A. Final Site Plan
Camelot Pump Station [SDP200900096, WP0200900066]
Charles Luck, P.E. [cluck @wrallp.com]
HMC Holdings LLC
24 November 2009
23 December 2009
John P. Diez — Engineering Technician
1. Please provide a benchmark location, elevation, and datum for topography. An existing utility or
other known position will suffice.
2. Please provide FEMA map and date references labeled for FEMA floodplains.
3. All slopes 25% and over (critical slopes by County Zoning Ordinance) must be shaded.
[18- 32.6.6] Critical slope disturbance will be considered exempt per 18- 4.2.6.c unless the
unnecessary construction entrance south of the new appurtenances are to remain.
4. Proposed slopes steeper than 3:1 must have low maintenance (not grass) ground cover specified on
the plan. Examples of acceptable groundcovers can be found in Table 3.37C of the VESCH.
5. Please provide all offsite temporary and permanent easements necessary to construct the site as
proposed. Temporary easements (for construction) can be in the form of letters or emails from the
property owner. To assist county review in determining where all easements are needed, please
show existing easement lines on the plan with references to deed book and page numbers.
B. Erosion and Sediment Control Plan
1. Please include the inlet protection in the limits of disturbance. Please also include the work within
the VDOT ROW as part of the limits of disturbance.
2. Please provide dust control (DC).
3. Please provide a construction entrance to the offsite portion of the site on the West side of US -29.
4. Please remove the construction entrance south of the proposed site.
5. Clean water diversions are not a state standard. If the applicant wishes to divert offsite water
around the construction site, a riprap or sod V -ditch with be necessary.
6. Please remove the silt fence outlet protections.
7. Silt fence must be placed parallel to contour lines wherever possible. For instance, east of the
larger WWTP basin, at least 100ft of silt fence can be provided along a contour line.
8. All diversions should be removed from the plan. In their place, please provide silt fence parallel to
contour lines wherever possible.
9. Additional comments may be required based on enforcement of adjacent parcel earthwork
currently underway.
Once these comments have been addressed, please submit two (2) copies of the revised plans, calculations,
and narratives to Current Development Engineering.
Albemarle County Community Development
Engineering Review Comments
Page 2 of 2
Current Development Engineering is available from 2:30pm — 4:00pm on Thursdays to discuss these
review comments. Please contact Amy Pflaum at 434 - 296 -5832 or apflaum @albemarle.org to schedule an