HomeMy WebLinkAboutSDP200800118 Review Comments Final Site Plan and Comps. 2009-08-11SDP - 2008 -00118 Emanuel Episcopal Church
Megan Yaniglos
From: DeNunzio, Joel D., P.E. [ Joel .DeNunzio @VDOT.virginia.gov]
Sent: Tuesday, August 11, 2009 10:02 AM
To: Megan Yaniglos
Cc: Amy Pflaum
Subject: SDP - 2008 -00118 Emanuel Episcopal Church
SDP - 2008 -00118 Emanuel Episcopal Church
Megan,
Page 1 of 2
VDOT's previous comments for the above site plan have been properly addressed. A Land Use Permit will be
required for work within the Route 250 right of way.
Thanks
Joel
Joel DeNunzio, P.E.
Staff Engineer
434 - 293 -0011 Ext. 120
ioeL den unzio(�bvdot.viroinia.00v
From: DeNunzio, Joel D., P.E.
Sent: Thursday, June 18, 2009 8:16 AM
To: 'Elizabeth Marotta'
Cc: 'Amy Pflaum'
Subject: SDP - 2008 -00118 Emanuel Episcopal Church
SDP - 2008 -00118 Emanuel Episcopal Church
Elizabeth,
I have reviewed the above site plan and have the following comments:
1. Please include a typical section for the turn lane on Route 250.
2. Commercial entrances should be labeled as CG -11. Please include the CG -11 detail and show the
entrance profile for the proposed entrances. Curb and gutter does not need to be provided as shown in the CG-
11 detail but the grade changes for the entrance needs to be in accordance with the detail.
If you have any questions or comments, please let me know.
Thanks
Joel
8/11/2009
SDP - 2008 -00118 Emanuel Episcopal Church
Joel DeNunzio, P.E.
Staff Engineer
434 - 293 -0011 Ext. 120
ioel.denunzio(c vdot.virainia.aov
8/11/2009
Page 2 of 2