HomeMy WebLinkAboutWPO200900065 Review Comments Stormwater Management Plan 2010-06-04OF ALg
a®
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: The Reserve (Belvedere Block 2) [WPO- 2009 - 00065]
Plan preparer: Mr. Scott Collins, PE; Collins Engineering
Owner: Mr. Robert Hauser and Stan Manoogian; Belvedere Station Land Trust
Developer: Mr. Todd Dofflemeyer; Cathcart Properties
Plan received date: 23 November 2009
(Rev. 1) 18 February 2010
(Rev. 2) 23 April 2010
Date of comments: 8 January 2010
(Rev. 1) 2 April 2010
(Rev. 2) 4 June 2010
Reviewer: Phil Custer
The second revision to the ESC and SWM plans for the The Reserve (Belvedere Block 2), received on 23
April 2010, have been reviewed. Comments for these plans are provided in this letter. The review of the
site and road plans has been provided in a separate comment letter.
C. Stormwater Management Plan [WPO- 2009 - 00065]
1. Belvedere Blvd. from Sta. 29 +00 to Sta. 47 +50 should be captured by the SWM facility.
Currently, the whole road is not shown within the drainage area. Additionally, the cut sideslopes
adjacent to the road also eventually drain to the Belvedere Blvd. drainage system and should be
included in the facility's drainage area. [17- 312.C]
(Rev. 1) The drainage area from Sta. 29 +00 to Sta. 32 +00 is shown correctly, but only a fraction
of the drainage area west of Belvedere Blvd. from Sta. 32 +00 to Sta. 43 +00 drains to the facility.
The drainage map on DP -I appears to be a closer approximation of the drainage area. By my
calculations, the drainage area shown on Sheet SWM -1 west of the Belvedere Blvd. curbline is
4.60 acres. Of this area, only 1.I0acres drains to the stormwater facility. Please update all
calculations accordingly.
(Rev. 2) Comment has been addressed.
2. Please run roof drainages from the eastern half of Building 6 to the stormwater structure in the
southeast corner of the parking lot and adjust all drainage and SWM computations accordingly.
[17- 312.C]
(Rev. I) Comment has been addressed.
3. Please provide a modified simple spreadsheet for the pond. In the table, include all grassed or
landscaped areas on the plan as "lawn ". The pre - development impervious area for the project
should be zero because the site was forested before clearing.
(Rev. 1) The spreadsheet must be updated to match the drainage area per comment #1. The
drainage area in the table is based off of the pre- development area. This update should not affect
the Water Quality Volume used to check the volume of the facility, only the RR required of the
development.
(Rev. 2) Comment has been addressed.
4. The pre - development rates for the 2 and 10 year storm that must be met for this pond should
consider the whole watershed to be forested. Because 90% of the soils onsite are type C, the pre -
development curve number is 70. The time of concentration used for the pre - development
condition of 0.2 hours is acceptable. The pre - development area of 19.58acres is also acceptable.
(Rev. 1) Considering comment 1 and the tc provided by the applicant (0.33hr), the 2 and 10 year
pre- development rates that I calculated are 19.8cfs and 46.4cfs, respectively. Please confirm in
calculations submitted with the next revision.
(Rev. 2) Comment has been addressed.
5. The volume of the pond must not consider any contour below a depth of 6ft. [VSMH]
(Rev. 1) The volume of the pond is not large enough. The Water Quality spreadsheet on sheet
SWM -I calculates a Water Quality Volume of 869.2cy from the impervious areas provided by the
applicant. This water quality volume requires a pond with a volume of 3477 cy to treat at 65%
(with an aquatic bench). The input data from the routing software shows that from 393 to 399, the
volume of the pond is only 3158.7cy.
Also, the contours are mislabeled in the forebay.
(Rev. 2) Engineering review will allow the slight undersizing of the wet volume within the pond
because the addition of the extended detention orifice.
6. The 1, 2, 10, and 100 year 24 -hour storms are 3.5in., 3.7in., 5.6in., and 9.1in. Please adjust all
calculations accordingly. [DM]
(Rev. 1) Comment has been addressed.
7. The slope of the Stormwater access path is greater than 20% measured between many contours.
Please adjust the slope so that no portion of the access road is steeper than 20 %. [DM]
(Rev. 1) Comment has been addressed.
8. Detention calculations must be provided for 2 and the 10 year storms, not 1 and 2. Also, please
provide all of the input and output basinflow data on the plan. (see below)
(Rev. 1) The 2 and 10 year storms have been routed and the basinflow data has been provided.
9. Please provide a stage /discharge curve for the proposed concrete anti - vortex trashrack so the
routings can be independently checked. If you are proposing to use the Hanson Anti - vortex top, I
have a copy of that stage discharge curve already and will use it in the routing.
(Rev. 1) The applicant is proposing a riser top with a stage- discharge relationship the county
already has on record. The routing should be updated to replace the 30" weir top with the 36"
Hanson Antivortex Device. Please contact me if you are having problems setting up the file.
(Rev. 2) Comment has been addressed.
10. Please provide a typical 10'x10' planting detail for the aquatic bench. The aquatic bench must
have at least three species of aquatic plants. [DM]
(Rev. 1) I do not think most of the proposed plants are appropriate for use in an aquatic bench.
Arrowwood viburnun is the only proposed plant specified for Zone 2 in Figure 3.05 -4 of the
VSMH. Please propose an even distribution of at least two other species for plants specified for
Zone 2 of the VSMH, or a similar source.
(Rev. 2) Comment has been addressed.
11. Use a post - development CN of at least 90 (VSMH- Townhouse /Condominiums) or else provide a
detailed curve number calculation. The current calculation in the plan is for the rational method
coefficients while the routing is performed using the SCS method.
(Rev. 1) Calculations have been provided. However, the curve number calculation will need to
be updated per comment 1. Using the adjusted data from TR -55 worksheet for post- development
drainage areal, I found the CN to be 86.6 [CN = 74 *(7.08121.79) + 98 *(11.93121.79) +
70 *(2.78/21.79) = 86.61
The time of concentration used in the routing has doubled. In the routing, use a time of
concentration that matches the design calculations for the pipe systems (0.18 hours)
With the above changes, I anticipate that the BMP will meet detention requirements (2 and 10
year routed flows of 14.9 and 17.2). However, I noticed that if the top was raised to 402.5, the
output of the 2 -year storm would be reduced to 8.33 with only an increase of the 10 -year storm to
17.6. This may be beneficial to the applicant when analyzing the downstream channel.
(Rev. 2) Comment has been addressed.
12. Please use an orifice coefficient of 0.6 in the routing.
(Rev. 1) Comment has been addressed.
13. The emergency spillway must either be relocated so it is placed on existing grade or armoring
needs to be provided. Engineering review recommends that the spillway be moved 130ft to the
west along the embankment so that it is close to existing grade with only a short flow path to the
stream. If the general location of the embankment is to remain in its current location a private
drainage easement will be needed on the downstream property.
(Rev. 1) Comment has been addressed.
14. A SWM facility maintenance agreement will need to be recorded before the site plan can be
approved. Please submit this document with $17 fee directly to Ana Kilmer after consulting the
guidelines available on the county website.
(Rev. 1) Comment has not been addressed.
(Rev. 2) Comment has not been addressed.
15. The SWM portion of the WPO bond will be calculated at the time of plan approval.
(Rev. 1) Comment remains unchanged.
(Rev. 2) The SWM portion of the WPO bond will be computed at a later date.
16. (Rev. 1) This facility is a Type III retention basin, not Type II. Pleaac 11tu" yj all incorrect
references.
(Rev. 2) Comment has been addressed.
17. (Rev. 1) The upstream slope of the embankment is graded at 2:1 but is labeled on the plan and in
the detail as 3:1. Please correct this discrepancy.
(Rev. 2) Comment has been addressed.
D. Erosion and Sediment Control Plan [WPO- 2009 - 00065]
1. Th ag prc n the L _plan has been placed at the preservation line
which is not congruent with the Code of Development. The Code of Development requires the
tree protection fencing to be placed "no closer than the dripline of any tree growing inside the
preservation areas." If a tree survey stamped and signed by a licensed surveyor is not provided,
place the tree protection fencing 20ft off the tree preservation line of the approved application
plan. The fence must also be called out as chainlink and not orange construction fence. (pg. 28
COD)
(Rev. 1) A dripline has been shown. County inspection will confirm in the field that tree
protection fencing is placed at the correct locations.
2. Belvedere Blvd. from Sta. 29 +00 to Sta. 47 +50 should be captured by the ESC facility.
Currently, the whole road is not shown within the drainage area. Additionally, the cut sideslopes
adjacent to the road also eventually drain to the Belvedere Blvd. drainage system and should be
included in the facility's drainage area.
(Rev. 1) The drainage area for the facility as shown is adequate.
3. A metal anti - vortex device is being proposed in the SB -1 detail. The concrete anti - vortex device
seems to work for both ESC and Stormwater and engineering review recommends that it be used
for both so the ESC to SWM facility retrofit is simpler.
(Rev. 1) The riser for the ESC facility will be used for the permanent SWM facility.
4. Based on comment 2, the drainage area to this sediment basin may increase slightly and the
dewatering orifice elevation may need to be raised. Engineering review also recommends that
some of the excess volume in this facility be used in the wet volume for greater basin efficiency
and less frequent maintenance.
(Rev. 1) The sediment basin volume as designed is adequate.
5. Trap 1 appears to be unnecessary as long as the diversions to Existing Basin IB and Proposed
Basin 1 are provided. The facility may remain on the plan but can be removed in the field with
the authorization of the inspector.
(Rev. 1) Trap I has been removed.
6. In the January 6"' meeting between the applicant and the County, the drainage system from the
VDOT road was discussed and it is my understanding that a storm sewer will be provided north
of Flat Branch between the development and the stream. The construction of this line should
occur immediately after the construction of Sediment basin 1. The outfall of existing basin SBI
must be temporarily connected to this drainage system or an inlet with adequate headboard should
be provided at the basin's outfall so that the abnormal diversion as specified in detail on sheet
ESC -4 is not necessary (otherwise a variance to the county engineer should be provided). At the
same time the storm sewer is constructed, the diversion directing runoff to the basin should be
installed. Please call this out in the construction sequence.
(Rev. 1) There does not appear to be any sump provided downstream of inlet 82. A considerable
amount of discharge from the existing sediment basin will likely bypass the inlet without the sump
condition, especially if inlet protection is provided. It appears that grading offsite will be
necessary in order to provide this freeboard. I recommend proposing a temporary connection
from the outlet of the basin to structure 82 to reduce the amount of freeboard needed. Please
also place the diversion on the downhill side of the storm sewer line.
(Rev. 2) The diversion was not placed downhill of the drainage pipe and in some cases is
shown on fill at the foot of the wall. The addition of the new trail also complicates this corner
of the site.
The temporary pipe from the existing basin outlet to the VDOT drainage system will work until
the basin has to be removed to construct the pool, clubhouse, and retaining walls. During this
time, this inlet will be responsible for the entire drainage area, since the diversion cannot be
constructed with positive drainage to the basin because of existing topography. A greater sump
must be provided for inlet 82. It looks as though the hill needed to provide the necessary sump
can be used as the location of the permanent trail when finished so that another bridge is not
necessary.
7. The dewatering orifice must be sized using the height and volume required for the dry storage,
not the volume provided. Calculating the required orifice diameter with the current proposed
dimensions of the dry volume results in an oversized orifice and substandard basin efficiency.
Please provide this calculation as outlined on pages III -107 and III -108 of the VESCH with the
next submittal.
(Rev. 1) The dewatering orifice calculations are correct. However, final results must be rounded
down rather than up. Please specify an 8" diameter orifice with a 10" flexible pipe.
(Rev. 2) Comment has been addressed.
8. Mention in the narrative that any offsite property used for cut disposal or fill acquisition must
have an approved erosion and sediment control plan.
(Rev. 1) Comment has been addressed.
9. Please provide a copy of the temporary construction easement negotiated with the property to the
south referred to in the ESC narrative. An easement on the property to the north is also
necessary.
(Rev. 1) The permanent off site easements must be recorded prior to the approval of the site plan.
The temporary construction easements should be graphically shown on the same documents of
the permanent easements when possible.
(Rev. 2) Comment has not been addressed.
10. A properly sized channel from the outlet of the pond to the stream is needed. Provide this
channel cross - section and a calculation of the 2 and 10 year storms in the resubmittal. [MS -19]
(Rev. 1) The design of the basin outlet does not appear to be adequate. The exit velocity of the
barrel(—] 7fps) will likely displace the 6" diameter riprap outlet protection. This is especially a
concern because the slope of the outlet is close to 25% [ (386- 380)124 J. Please reevaluate the
stone size at the outlet (use Plate 3.19 -3 from the VESCH). The 3.75ft bottom width should be
maintained and not widened as the riprap approaches the stream. Engineering review
recommends dropping the invert out of the pipe so that a flatter channel with less energy is
created as it enters the stream. A drop in the invert out would also require a drop in the invert in
of the barrel so that the outlet velocity can be kept at an acceptable level ( <15fps).
(Rev. 2) Comment has been addressed.
11. Engineering review does not agree with the applicant's conclusion in the adequate channel
analysis. Please see the list below for the county's comments and expectations of the analysis.
a. The channel analysis seems to be missing graphics of the cross - sections for each of the
three chosen locations of analysis. I also could not find any accompanying calculations
with these cross - sections either. For each channel cross - section segment, please provide
a separate n- value, permissible velocity (Table 5 -22), and computed velocity. A uniform
n- value, permissible velocity, and computed velocity should not be used in the
calculations. Water flowing within the banks of the channel flows much quicker than the
water that flows above the banks.
(Rev. 1) Comment has not been addressed. The downstream channel analysis and any
proposed improvements must be approved with the ESC plan prior to site plan approval.
(Rev. 2) An analysis of the sharp, eroding bend in the stream channel was not included
in the calculations and is necessary. This cross - section should use sinuosity reductions
to the Mannings coefficient and permissible velocity.
b. The hydrology and peak discharges to the channel cross - sections do not appear to be
accurate. After looking at a printout from the county's GIS system, it appears the
drainage area to sections A, B, and C is close to 95 acres. The drainage area appears to
be bounded by Rio Road (between Huntington Road and Chapel Hill Road), a ridge 500ft
north of Wakefield Rd, and approximately Free State Road.
(Rev. 1) The watershed has been shown correctly, but the time of concentration of the
watershed is not accurately estimated. If the applicant wishes to model the effect of the
upstream culvert, a separate hydrograph will need to be generated and added to the two
other hydrographs (from the Block 2 pond and the remainder of the watershed) with an
appropriate lag time. Please contact me to discuss this further.
(Rev. 2) The method of adding the three hydrographs is acceptable. However, the
curve number of 70 used for watersheds 2 and 3 seemed too low considering the fact
that C soils make up the overwhelming majority of these drainage areas. Please
provide the composite CN calculations using the soil information and Table 4 -6 in the
VSMH.
c. The soils in the area of the stream analysis are 39B, Hazel Loam, and 95, Wehadkee Silt
Loam. The permissible velocities for each segment of the stream cross - section should be
adjusted accordingly. Some segments of channel cross - sections are Cobbles and Shingles
(bottom), Graded- Loam to Cobbles(bottom), Ordinary Firm Loam, Silt Loam, as well as
Alluvial Silts.
(Rev. 1) Comment has not been addressed. The downstream channel analysis and any
proposed improvements must be approved with the ESC plan prior to site plan approval.
(Rev. 2) Manning's values for adequate channel calculations should be compiled from
Tables 5 -16, 5 -17, 5 -18, 5 -19, 5 -20, and 5 -21 of the VESCH. Table 5 -22 lists the
permissible velocities for Silt Loam and Graded -Loam to Cobbles as 3.Ofps and 5.0
respectively. Each segment of the cross - section should be classified as one of the soil
types listed in Table 5 -22. Please update the adequate channel analysis accordingly
where silt loam banks or Graded, Loam to Cobble bottoms are encountered.
d. For the portion of the stream adjacent to the pond and downstream of the outlet, please
remove all non - natural debris. There are several sections of old pipe obstructing stream
flow.
(Rev. 2) Comment has been addressed.
e. State guidance stresses that adequate channel analyses should be provided downstream
until the developed site is 1% of the total drainage area. In this project's case, please
provide an analysis up to and including the culvert to Shepherd's Ridge Rd. The
locations of the analyzed cross - sections should be areas with high erosion concerns
(bends or changes in cross - section).
(Rev. 1) Comment has not been addressed. The downstream channel analysis and any
proposed improvements must be approved with the ESC plan prior to site plan approval.
(Rev. 2) The calculations provided analyzed a 72" culvert when the narrative described
it as a 60" culvert. Please update the calculations. The culvert only needs to be
analyzed with the 10 -year storm.
The photograph and cross - section for Point D appears to be incorrect. The photo
appears to have been taken closer to Point B. Please provide a new cross - section and
calculation for Point D.
f. The volume and peak discharge to the channel on TMP 62F -F from Block 2 will both be
reduced with development. Therefore, adequate channel regulations do not apply to the
reach north of the Shepherd's Ridge pond.
g. (Rev. 2) The slope of the stream channel as surveyed is steeper than the slope used in
the calculation. Please use slopes more consistent with the survey in the calculations.
Engineering review recommends moving the location of the facility outlet 120ft farther
downstream so less analysis of the channel is required and so that the new channel from the
facility will enter the stream at a more natural angle, rather than perpendicular. (However, this
would require a permanent private drainage easement to the stream on the adjacent property.)
After walking the channel from the Shepherd's Ridge Rd. culvert to the outfall of the basin, I
found several locations where erosion appeared to be occurring rapidly, particularly west of the
confluence of the two channels from the ponds from the Shepherd Ridge Development and Block
1. Engineering review recommends providing a detailed streambank restoration plan to help with
proving the adequacy of this channel by providing greater bank stabilization and more erosion
tolerant cross - sections.
(Rev. 1) Comment remains unchanged, though engineering review acknowledges that the outlet
has been altered to provide a more natural convergence with the stream.
(Rev. 2) No improvements have been proposed.
12. The ESC portion of the WPO bond will be calculated at the time of plan approval.
(Rev. 1) Comment remains unchanged.
(Rev. 2) The ESC portion of the WPO bond will be computed at a later date.
13. (Rev. 2) The basin detail specifies the barrel as CMP while the SWMplan refers to the pipes as
RCP. Please clarify.
14. (Rev. 2) The plan needs to show the grading for the trail construction and all grading
associated with the trail construction. ESC measures for the trail construction will also be
needed. Silt fence will likely not be appropriate in many locations at the bottom of fill in areas
where water concentrates.