HomeMy WebLinkAboutSDP201000083 Review Comments Final Site Plan and Comps. 2010-12-17Megan Yaniglos
From: DeNunzio, Joel D., P.E. [ Joel .DeNunzio @VDOT.virginia.gov]
Sent: Friday, December 17, 2010 1:29 PM
To: Megan Yaniglos
Cc: Philip Custer
Subject: National College final site plan - SDP - 2010 -00083
National College final site plan - SDP - 2010 -00083
Megan,
I have reviewed the National College plan and have the following comments:
1. Pavement widening must be constructed in accordance with standard WP -2. The pavement section along Route 29
will likely require a thicker section than what is proposed and will be determined in the Land Use Permit application. A
note should be added to the plan that the pavement will be in accordance with the permit.
2. The general layout that needs to be followed for the turn lane extension and entrance needs to be in accordance
with the VDOT Road Design Manual Appendix F page F -98. The following items in the plan need to be adjusted as
shown in the diagram:
a. Curb and gutter CG -7 must be used and the minimum offset from the existing edge of lane shall be 12 feet along the
entire frontage.
b. The proposed CG -7 must tie into the existing radial CG to the northern entrance.
C. A new drainage structure may be needed.
d. Show all entrance dimensions in accordance with the drawing on F -98.
e. Add the 48 foot taper to the south of the proposed right our from the fabric store.
3. A pavement striping detail needs to be shown.
An entrance profile needs to be shown.
Show drainage calculations on proposed DI along Route 29.
Show dimensions of right out in accordance with page F -90 of the VDOT Road Design Manual.
Please let me know if you have any questions.
Thanks
Joel
Joel DeNunzio, P.E.
VDOT Culpeper
Land Development
434 - 589 -5871
ioel .denunzioCabvdot.virainia.00v