HomeMy WebLinkAboutSDP200900048 Review Comments Final Site Plan and Comps. 2009-06-30*-&A County of Albemarle Department of Community Development Memorandum To: Elizabeth Marotta, Current Development Project Planner From: Phil Custer, Current Development engineering review Date: 30 June 2009 Subject: Stonewater Townhomes Final Site Plan (SDP- 2009 - 00048) The final site plan for the Stonewater Townhomes has been reviewed. The engineering review for current development can recommend approval to the plan after the following comments are addressed: 1. The road plan that was submitted with the subdivision plats has been approved. (SUB - 2007- 00077) 2. The ESC and SWM plans that were submitted with the subdivision have been approved; however offsite easements are pending recordation. (WPO- 2007 - 00045) The approved plans cover this site for both erosion and sediment control and stormwater management. If this site plan is constructed well after the roads are in and all disturbed areas stabilized, an additional ESC plan for the townhome area may be required by the ESC inspector. 3. The public Right -of -Way lines should match the recently submitted final plat and road plans. The sidewalk along Rio Road should be lft within the public ROW. 4. The sidewalk behind the townhomes should be within an easement allowing for access to and from the Stonehenge and Treesdale properties. 5. Any modification to access easements, lot lines, and drainage easements should be reflected in the final plat and road plans. 6. All driveways must have at least 18ft of pavement from the edge of the sidewalk. The sidewalk cannot be obstructed by a parked vehicle. 7. The specs provided for the low- maintenance groundcover appear to be only temporary measures. Please see table 3.37C of the VESCH for examples of acceptable groundcovers. 8. Please remove all road plan sheets from this set. All roads were reviewed and approved under application SUB - 2007 - 00077. File: E1_fsp_PBC_sdp200800129