From: DeNunzio, Joel D., P.E. [ Joel .DeNunzio @VDOT.virginia.gov]
Sent: Tuesday, July 13, 2010 9:18 AM
To: Megan Yaniglos
Subject: RE: SDP - 2010 -00039 Holiday Inn Express - Preliminary Sight Plan
Megan,
You can say "Final approval is subject to the requirement that the entrance to proposed state maintained roads shall be in
accordance with Appendix F, Access Management Design Standards for Entrances and Intersections, of the VDOT Road
Design Manual.
Thanks
Joel
Joel DeNunzio, P.E.
Staff Engineer
434 - 293 -0011 Ext. 120
ioel.denunzio@vdot.viroinia.gov
From: Megan Yaniglos [mailto:myaniglos @albemarle.org]
Sent: Tuesday, July 13, 2010 9:12 AM
To: DeNunzio, Joel D., P.E.
Subject: RE: SDP - 2010 -00039 Holiday Inn Express - Preliminary Sight Plan
Thanks Joel. Do you have any language that you would like me to use for the final site plan conditions of approval? I am
writing the preliminary approval letter that includes what they will need to be address before final approval is given from
each agency. I will use this comment as one of the conditions for approval, but do you have general language for final
approval? something like, "final approval subject to VDOT regulations "?
Thanks.
megan Yaniglos
senior planner
Albemarle County Community Development Department
Division of Current Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902
ph: 434.296.5832 x. 3004
fax: 434.972.4126
From: DeNunzio, Joel D., P.E. [ mailto:J oel.DeNunzio @VDOT.virginia.gov]
Sent: Tuesday, July 13, 2010 9:07 AM
To: Megan Yaniglos
Subject: SDP - 2010 -00039 Holiday Inn Express - Preliminary Sight Plan
Megan,
I have reviewed the subject site plan and have the following comment:
• The canopies of the proposed Clethra Almifolia along the existing sight line easement may restrict the sight lines
once it grows above 2.5 feet and the sight easement runs along the proposed curb for 70 or 80 feet. These shrubs should
not be placed on the sight easement or at a location where they will eventually grow into the sight easement.
Please let me know if you have any questions.