Loading...
HomeMy WebLinkAboutWPO201000021 Review Comments Bond Estimate 2010-05-21BOND ESTIMATE - EROSION CONTROL PROJECT NAME: PROJECT NUMBER: DATE OF ESTIMATE ESTIMATE BY: BASED ON: Fontaine Dam Repair W PO201000021 05/21/10 MRG Approved plan WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 0.2 1500 300 SILT FENCE LF 0 5 0 SAFETY FENCE LF 0 3 0 TEMPORARY FILL DIVERSION LF 0 3 0 DIVERSION DIKE LF 0 3 0 TEMPORARY SLOPE DRAIN LF 0 20 0 SEDIMENT TRAP 1 ACRES 0 1000 0 SEDIMENT BASIN 1 ACRES 0 1000 0 CULVERT INLET PROTECTION EA 0 500 0 INLET PROTECTION EA 0 200 0 OUTLET PROTECTION EA 0 200 0 EC -2 & 3 DITCH PROTECTION LF 0 10 0 RIP -RAP Cu.Yd. 267 55 14685 CHECK DAMS SQ.YD. 0 30 0 PAVED CONSTRUCTION ENTRANCE EA 1 2000 2000 subtotal 16985.00 project management 2547.75 subtotal 19532.75 CONTINGENCY LS 10% 1953.28 TOTAL 21486.03 BOND AMOUNT REQUIRED 21500.00 last revised:12 -5 -01