Loading...
HomeMy WebLinkAboutSDP200900081 Review Comments Letter of Revision 2 2010-08-19Philip Custer From: Philip Custer Sent: Thursday, August 19, 2010 5:16 PM To: Elizabeth Marotta Cc: Ray Lilly Subject: Engineering review of Second Letter of Revision for the Waldorf School (SDP- 2009 - 00081) Elizabeth, I have reviewed the second Letter of Revision for the Waldorf School Site plan that relocates the biofilter farther downhill and reintroduces the cistern, though at a different corner of the building. At this time, I have no objection to the proposed change. But, the applicant should be informed that the new location of the biofilter is an area of the site that was delineated as a "Future Phase" on SP- 2006 - 00010. The new location of the biofilter may complicate the review of the future development in the area to some degree. The change is also not substantive with regard to the Stormwater Management on site. The footprint of the facility is the same size and all of the other approved characteristics of the facility remain as approved: section detail of the facility, planting plan, depth from the bed to the top of dam as 1.5ft, etc. The excess copies of the plan that I have will be distributed to the water resource inspectors. The bond amount does not need to be updated. Please let me know if you have any questions. Thanks, Phil X3072