peak Flow in the Detention Compliance table. 14. A site visit revealed that the proposed pond will release into a natural drainage swale that would not be considered an adequate receiving channel. It is recommended that the pond be designed to detain to a release rate that is less than the pre - developed peak flow. Erosion & Sediment Control Comments 15. A full review of the Erosion & Sediment Control plans will be performed once a Water Protection Ordinance Application has been submitted. REV 1: Comment has been noted. 16. Grading on E &S Plan (Sheet 15) does not match grading on Grading Plan (Sheet 5). 17. The proposed stub -out to TMP 31 -21B is not shown on the E &S Plan. 18. Please show the location of the top soil stockpile. 19. Please show the sediment basin drainage area limits. 20. Directing all disturbed areas to the sediment basin with diversion dikes is preferred to protecting large areas with silt fence. Once these comments have been addressed, please submit 2 copies of the revised plans, calculations, and narratives to Current Development Engineering. Current Development Engineering is available from 2:30 -4 PM on Thursdays to discuss these review comments. Please contact Amy Pflaum at 434 - 296 -5832 ext. 3069 or email adpflaum @albemarle.org to schedule an appointment. \ \Cob- dts01 \cityviewlnk\Docs \2008 \SDP \SDP200800061 Earlysville Buisness Park - Final \CDE2_fsp_ADP_08 -00061 Earlysville Business.doc