Good morning,
Engineering has received the last submittal of the SWM plans for South Plains Presbyterian Church (WPO- 2009 - 00050).
All comments regarding the SWM plan have been addressed and the SWM plan is hereby approved pending site plan
approval. (The ESC plan had previously been approved —see below.) Now that the WPO plan has been approved,
Engineering review has no objection to the approval of the site plan.
The WPO bond amounts remain the same. The ESC bond has been computed to be $8,800. The SWM bond has been
computed to be $3,600. The forms and instructions to post the Water Protection Ordinance Bond can be found on
the Community Development Department Web site on www.albemarle.org. You may contact Ana Kilmer (Albemarle
County Department of Community Development) at ext. 3246 for further information on bonding procedures.
Once the site plan is approved by the planner and the WPO bonds posted, the applicant may schedule a pre- construction
meeting with the Erosion and Sediment Control Inspector.
Please contact me if you have any questions.
Thanks,
Phil
296 -5832 x3072
From: Philip Custer
Sent: Monday, February 22, 2010 9:55 AM
To: Gregory Solis; 'Gathright, Clark'
Cc: Elizabeth Marotta
Subject: Engineering review of South Plains Presbyterian Church (WPO- 2009 - 00050)
Good morning,
Engineering has received the last submittal of the ESC and SWM plans for South Plains Presbyterian Church (WPO -2009-
00050). All comments regarding the ESC plan have been addressed and the ESC plan is hereby approved pending site
plan approval. The SWM plan can be approved after the following minor changes are made:
- Increase the footprint of the infiltration trench by 18% and update the infiltration calculations with the data
from the soil tests (the impervious area draining to this facility is 7247sf, not 6140sf). Also, the callout on sheet
C3.1 specifies a footprint of 160sf and should be corrected.
- Label the set on the Cover Sheet as Erosion and Sediment Control and Stormwater Management Plans
- The professional seal must be signed and dated.
- Remove the soil test note on the infiltration trench detail on sheet 3.2 (this is only a recommendation because
another soil test is not required)
Once these changes have been made, please submit 5 copies of the plans for approval. Another $300 review fee is not
warranted.
The ESC bond has been computed to be $8,800. The SWM bond has been computed to be $3,600. The forms and
instructions to post the Water Protection Ordinance Bond can be found on the Community Development Department Web
site on www.albemarle.org. You may contact Ana Kilmer (Albemarle County Department of Community Development) at
ext. 3246 for further information on bonding procedures.
Once the SWM plans have been officially approved, the site plan signed by the planner, and the WPO bonds posted, the
applicant may schedule a pre- construction meeting with the Erosion and Sediment Control Inspector.
Please contact me if you have any questions.
Thanks,
Phil