Project: SDP - 2009 - 00078, City of Charlottesville CTS Operations Center
Plan preparer: Mr. Justin Walton, VMDO Architects
Owner or rep.: Mr. Scott Hendrix; City of Charlottesville
Date received: 14 September 2009
Date of Comment: 5 October 2009
Engineer: Phil Custer
The major site plan amendment for the City of Charlottesville CTS Operations Center, received on 14
September 2009, has been reviewed. The engineering review for current development can recommend
approval to the plan after the following comments have been addressed.
The storm sewer line from structure 4 -1 to 4 -4 must be included in the phase A.
2. The underground cistern must be included in phase A.
3. If the biofilter south of Building A is to be included in Phase A, please include the storm
sewer from structures 2 -1 to 4 -4 in Phase A as well. From the perspective of engineering
review, I do not see any need for this biofilter to be included in Phase A. To simplify the
phasing, I recommend that the phase line be moved closer to building A.
4. Please remove all ESC and Stormwater management sheets from this set. The addition of
phase lines for Zoning purposes will not affect the WPO plans. If substantial deviations from
either the Stormwater or Erosion Control Plans are required at this time, please submit a
separate WPO application and appropriate fees for amendments to those plans. The changes
to the plan as currently listed (modifications to utility lines and the addition of zoning phase
lines) will not require a WPO plan amendment.
File: El_fmj_PBC_SDP200900078_CTS construction revisions.doc