Philip Custer
From: Philip Custer
Sent: Monday, March 30, 2009 5:41 PM
To: 'Ankita Kot'; 'Ankita Kot'
Cc: Bill Fritz
Subject: Engineering Review of the Crown Automotive Site Plan (SDP- 2008 - 00144)
Good evening,
Engineering review for Current Development has completed their review of the latest site plan submittal for the
Crown Automotive Retail, Parts, and Service Building (SDP- 2008 - 00144). All outstanding comments have been
addressed and engineering review has no objection to the approval of the site plan once the receipt of plat
recordation for application SUB - 2008 -00286 is received.
The ESC and SWM plan had previously been approved. A grading permit can be issued for this project once:
-the final site plan is signed by all reviewing agencies
-the applicant delivers 4 full copies of the latest plan and 1 copy of the SWM set (sheets C1, C10, C17, C19, and
C21 -C30) to engineering review
-a SWM facility maintenance agreement and fee are recorded for parcel 78 -15.
-the WPO bond is posted (The forms and instructions to post the Water Protection Ordinance Bond can be found
on the Community Development Department Web site on www.albemarle.org. You may contact Pam Shifflett
(Albemarle County Department of Community Development) at ext. 3246 for further information on bonding
procedures.); and
-a preconstruction meeting is held between the contractor and county inspector
Please direct all questions regarding the site plan process to Bill Fritz. For any questions regarding the approval
of the WPO, please feel free to contact me.
Thanks,
Phil