HomeMy WebLinkAboutSDP200900097 Review Comments Final Site Plan and Comps. 2009-12-28pF AL13��r
County of Albemarle
Department of Community Development
To: Scott Collins; Collins Engineering via email: scotta- )- collins- engineering.com
CC: Todd Dofflemeyer; Cathcart Properties via email: todd @cathcartproperties.com
From: Summer Frederick, Senior Planner
Division: Current Development
Date: December 28, 2009
Subject: SDP2009 -97 The Reserve at Belvedere — Final prior to preliminary
The Planner for the Current Development Division of the Albemarle County Department Community
Development will recommend approve the plan referred to above when the following items have been
satisfactorily addressed. (The following comments are those that have been identified at this time.
Additional comments or conditions may be added or eliminated based on further review.) [Each
comment is preceded by the applicable reference to the Albemarle County Code.]
1. [Sec. 18- 32.5.6(x)] Please provide name of developer.
2. [Sec. 18- 32.5.6(a)] All relevant rezoning, proffer, and variance information must be specifically
listed on cover sheet.
3. [Sec. 18- 32.5.6(x)] Datum reference for elevation seems to be inaccurate.
4. [Sec. 18- 32.5.6(a)] All information regarding owner, zoning, tax map and parcel number and
present use of all adjacent parcels must be included on plan.
5. [Sec. 18- 32.5.6(b)] Maximum height of all buildings must be specified on plan.
6. [Sec. 18- 32.5.6(c)] If phasing of plan is anticipated, phase lines and proposed timing of
development must be indicated on plan.
7. [Sec. 18- 32.5.6(m)] Distance to centerline of the nearest existing street intersection must be
shown on plan.
8. [Sec. 18- 32.5.6(p), 18- 32.6.6(i), 18- 32.7.9] Not all labels /lines point to graphics. Please correct.
9. [Sec. 18- 32.5.6(p), 18- 32.6.6(i), 18- 32.7.9] Graphic depictions of plants do not match numbers
listed in planting schedule. Please correct.
10. [Sec. 18- 32.5.6(p), 18- 32.6.6(i), 18- 32.7.9] Landscape plan needs to be shown at a larger scale
in order to ensure accurate review is possible.
11. [Sec. 18- 32.5.6(p), 18- 32.6.6(i), 18- 32.7.9] Owner's signature is required on conservation
checklist.
12. [ZMA2004 -007, Proffer 6.1] A final report for the archeological survey done on the Belvedere
project site is due January 1, 2010. Failure to meet this proffer deadline will result in all
approvals being withheld for projects on parcels included in the rezoning.
13. A complete critical slopes waiver application must be submitted.
14. Approval of all applicable variations must be granted by the Director of Planning. It is
understood that neither the appropriate variation application, nor the requested accurately
revised Code of Development, have been submitted to Long Range Planning. It is also
understood that the letter presented with this site plan regarding deviations from the application
plan does not cover all changes identified on site plan. Applicant and owner will need to work
with Long Range Planning to correct the status of the required variations.
Please contact Summer Frederick at the Department of Community Development 296 -5832 ext. 3565
for further information.